Cheap quote vs delay simulator
Run 10,000 simulated projects to compare a cheaper quote with a higher one, once the risk and cost of delay are priced in.
Chance the cheaper quote ends up costing more
Share of simulated projects finished within each total cost
How this works. Each simulated project is either on time or late, with the chance you set. When it is late, the delay is drawn from a lognormal distribution, a right-skewed shape that matches how construction overruns behave: most delays are modest, a few are very long. Total cost = quote + weeks late x weekly cost of delay. The default numbers are illustrative; replace them with your own.
Read more: Cheapest Quote vs Delay Risk: The Economics of Choosing a Contractor in Singapore. Liquidated Damages and Extension of Time in Singapore: An Owner's and Contractor's Guide. Variation Orders and Provisional Sums: How to Stop Surprise VOs on Singapore Building Works.