The short answer

The defects liability period (DLP), called the maintenance period in SIA contracts, is the window after completion in which the contractor must return and fix defects. Retention is typically released half at completion and half when the DLP ends. Later defects can still be claimed: generally within 6 years, or for negligence 3 years from knowledge, subject to a 15-year long-stop.

Every construction contract ends twice. The first ending is practical completion, when the owner takes the space back and starts using it. The second ending comes months later, when the defects liability period (DLP) expires, the last of the retention money is released, and the final account is signed off. Most disputes about defects and money happen in the gap between those two dates, usually because nobody wrote down what was supposed to happen in it.

This guide explains how the DLP works under the main Singapore contract forms, how retention money is held and released, what the final account is, and what happens when a defect shows up after the DLP has ended. It is written for owners, managing agents, facility managers and fit-out managers, and for contractors who want their retention back on time. The rules on limitation periods are taken directly from the Limitation Act 1959; the contract mechanics come from the Public Sector Standard Conditions of Contract (PSSCOC) 2020 and from Singapore court decisions on Singapore Institute of Architects (SIA) contracts.

A note on scope: if you bought a new home from a developer, the DLP comes from the prescribed Sale and Purchase Agreement, not from a building contract. That regime is covered in the companion guide on defects in a newly completed property.

What the defects liability period is, and what it is not

The DLP is a fixed period after completion during which the contractor must come back and make good defects that appear, at its own cost. Different forms use different names:

  • The PSSCOC (the government’s standard conditions, 8th edition July 2020) uses “Defects Liability Period” and defines it by reference to the Appendix, where the length is filled in for each contract.2
  • The SIA building contract uses “Maintenance Period”. In Eltraco International v CGH Development, the Court of Appeal described an SIA contract whose clause 27 provided a 12-month maintenance period, extendable by 6 months for certain recurring defects.4
  • The prescribed developer Sale and Purchase Agreement for strata homes uses a 12-month “defects liability period”.10

Under the PSSCOC, the contractor must complete outstanding work and carry out “amendment, reconstruction and remedying defects” that the Superintending Officer instructs during the DLP or within 14 days after it expires (cl 18.1).2 That 14-day tail matters: a defect inspected on the last day of the DLP can still be instructed shortly afterwards.

Two things the DLP does

  1. It obliges the contractor to return. The contractor must fix notified defects at its own cost if they result from defective work, from its design (where it designed), or from any other breach (PSSCOC cl 18.2).2
  2. It gives the contractor a right to fix its own work. The owner normally cannot ignore the contractor, appoint someone else and send the bill without first giving the contractor the notice and opportunity the contract requires.

One thing it does not do

The DLP is not normally a cap on liability. The PSSCOC says so expressly in clause 18.5.

PSSCOC 2020, clause 18.5 and the High Court in Thio Keng Thay v Sandy Island

The PSSCOC states that the defects clauses “shall not derogate in any way whatsoever from the Contractor’s liability” at common law for defective work.2 The High Court took the same view of a developer’s defects clause in Thio Keng Thay v Sandy Island Pte Ltd [2019] SGHC 175: without express contrary wording, a defects liability clause does not extinguish the right to recover damages at common law. The court also found that the owner had breached the clause by unreasonably rejecting the developer’s rectification proposals, and treated that as relevant to the amount recoverable, applying the principle that an owner cannot recover more than it would have cost the defaulting party to remedy the defects.6

The practical lesson from Thio runs in both directions. Owners keep their right to damages after the DLP, but an owner who shuts the contractor out of rectification during the DLP may find the recoverable amount reduced.

When the DLP starts

The DLP normally starts on the completion date certified under the contract.

Contract form Completion event What starts Source
PSSCOC 2020 Certificate of Substantial Completion; the Superintending Officer responds within 21 days of the contractor’s notice and undertaking (cl 17.1) DLP; contractor’s licence to occupy the site ends, with re-entry allowed for defects (cl 17.2) 2
SIA (9th ed, 2010, as discussed by the Court of Appeal) Completion Certificate (cl 24(4)) Maintenance Period (cl 27(1)); release of first half of retention (cl 31(9)); final accounts process (cl 31(11)) 3
Developer SPA, Form 5 Earlier of actual vacant possession, or the 15th day after the buyer receives TOP/CSC and the completion notice 12-month DLP (cl 17.1) 10
Typical small private contract Whatever the contract says; often a handover or joint inspection date Whatever the contract says Your contract

Two practical points follow.

Sectional completion. The PSSCOC allows substantial completion to be certified for a phase or part of the works, including parts the employer occupies early (cl 17.3).2 Each part can then have its own DLP, and the PSSCOC’s final certificate waits for the latest of them (cl 34.1). On a staged office fit-out, write down which areas were handed over on which date.

Outstanding works. Completion is rarely perfect. Under the PSSCOC, the contractor applying for completion gives an undertaking to finish outstanding work during the DLP (cl 17.1).2 In the SIA mechanism discussed in Ser Kim Koi v GTMS Construction, the architect may hold back a reasonable sum to cover the cost of outstanding work when releasing retention at completion.3 Either way, the outstanding-works list should be agreed in writing at handover.

In Ser Kim Koi, the Court of Appeal held that a Completion Certificate not issued in accordance with the contract lacked the effect the contract gave it, which affected the maintenance period dates and the liquidated damages position.3 Completion certificates are not formalities.

Retention money: how it works

Retention money (retention monies, retention sum) is a percentage of each progress payment that the owner keeps back as security for completion and defects. It is the contractor’s money, earned for work already done, held back until conditions are met.

SIA-type retention mechanics

Singapore court decisions on SIA-form contracts describe a consistent pattern, with the actual figures filled into the contract’s Appendix:

  • In Hsing Mei Construction v Lim Check Meng [2000] SGHC 75, interim payments were made at 90% of the gross certified value, so 10% of each certificate was retained, with the total retention limited to 5%. Half of the retention not yet paid was to be certified on completion, and the balance at the expiry of the Maintenance Period.5
  • In Eltraco International v CGH Development [2000] SGCA 51, a 1990 SIA contract allowed the employer to retain up to 5% of the contract sum; half was to be released on the completion certificate.4
  • In Ser Kim Koi v GTMS Construction [2016] SGCA 7, on the 9th edition (2010) SIA conditions, clause 31(9) required one-half of the retention not yet paid to be certified as due on completion, less a reasonable sum for outstanding work.3

These are examples from specific contracts, not a statutory rate. Nothing in Singapore law fixes the retention percentage for private works; the contract does.

5% of the contract sum: the retention limit in the SIA contract considered in Eltraco v CGH Development4

PSSCOC 2020: a security deposit instead of retention

The public-sector form works differently. PSSCOC 2020 has no standing retention on progress payments. Instead, within 14 days of the Letter of Acceptance (or a longer period in the Appendix), the contractor provides a security deposit of the amount stated in the Appendix, in cash or as a guarantee (cl 4.5). The employer can use it to make good loss from the contractor’s breach, including liquidated damages, and returns the unused balance without interest when the Final Completion Certificate is issued.2

The PSSCOC does keep a targeted retention power: if the contractor fails to submit an adequate programme, the Superintending Officer may certify that 10% of interim payments be retained until the programme is in order (cl 9.4).2

Illustrative example: how retention builds up

The table below uses SIA-type mechanics: 10% of each certified amount retained until retention reaches 5% of the contract sum. Illustrative figures for a S$200,000 fit-out; your contract’s percentages may differ.

Stage (Illustrative) Cumulative value certified Retention at 10% Retention cap (5% of S$200,000) Retention actually held
Month 1 S$50,000 S$5,000 S$10,000 S$5,000
Month 2 S$120,000 S$12,000 S$10,000 S$10,000 (cap reached)
Completion S$200,000 S$20,000 S$10,000 S$10,000
Release on completion (half) S$5,000 released, S$5,000 still held
End of DLP, defects made good S$5,000 released

The cap is why retention on a well-run project is usually a modest sum by completion. It is also why the second half matters to the contractor: on a small job, the last few thousand dollars can be most of the profit.

Release at completion and at the end of the DLP

How retention is typically released under SIA-type mechanics

  1. Completion is certified. The architect or contract administrator issues the completion certificate, with any outstanding-works list attached.
  2. First half released. Half of the retention not yet paid is certified as due, less a reasonable sum for outstanding work (SIA cl 31(9) as described in Ser Kim Koi).3
  3. DLP runs. The owner notifies defects in writing as they appear; the contractor returns and fixes them.
  4. End-of-DLP inspection. A joint inspection produces the final defects list. Under PSSCOC, instructions can still be issued within 14 days after the DLP expires (cl 18.1).2
  5. Defects made good. The contractor completes the list; the contract administrator confirms it.
  6. Final certificate and balance released. The balance of retention is certified at the end of the maintenance period (as in Hsing Mei), or, under PSSCOC, the Final Completion Certificate is issued within 30 days after the DLP expires or after the instructed work is done (cl 34.1), and the unused security deposit is returned.52

When the owner can keep retention

Retention is security, not a bonus. The owner can apply it against the cost of defects the contractor fails to fix after proper notice, and against other sums due under the contract. The PSSCOC illustrates the tools an owner can use:

  • If the contractor fails to comply with an instruction within 14 days, the employer may employ and pay others to do the work and recover the cost (cl 2.6).2
  • If urgent remedial work is needed during the DLP and the contractor cannot or will not do it at once, the Superintending Officer may have someone else do it (cl 2.7).2
  • If a defect is impracticable or inconvenient to fix, the Superintending Officer may instead assess the diminution in value of the works, which is recoverable from the contractor (cl 18.3).2

Holding the whole retention indefinitely because “there might be more defects” is not one of those tools. If the contract gives a release date and the conditions are met, the money is due.

Retention, payment claims and SOPA

The Building and Construction Industry Security of Payment Act 2004 (SOPA) applies to written construction contracts, but not to contracts for work on residential property that does not require approval from the Commissioner of Building Control (s 4(2)(a)).9 Where SOPA applies, the statutory payment-claim and payment-response timetable governs, and a respondent who withholds money must give reasons in a payment response. The PSSCOC builds this in: its final payment claim is expressly treated as a payment claim under the Act (cl 32.4(3)).2 Whether, when and how a retention release can be claimed depends on the contract and on how the claim is framed. Read the SOPA guide before serving or answering a claim that includes retention. If adjudication follows, the Singapore Mediation Centre’s application fee is S$654 including GST under its fee schedule from 1 August 2025.12

The final account

The final account settles what the contract is finally worth: the original contract sum adjusted for variations, remeasured quantities, provisional sums, loss and expense claims, and deductions such as liquidated damages. It is where disputes about variation orders and provisional sums and liquidated damages and extensions of time are finally priced.

The PSSCOC sets out a full timetable, which is a useful model even for private contracts:

Step (PSSCOC 2020) Deadline Clause
Contractor submits Final Payment Claim, with substantiation of all claims Within 90 days of the Date of Substantial Completion 32.4(1)–(2)
Superintending Officer issues Interim Final Account and payment certificate Within 21 days of the Final Payment Claim 32.5(1)(a)
If no Final Payment Claim is submitted, Superintending Officer issues Interim Final Account anyway Within 150 days of substantial completion 32.5(2)(a)
Superintending Officer provides draft Final Account Not later than 30 days after the end of the DLP 32.5(3)
Contractor accepts or submits grounds of dispute; undisputed amounts are deemed accepted Within 30 days of receiving the Final Account 32.5(4)
Superintending Officer amends, or says he will not Within 30 days of the contractor’s grounds 32.5(5)
Final Account Certificate issued Within 30 days of acceptance, or of the decision not to amend 32.5(6)
Corrections for errors Within 30 days of the Final Account Certificate or Final Completion Certificate, whichever is later 32.5(8)

Source for the whole table: PSSCOC 2020, clause 32.2

Three features deserve attention:

  • Claims not substantiated in time can be lost. Under clause 32.4(2), failing to substantiate a claim for an event before substantial completion bars the contractor from advancing it, subject to limited exceptions.2
  • Silence is acceptance. Amounts the contractor does not dispute within 30 days are deemed accepted and binding (cl 32.5(4)).2
  • The final account does not end defects liability. Issuing a Final Account Certificate before the Final Completion Certificate does not relieve the contractor of its DLP obligations (cl 32.5(9)), and no certificate is by itself conclusive that the work complies (cl 34.2).2

Under the SIA conditions, the Court of Appeal noted that the Completion Certificate also triggers the contractor’s obligation to submit its final accounts documents under clause 31(11).3 On small private jobs there is often no formal final account at all, only a “final invoice”. That is where disputes start: the contractor’s last invoice adds variations the owner never priced, and the owner deducts defects the contractor never saw.

Defects that appear after the DLP

The end of the DLP changes the procedure, not necessarily the liability. After it expires, the contractor is no longer obliged to return under the defects clause, and the owner can no longer insist on rectification in kind under that clause. But a defect that results from a breach of contract or negligence can still found a claim for damages, as Thio and PSSCOC clause 18.5 show.62 BCA makes the parallel point for new homes: a defect reported during the DLP stays the developer’s responsibility even if it is still unresolved when the period ends.11

The real constraint is time.

Limitation periods under the Limitation Act 1959

Claim Time limit Provision
Action founded on contract or tort (general rule) 6 years from the date the cause of action accrued s 6(1)(a)
Action to enforce an arbitration award 6 years from accrual s 6(1)(c)
Damages for negligence, nuisance or breach of duty (not personal injury), including a duty arising under a contract Later of: 6 years from accrual, or 3 years from the earliest date the claimant had the knowledge required and a right to sue s 24A(1), (3)
Overriding long-stop for actions under s 24A 15 years from the last act or omission alleged to be negligent, even if damage has not yet occurred s 24B
Contribution between wrongdoers (e.g. contractor against subcontractor) 2 years from when the right to contribution accrued s 6A
Debt or other liquidated sum (e.g. unpaid retention) acknowledged in writing or part-paid Time restarts from the acknowledgment or last payment s 26(2)
Fraud, or right of action concealed by fraud Time runs from when the fraud was or could reasonably have been discovered s 29(1)

Source: Limitation Act 1959, current version on Singapore Statutes Online.1 Section 24A(3) took its current wording on 1 April 2022.1

How these interact in a defects case:

  • Contract claims against the contractor are measured from when the cause of action accrued. As a general principle, a contractual cause of action accrues on breach rather than on discovery, so time can start running before anyone sees the defect. Take legal advice on the accrual date in your case.
  • Negligence claims accrue when damage occurs. For construction defects, the Appellate Division in MCST Plan No 4099 v KTP Consultants [2024] SGHC(A) 32 described this as the point when defects manifest as physical damage to the building.7
  • The knowledge limb gives 3 years from when the claimant knew, or could reasonably have found out with expert advice it would be reasonable to seek, that the damage was attributable to the defendant’s act or omission and who the defendant was. The required knowledge is “reasonable rather than absolute or certain”.78 In KTP, the court refused to strike out the MCST’s claim because it was arguable that the MCST learned of the engineer’s role only from a later expert report.7
  • The long-stop in s 24B is absolute for negligence claims: 15 years from the last negligent act or omission, regardless of discovery.1

Composite scenario: the leak that arrived in year three

A company fits out a ground-floor clinic with a new wet-area waterproofing system on a 12-month DLP. Practical completion is in March; the DLP passes with a short snag list, and the retention is released in full. In the third year, water stains appear in the unit below. The neighbour’s insurer writes to the clinic. Opening up shows the membrane was never lapped at the floor trap. The clinic now has to fund investigation, temporary closure of two treatment rooms, rectification and the neighbour’s ceiling repair. It has no retention left, the contractor has stopped trading, and the only records are a quotation and WhatsApp messages. The claim is still within time in principle, but there is no solvent defendant and little evidence of what was installed. This is a composite scenario, not a reported case.

The scenario shows why the DLP is a starting point and not the whole protection. A written specification, photographs of concealed work before it was covered, a test record (for example a ponding test) and a product warranty in the owner’s name would each have changed the outcome. See façade and water-leak diagnosis for how leaks are traced, and protecting yourself if your contractor goes bust for security beyond retention.

Practical tips for small A&A and fit-out contracts

Small addition and alteration (A&A) works and office or retail fit-outs are often done on a two-page quotation. That is where DLP and retention terms are most often missing. The fixes are cheap if made before signing.

Contract term Why it matters What to write in
DLP length and start trigger Without it, the contractor has no clear obligation to return A stated period and a start event, e.g. the date of a signed joint-inspection handover
Defect notification method Disputes often turn on whether notice was given Written notice to a named email address, with photographs, and a response time
Retention percentage, cap and release triggers The only security most small owners hold The percentage per payment, the maximum, and the two release events
Outstanding-works list at handover Separates unfinished work from defects A signed list with target dates, priced if possible
Owner’s right to use others Lets the owner act if the contractor does not Notice period, then the right to engage others and deduct reasonable cost
Final account timetable Stops open-ended variation claims Contractor submits the final account within a set number of days of completion
Warranties and as-builts Latent defects often surface after the DLP Product and installer warranties issued in the owner’s name; as-built drawings and test records at handover

Before you sign

  • Is the DLP length written down, and does everyone agree what event starts it?
  • Is the retention percentage, cap and release timing written down? For lump-sum payment structures without monthly valuations, is there another form of security instead?
  • Are concealed works (waterproofing, embedded pipes, fire-stopping) to be photographed or inspected before they are covered?
  • Who issues the completion certificate or signs the joint inspection: you, your consultant, or the landlord?
  • Is there a final account deadline, and a rule that late claims are not admissible?
  • If the works are residential and do not need Building Control approval, have you noted that SOPA will not apply, so payment disputes go to negotiation, mediation, the Small Claims Tribunals or the courts?9
  • Will you keep the contract, drawings, photographs, notices and payment records for at least the limitation periods above?

During the DLP

  • Report each defect in writing as soon as it appears, with date, location and photographs. Do not save them up for a final list.
  • Give the contractor reasonable access to inspect and fix. Refusing access can reduce what you can later recover, as the Thio decision shows.6
  • If a defect is urgent (active leak, electrical fault, falling hazard), say so, and keep a record of the time you notified and the response.
  • Before engaging another contractor, follow the contract’s notice steps and keep the quotation you relied on.
  • Diarise the DLP expiry date and book the end-of-DLP joint inspection at least a few weeks before it.
  • Do not alter or cover up defective work before it has been recorded, especially if it may become the subject of a claim.

For contractors: getting the retention back

  • Ask for the completion certificate or signed handover in writing; it starts the DLP and, under SIA-type terms, the first retention release.3
  • Respond to every defect notice in writing, with an attendance date. Silence is the most common reason owners hold retention.
  • Book the end-of-DLP inspection yourself, and send the closed-out defects list with photographs.
  • Submit the final account on time and with substantiation; under PSSCOC-style terms, late or unsubstantiated claims can be barred.2
  • If retention is acknowledged in writing as owing but unpaid, note that a written acknowledgment or part payment of a debt restarts the limitation clock (Limitation Act s 26(2)).1

Independent engineer's note

When a defect appears after the DLP and the cause is disputed (structural cracking, water ingress through a slab, failing fixings), the evidence that decides the claim is usually an engineer’s investigation. That report should come from a Professional Engineer appointed and paid by the owner, not by the contractor whose work is in question, so its conclusions are not open to challenge for lack of independence. RRD’s usual independent engineering partner is CVC Engineers, but owners can appoint any PE. See the independent-engineer model and when cracks need a PE.

How RRD approaches this

RRD’s quotations list the DLP, the payment and retention terms, and the cost-risk items before signing. Each job closes with a joint inspection and a signed handover list, which fixes the start of the DLP and separates outstanding work from defects. Defects notified during the DLP are logged with photographs and closed out in writing.

Choosing protection that fits the job size

Retention is only one tool. On larger contracts, owners also use performance bonds and security deposits; on small jobs, the simplest protection is a payment schedule that never runs ahead of work done. See verifying a contractor’s licences and red flags for payment-structure guidance and the true cost of choosing the cheapest quote for how defects and delay change the real price of a bid. For commercial tenants, end-of-lease works raise the same questions in reverse; see office reinstatement.

If a defect or retention dispute cannot be settled, the options range from mediation to the Small Claims Tribunals, SOPA adjudication, the State Courts and arbitration. The renovation and construction disputes guide compares them by claim size and type.

Summary

  • The DLP (SIA: maintenance period) is the period after completion in which the contractor must return to fix defects. Its length and start event come from the contract; reported SIA cases show 12 months.4
  • Under SIA-type terms, retention is typically 10% of each certificate up to a 5% cap, half released at completion and the balance at the end of the maintenance period.54 PSSCOC 2020 uses a security deposit instead, returned on the Final Completion Certificate.2
  • The final account settles the contract sum. PSSCOC 2020 requires the draft final account within 30 days after the DLP ends and treats undisputed amounts as accepted after 30 days.2
  • The DLP does not normally cap liability. Claims for later defects remain possible: 6 years in contract or tort, and in negligence the later of 6 years from damage or 3 years from knowledge, with a 15-year long-stop.1
  • For small A&A and fit-out contracts, write down the DLP, retention, notice method and final account timetable before signing, and keep the evidence for years.

Questions people ask

What is the difference between the defects liability period and the maintenance period?

In practice they mean the same thing: a fixed period after completion during which the contractor must return and make good defects at its own cost. The Public Sector Standard Conditions of Contract (PSSCOC) call it the Defects Liability Period and set its length in the Appendix. The SIA building contract calls it the Maintenance Period. Reported SIA cases show 12-month maintenance periods. Whatever the label, read your own contract for the length, the start date and how defects must be notified.

How much retention money is usually held in Singapore?

It depends on the contract, and the figure should be written into it. In reported cases on SIA-form contracts, the employer kept 10% of each interim certificate until retention reached a limit of 5% of the contract sum. Half was released at completion and the balance at the end of the maintenance period. The public-sector PSSCOC 2020 form takes a different approach: no standing retention, but a security deposit or guarantee of an amount set in the Appendix.

When should retention money be released?

Under SIA-type mechanics, half of the unpaid retention is certified on the Completion Certificate, less a reasonable sum for outstanding work, and the balance at the end of the maintenance period once defects are made good. Under PSSCOC 2020, the unused security deposit is returned when the Final Completion Certificate is issued. For small private contracts, write down the release dates and conditions, because the contract is the only source of the obligation.

Can I still claim for defects found after the defects liability period ends?

Usually, yes. The DLP is a period in which the contractor must return to fix defects. It is not normally a cap on liability. PSSCOC clause 18.5 says the defects clauses do not reduce the contractor's liability at common law, and the High Court in Thio Keng Thay v Sandy Island (2019) held that a defects clause does not remove the right to damages without express words. The claim must still be brought within the limitation period.

How long do I have to sue for a latent defect in Singapore?

A claim in contract or tort must generally be brought within 6 years of the cause of action accruing (Limitation Act s 6). For negligence and breach of duty, s 24A(3) allows the later of 6 years from accrual or 3 years from when the claimant knew enough to sue. Section 24B then bars negligence claims 15 years after the last negligent act or omission. Get legal advice early, because accrual dates are often disputed.

What is a final account in a construction contract?

The final account is the statement that settles the contract sum after all variations, provisional sums, claims and deductions such as liquidated damages. Under PSSCOC 2020, the contractor submits a final payment claim within 90 days of substantial completion, the Superintending Officer issues a draft final account within 30 days after the DLP ends, and a Final Account Certificate follows. Smaller private contracts should set a simpler timetable.

Can the owner fix defects using another contractor and deduct the cost?

Only after giving the original contractor the notice and chance the contract requires. PSSCOC lets the employer employ others and recover the cost if the contractor fails to comply with an instruction within 14 days. In Thio Keng Thay, an owner who unreasonably refused the developer's rectification proposals was held to have breached the defects clause, and the court treated this as relevant to how much could be recovered.

Does SOPA apply to claims for retention money?

The Security of Payment Act applies to written construction contracts, except contracts for residential property work that does not need approval from the Commissioner of Building Control. Where SOPA applies, payment claims and payment responses follow its strict timelines. How a retention release is claimed depends on the contract terms and how the claim is framed, so check both before serving a claim.

Sources

12 sources. Official sources are marked dark. Links were checked when this guide was last updated.

  1. sso.agc.gov.sgLimitation Act 1959 (current version), ss 6, 6A, 24A, 24B, 26 and 29. Singapore Statutes Online. https://sso.agc.gov.sg/Act/LA1959 (accessed Nov 2026) ↩↩↩↩↩
  2. isomer-user-content.by.gov.sgBuilding and Construction Authority — Public Sector Standard Conditions of Contract for Construction Works 2020 (8th edition, July 2020, with amendments), clauses 2.6, 2.7, 4.5, 9.4, 17, 18, 32 and 34. https://isomer-user-content.by.gov.sg/338/5349d125-0337-4dc3-a36d-623e599f2865/1-psscoc-for-construction-works-2020.pdf (accessed Nov 2026) ↩↩↩↩↩↩↩↩↩↩↩↩↩↩↩↩↩↩↩↩↩↩↩
  3. elitigation.sgSer Kim Koi v GTMS Construction Pte Ltd [2016] SGCA 7 (Court of Appeal), discussing SIA Lump Sum Conditions (9th ed, 2010), cll 24(4), 27(1), 31(9) and 31(11). https://www.elitigation.sg/gd/s/2016_SGCA_7 (accessed Nov 2026) ↩↩↩↩↩↩↩
  4. elitigation.sgEltraco International Pte Ltd v CGH Development Pte Ltd [2000] SGCA 51 (Court of Appeal), on the 1990 SIA Conditions. https://www.elitigation.sg/gd/s/2000_SGCA_51 (accessed Nov 2026) ↩↩↩↩↩
  5. elitigation.sgHsing Mei Construction Pte Ltd v Lim Check Meng [2000] SGHC 75 (High Court), on SIA-form contracts, cl 25(1). https://www.elitigation.sg/gd/s/2000_SGHC_75 (accessed Nov 2026) ↩↩↩
  6. elitigation.sgThio Keng Thay v Sandy Island Pte Ltd [2019] SGHC 175 (High Court). https://www.elitigation.sg/gd/s/2019_SGHC_175 (accessed Nov 2026) ↩↩↩
  7. elitigation.sgManagement Corporation Strata Title Plan No 4099 v KTP Consultants Pte Ltd [2024] SGHC(A) 32 (Appellate Division, 9 October 2024). https://www.elitigation.sg/gd/s/2024_SGHCA_32 (accessed Nov 2026) ↩↩↩
  8. scl.org.sgSociety of Construction Law (Singapore) — D Menon and N Tong (Rajah & Tann Singapore LLP), “Date of Damage or Discovery? Unravelling Section 24A of the Limitation Act 1959 (2020 Rev Ed)” (28 August 2025). https://scl.org.sg/public-resources/articles-menu/1056-date-of-damage-or-discovery-unravelling-section-24a-of-the-limitation-act-1959-2020-rev-ed.html (accessed Nov 2026) ↩
  9. sso.agc.gov.sgBuilding and Construction Industry Security of Payment Act 2004 (current version), s 4(2)(a). Singapore Statutes Online. https://sso.agc.gov.sg/Act/BCISPA2004 (accessed Nov 2026) ↩↩
  10. sso.agc.gov.sgHousing Developers Rules (R 1), rule 12 and First Schedule Form 5 (Sale and Purchase Agreement for strata units), cl 17. Singapore Statutes Online. https://sso.agc.gov.sg/SL/HDCLA1965-R1 (accessed Nov 2026) ↩↩
  11. bca.gov.sgBuilding and Construction Authority — “What to know as a condo owner”. https://www1.bca.gov.sg/home-and-building-owners/condo-strata/condo-living-be-condo-savvy/what-to-know-as-a-condo-owner/ (accessed Nov 2026) ↩
  12. mediation.com.sgSingapore Mediation Centre — “Building and Construction Industry Security of Payment Act Fee Schedule” (Annex E, 10th Edition, 1 August 2025). https://mediation.com.sg/wp-content/uploads/2025/08/SMC-Adjudication-Rules-Fee-Schedule-1-Aug-2025.pdf (accessed Nov 2026) ↩
Cite or link to this guide

Use this guide in a report, a tender or a by-law briefing. Please link to the page so readers get the current version.

RRD Engr & Constr. (2026). Defects Liability Period and Retention Money in Singapore: DLP, Maintenance Period, Final Account and Late Defects. RRD Field Guide. Updated 9 November 2026. https://rrd.sg/guides/defects-liability-period-retention-singapore/
Report a correction