Cheapest Quote vs Delay Risk: The Economics of Choosing a Contractor in Singapore

Updated 9 November 202621 min read16 sources, 4 officialBy RRD Engr & Constr, editorial standards
The short answer

The cheapest quote is only cheaper if the job finishes on time and on scope. Overrun research shows delays are common and fat-tailed, so a small price saving can be wiped out by a few weeks of rent, lost revenue or holding-over. Compare quotes on expected total cost, including probability-weighted delay cost and the worst plausible outcome, not the tender price alone.

Every owner who has collected three quotations for a fit-out, an office reinstatement or an addition and alteration (A&A) job has faced the same question: the lowest price is in front of you, the difference is real money, and the risks of accepting it are hard to put a number on. The usual answer is intuition, or a vague sense that “you get what you pay for”. Neither helps when you have to justify the decision to a board, a landlord or a managing agent.

This guide replaces intuition with a method. It draws on the research literature on project overruns, which is large and surprisingly consistent: most projects run late, and the distribution of delays has a long right tail. It explains why the lowest bidder in a competitive tender is systematically more likely to have under-priced the work (the “winner’s curse”), and how under-priced work tends to come back to the owner as variations, claims or delay. It then works through an Illustrative comparison of two quotes using probability-weighted delay cost, which is the same logic behind our cheap quote vs delay risk simulator.

None of this is an argument for always paying more. A higher quote is not proof of quality, and a lower quote is not proof of risk. The point is to compare quotes on expected total cost to the owner, which includes the cost of time.

The question owners are really asking

When an owner compares a S$168,000 quote with a S$185,000 quote, the visible difference is S$17,000. The invisible question is: what is the total cost of each option once the project is finished, including the cost of any delay, any variation claims, and any disruption to the business?

That total cost has three parts:

Component What it includes Who usually sees it at tender stage
Contract price The quoted lump sum Everyone
Scope growth Variations, provisional sum adjustments, items excluded from the quote Partly visible if exclusions are read carefully
Time cost Rent, holding-over, lost revenue, financing, extended fees, disruption, for every week past the planned date Almost never priced into the comparison

The third line is where most comparisons fail. A delay of two or three weeks on a commercial fit-out can easily cost more than the gap between two quotes, but it does not appear on any quotation. Our guide on the true cost of a late handback and the overstay cost calculator cover the weekly cost side in detail. This guide focuses on the probability side: how likely is a delay, and how large could it be?

What the evidence says about overruns

Base rates: most projects overrun

One of the largest bodies of evidence on project outcomes comes from Bent Flyvbjerg and colleagues. Their 2002 study of 258 transport infrastructure projects in 20 countries found that actual costs were on average 28% higher than forecast, and the authors argued that the pattern was too consistent to be explained by honest error alone.1 Other researchers have disputed that interpretation, and the cause of overruns remains debated; the existence of a large average overrun is the point that matters here.

The later database behind Flyvbjerg and Gardner’s book How Big Things Get Done (2023) covers more than 16,000 projects across more than 20 fields and 136 countries. According to a review of the book, 91.5% of those projects went over budget, over schedule, or both, and fewer than 1% were delivered on budget, on time and with the promised benefits.2

91.5% of 16,000+ projects in Flyvbjerg’s database went over budget, over schedule, or both2

Closer to the scale of building works, a study of large construction projects in Saudi Arabia by Assaf and Al-Hejji reported that 70% of projects experienced time overrun, and that change orders were the most common cause of delay identified by owners, consultants and contractors alike.3 That finding matters for this guide: the delay problem and the variation problem are the same problem seen from two angles. See our guide to variation orders and provisional sums.

These are not Singapore fit-out statistics, and nobody publishes a clean base rate for small A&A jobs in Singapore. But they establish a prior that any owner should start from: on-time completion is the exception, not the default.

Reference class forecasting: the outside view

Why do plans keep underestimating? Kahneman and Lovallo described two ways of forecasting. The “inside view” builds a forecast from the details of the current plan: the programme, the sequence, the crew size. The “outside view” asks how long similar projects actually took.4 The inside view is systematically optimistic, because plans describe what should happen, not the many small things that do happen.

Flyvbjerg turned the outside view into a practical method called reference class forecasting: identify a class of comparable past projects, establish the distribution of their outcomes, and position the new project within that distribution.5 The 2006 paper describes the method’s first practical application, to cost forecasts for large transport projects.

For an owner comparing quotes, the reference class is not “fit-outs in general”. It is “jobs of this type, done by this contractor”. That is why a contractor’s delivery record is worth more than its programme. A programme is an inside-view forecast. A record of comparable completed jobs is an outside-view forecast.

Delays are fat-tailed, not bell-shaped

The second lesson from the research is about the shape of the distribution.

If delays followed a normal (bell-shaped) distribution, an owner could reason from the average: a job that is “usually two weeks late” would rarely be more than four or five weeks late. The data say otherwise.

  • Love, Sing, Wang, Edwards and Odeyinka analysed schedule overruns on 276 Australian construction and engineering projects and found the data were non-Gaussian, with skewness and kurtosis inconsistent with a normal distribution. The best overall fit was a four-parameter Burr distribution, a family with a heavy right tail.6
  • Flyvbjerg and co-authors found that cost overruns on IT projects follow a power-law distribution: many projects overrun a little, and a fat tail of projects overrun enormously. A later clarification restated the cost-overrun sample as 4,677 projects.7
  • For the Olympic Games, Flyvbjerg, Budzier and Lunn estimated power-law tail exponents between roughly 1.2 and 1.7, a range in which the variance of outcomes is not finite and averages never settle down. They called the resulting pattern “regression to the tail”: eventually a new, larger extreme arrives.8

A small office fit-out is not an Olympic Games. Interdependence is far lower, so the tail is thinner. But the mechanism that produces fat tails is present on every construction job: one problem (a late approval, a wrong material delivery, a concealed defect behind a wall) delays the next trade, which delays the next. Delay compounds; it does not average out.

Flyvbjerg et al., Journal of Management Information Systems (2022)

The authors found that project cost overruns followed a power law with a “fat tail” of extreme cases, and warned that assuming a normal distribution greatly underestimates the frequency of extreme outcomes. They traced the tail to interdependencies, where a problem in one component cascades into others.7

What this means for an owner

Two practical conclusions follow:

  1. Start from the base rate, then adjust. Assume some delay is likely and ask what evidence would justify assuming otherwise for a specific contractor.
  2. Price the tail, not just the average. The expected delay cost is dominated by the minority of bad outcomes. An owner who looks only at the “most likely” scenario will consistently under-estimate risk.

Why the lowest bidder is often the one who under-priced

The winner’s curse

In 1971, three researchers at the oil company ARCO, Capen, Clapp and Campbell, studied why oil companies earned poor returns on offshore lease auctions. Their explanation became known as the winner’s curse: when several bidders estimate the value of the same uncertain asset, the winner tends to be the bidder whose estimate erred the most in the optimistic direction.9

Construction tendering is the mirror image. Each contractor estimates the cost of the same uncertain scope. Estimates scatter around the true cost. The lowest bid is, statistically, more likely to come from the contractor who under-estimated the cost, not the one who is most efficient. The more bidders and the more uncertain the scope, the stronger the effect.

This is not a moral judgement. It is selection: picking the minimum of several noisy estimates selects for the most optimistic error.

How experienced contractors escape the curse (and who pays)

Dyer and Kagel tested this directly. Experienced construction executives fell prey to the winner’s curse in laboratory auctions, yet performed well in real tendering. The authors identified field mechanisms that let contractors escape the curse even after bidding too low, along with learned judgement about which jobs to bid and private cost advantages.10

Some of those escape mechanisms are benign: a contractor recognises a mistake and withdraws, or absorbs a small loss. Others shift the cost to the owner. Bajari, Houghton and Tadelis studied highway paving contracts in California and found that contracts are routinely adapted after award because the original specification was incomplete. They estimated that adaptation costs amounted to 7.5–14% of the winning bid, and found that bidders anticipate these changes and adjust their bids strategically. Those costs were much larger than the bidders’ mark-ups from market power.11

7.5–14% of the winning bid consumed by post-award adaptation costs in highway contracts11

The three recovery routes

When a quote is too low for the scope as actually built, the shortfall comes back in one of three ways:

Route How it shows up Owner’s exposure
Variations and claims Items treated as “outside scope”, re-measured quantities, claims for site conditions or design changes Direct cost increase; disputes over valuation
Quality and specification drift Substituted materials, fewer coats, thinner sections, less supervision Defects later; rectification during the defects period
Time Smaller crews, sequential instead of parallel trades, the job deprioritised when a better-paying job appears Delay cost to the owner, often larger than the price gap

The first route is visible and contractual; our guide to variation orders and provisional sums explains how to close it. The third route is the least visible at tender stage and frequently the most expensive. A contractor that has under-priced a job has an economic incentive to minimise resources on it, and fewer resources mean a longer duration.

Composite scenario: the S$14,000 saving that cost S$60,000

An owner of a 4,000 sq ft office selected the lowest of three quotes for a fit-out, S$14,000 below the next bid. The quote excluded ceiling access panels, fire-rated board around the server room and after-hours noisy works, all of which the building management later required. Variation claims added S$19,000. The contractor ran one crew instead of two, and the M&E subcontractor, paid late, left site for nine days. The job finished six weeks late. The owner paid rent on the new premises from the original target date, and the landlord of the old premises charged for holding over. The delay cost, around S$41,000, was more than the original saving and the variations combined. This is a composite scenario, not a specific event; the figures are Illustrative.

Expected value vs tail risk

Expected value

The simplest correct comparison uses expected total cost:

Expected total cost = Quote + Expected scope growth + (Probability of delay × Expected delay length if late × Cost per week of delay)

Each term can be estimated, even roughly, and a rough estimate is better than an implicit zero.

Why the expected value is not enough

Expected value treats a 10% chance of losing S$100,000 the same as a certain loss of S$10,000. Most owners do not. A small business cannot absorb a three-month delay on its only outlet; a tenant whose lease expires on a fixed date faces a cliff, not a slope. Two additional measures help:

  • Percentiles (P80, P90, P95): the cost that is not exceeded in 80%, 90% or 95% of scenarios. A P90 of S$254,000 means a one-in-ten chance of a total cost above S$254,000.
  • Conditional value-at-risk (CVaR), also called expected shortfall: the average cost in the worst tail, for example the worst 5% of scenarios. Rockafellar and Uryasev’s formulation made CVaR a standard risk measure because it captures how bad the tail is, not just where it starts.12

An owner with a hard deadline should give heavy weight to P90 and CVaR. An owner with flexibility and deep pockets can lean more on the expected value.

Worked example: Quote A vs Quote B (Illustrative)

The following example uses Illustrative numbers only. They are chosen to be plausible for a small commercial fit-out in Singapore and to show the method, not to describe any real contractor. The same defaults are loaded in the delay-risk simulator, where you can replace them with your own figures.

The inputs

Input (Illustrative) Quote A (lowest price) Quote B (on-time record)
Contract price S$168,000 S$185,000
Planned duration 12 weeks 12 weeks
Probability of finishing late 60% 25%
Median delay, if late 4 weeks 1.5 weeks
Spread of delay (lognormal sigma) 0.9 0.6
Owner’s cost per week of delay S$9,000 S$9,000

Why these numbers? The probabilities reflect the base rates above, adjusted for what the owner learned from references: Contractor B’s last several comparable jobs finished within a week or two of programme; Contractor A’s references were mixed. The wider spread for A reflects less evidence and more ways for things to go wrong. The weekly cost of S$9,000 is an Illustrative sum of rent on the new premises, holding-over on the old premises, and staff disruption.

Delays are modelled with a lognormal distribution: if the job is late, the length of the delay is the median multiplied by a random factor whose logarithm is normally distributed. The lognormal is right-skewed and has no negative values, which suits delays, and its tail is heavier than a normal distribution but lighter than a power law. It is a deliberately moderate choice for small projects, given the fat-tailed evidence above.

Expected values (calculated)

For a lognormal, the mean equals the median multiplied by exp(sigma²/2).

  • Quote A: mean delay if late = 4 × exp(0.405) ≈ 6.0 weeks. Expected delay = 0.60 × 6.0 ≈ 3.6 weeks. Expected delay cost ≈ 3.6 × S$9,000 ≈ S$32,400. Expected total ≈ S$200,400.
  • Quote B: mean delay if late = 1.5 × exp(0.18) ≈ 1.8 weeks. Expected delay = 0.25 × 1.8 ≈ 0.45 weeks. Expected delay cost ≈ S$4,000. Expected total ≈ S$189,000.

On expected value, the “expensive” quote is about S$11,400 cheaper.

The simulation (1,000,000 Illustrative runs)

Measure (Illustrative) Quote A Quote B
Expected total cost S$200,400 S$189,050
Median (P50) total cost S$183,100 S$185,000
P80 total cost S$221,100 S$193,200
P90 total cost S$254,000 S$200,800
P95 total cost S$293,100 S$207,400
CVaR 95% (average of worst 5%) S$371,600 S$217,700
Probability that this option ends up cheaper about 56% about 44%
Probability of a delay longer than 8 weeks about 13% under 0.1%

The last rows are the most instructive. Quote A is cheaper in the majority of scenarios (about 56% of runs). Its median total cost is lower than B’s. An owner who reasons from the “most likely” outcome will pick A, and more often than not will feel vindicated.

But A’s losses, when they come, are large, and the expected value and every upper percentile favour B. The break-even is simple: the S$17,000 price gap buys about 1.9 weeks of delay at S$9,000 a week. Quote A has roughly a 48% chance of running more than 1.9 weeks late in this example; Quote B has very little chance of doing so.

Adding liquidated damages (Illustrative)

Suppose both contracts carry liquidated damages (LDs) of S$6,000 per week, capped at 10% of the contract sum. In the simulation, LDs recover on average about S$8,700 from A and S$2,500 from B. The expected net cost becomes about S$191,600 for A and S$186,600 for B, so LDs narrow the gap. But A’s P95 net cost is still about S$275,800 against S$192,500 for B, because in about 39% of A’s runs the delay is long enough to exhaust the LD cap. LDs also assume the contractor has no valid extension of time and that the deduction is actually collected. See liquidated damages and extensions of time.

Inputs to collect before comparing two quotes

  • Your true cost per week of delay: rent, holding-over, lost revenue, financing, extended consultant fees, storage, staff time
  • Any hard deadline (lease expiry, opening date, landlord handback) and what happens if it is missed
  • Each contractor’s record on two or three comparable jobs: contract period vs actual completion
  • A normalised scope comparison (exclusions priced in)
  • The programme each contractor proposes, with crew sizes and key subcontractors named
  • The LD rate and cap each contractor will accept

The cost of delay to owners

The weekly cost of delay is the single most important number in the comparison, and it is usually larger than owners expect. Typical components:

Cost component How it accrues Notes
Rent on new premises From the end of any rent-free fit-out period Fixed by lease; often the largest item
Holding-over on old premises From lease expiry or handback date May be charged at a premium; see holding-over cost
Lost revenue or margin For retail, F&B, clinics, any trading premises Use contribution margin, not turnover
Financing Interest on a construction or fit-out loan Also the opportunity cost of capital
Extended professional fees Project manager, designer, engineer supervision Often time-based
Temporary arrangements Storage, temporary office, double IT services Easy to forget
Disruption Staff time, customer impact, reputation Hard to quantify; record a conservative figure

Our overstay cost calculator helps build this number for a commercial handback. For a broader view of where fit-out time goes, see realistic fit-out programmes and where delays come from.

The Singapore context in 2026

A busy market

Singapore’s Building and Construction Authority (BCA) projected in January 2026 that total construction demand would remain steady at S$47–53 billion in nominal terms in 2026, after preliminary demand of S$50.5 billion in 2025. Output was forecast at S$43–46 billion, and demand was projected to average S$39–46 billion a year from 2027 to 2030, with large projects such as Changi Airport Terminal 5 in the pipeline.13 BCA’s release did not forecast tender prices.

For an owner of a small job, a sustained pipeline of large projects has two practical effects. Good subcontractors and supervisors are in demand, so a contractor that has bid low may struggle to hold on to them. And contractors have alternatives: a job that turns out to be under-priced competes for resources with better-paying work.

Manpower constraints

Construction in Singapore relies heavily on foreign workers, and their numbers are capped. The Ministry of Manpower lists the construction sector’s dependency ratio ceiling (the maximum share of foreign workers in a company’s total workforce) at 83.3%.14 A contractor’s ability to add a second crew when a job slips is therefore bounded by its local headcount and quota, not simply by willingness to pay overtime. When comparing quotes, ask each contractor how many workers and supervisors it will deploy and whether they are its own employees or subcontracted.

How the public sector weighs time

Singapore’s public sector does not award construction contracts on price alone. Under BCA’s Price-Quality Method, building tenders with an estimated construction cost of S$3 million and above are evaluated with price weighted at 40–60% and quality at the remainder, and the quality attributes include past performance on timeliness and quality, safety record and the experience of key personnel.15 Private owners are free to adopt the same logic on a small job: score delivery record explicitly, alongside price.

How RRD approaches this

RRD carries out a site survey before quoting and issues an itemised quotation that lists cost-risk items, such as concealed conditions and authority requirements, before the owner signs. Each job has a written programme and supervised works, and ends with a joint inspection and handover. We would rather an owner compare our quotation line by line against others than on the bottom line alone.

Contractual levers that make on-time real

A contractor’s record is the best predictor of delivery, but the contract determines what happens when things slip. These levers turn a promise into an obligation.

1. Liquidated damages at a genuine pre-estimate

LDs give the owner a pre-agreed sum for each day or week of culpable delay without having to prove the actual loss. Under Singapore law, an LD clause is enforceable if it is a genuine pre-estimate of loss and not a penalty. The rate should be grounded in the weekly delay cost calculated above, and any cap should be understood as the point beyond which the owner bears the risk. Details in liquidated damages and EOT in Singapore.

2. A real programme, submitted early

The public sector form PSSCOC (Public Sector Standard Conditions of Contract) requires the contractor to submit a programme within 30 days of the letter of acceptance, allows the Superintending Officer to require a revised programme when progress departs from it, and allows 10% of interim payments to be retained until an adequate programme is provided.16 A private A&A contract can adopt a lighter version: a bar-chart programme with key milestones before work starts, updated fortnightly.

3. Notice and extension-of-time discipline

An EOT clause with clear grounds and notice periods protects both sides: the contractor gets more time for owner-caused delay, and the owner keeps its right to LDs. Without one, owner-caused delay can set time “at large” and leave the owner with only a claim for general damages.

4. Progress reporting

Weekly photographs, a short progress note against the programme, a look-ahead of the next two weeks’ activities, and a list of information the contractor needs from the owner. Reporting surfaces slippage when it is a few days, not a few weeks.

5. Payment linked to progress

Progress payments tied to completed and verified work (not to elapsed time) align the contractor’s cash flow with progress. In Singapore, payment claims and responses must also comply with the Security of Payment Act; see SOPA for owners and contractors.

6. Named key people and resources

Name the site supervisor and key subcontractors in the contract, and require the owner’s consent to change them. This targets the resource-thinning route by which under-priced jobs drift.

A defensible way to choose between quotes

  1. Normalise scope: list every exclusion and provisional item in each quote and price them, so you compare like with like.
  2. Calculate your weekly cost of delay from your own lease, revenue and financing figures.
  3. For each contractor, estimate the probability of delay and a plausible median delay from references on comparable jobs, starting from the base rate that most projects overrun.
  4. Compute expected total cost for each option, then look at P90: the outcome you would face one time in ten.
  5. Run the numbers in the delay-risk simulator to see how sensitive the answer is to your assumptions.
  6. Negotiate contractual levers (LD rate and cap, programme, reporting, named personnel) with the preferred contractor before signing.
  7. Record the reasoning, so that the choice can be explained to a board, MCST or landlord later.

Common objections, answered

“Our job is small; these statistics are about megaprojects.” The overrun magnitudes in the megaproject literature are larger than on a small fit-out, but the direction and shape (most projects late, right-skewed outcomes) have been found across many project types and sizes.6 Use smaller numbers, not zero.

“The contractor promised the date in writing.” A programme is an inside-view forecast. The question is what happened on the contractor’s last five comparable jobs.

“We’ll just impose heavy LDs.” An LD rate that is extravagant compared with the greatest loss that could conceivably follow is at risk of being struck down as a penalty, and an unrealistically high rate may simply deter better contractors from bidding. Set LDs at a defensible estimate of your loss.

“The price gap is certain; the delay is only a possibility.” Correct, which is why the comparison uses probabilities. But a possibility with a 50% chance and a heavy tail is not a rounding error.

Summary

  • On-time completion is the exception in the research literature. Start from that base rate.
  • Delays are skewed and fat-tailed: a minority of bad outcomes dominates the expected cost.
  • In competitive tendering, the lowest bid is statistically more likely to contain an under-estimate. Under-pricing is recovered through variations, quality drift or time.
  • Compare options on expected total cost, and check the P90 and the worst-tail average, not just the most likely outcome.
  • In the Illustrative example, the cheaper quote wins slightly more than half the time, yet costs about S$11,400 more in expectation and far more in the tail.
  • Contract levers (LDs, programme, notices, reporting, named resources) make on-time delivery enforceable, but they do not replace choosing a contractor with a good delivery record.

Questions people ask

Is the cheapest quote always the riskiest?

No. A low quote can come from a leaner overhead, a better method, or a contractor that genuinely wants the job. The risk is not the low price itself but what it is missing: excluded items, thin allowances for site risk, an unrealistic programme or too few supervisors. Normalise the scope first. If the gap survives a line-by-line comparison and the contractor's delivery record is good, the low quote may well be the best value.

How do I estimate the cost of one week of delay?

Add up every cost that runs by the week once the planned completion date passes: rent on the new premises you cannot use, holding-over charges on the old premises, lost trading revenue, interest on project financing, extended consultant fees, temporary storage, and staff time. Use your own lease and budget figures. The resulting weekly figure is the number to compare against any difference in contract price.

What is reference class forecasting?

It is a method of forecasting a project's cost or duration from the actual outcomes of a group of similar past projects, rather than from the details of the current plan. Kahneman and Lovallo called this the outside view. Flyvbjerg applied it to infrastructure planning. For a small fit-out, the practical version is to ask what happened on comparable jobs, not what the programme says should happen.

Why are construction delays described as fat-tailed?

Because most jobs overrun by a little, but a small number overrun by a lot, far more often than a bell curve would predict. Studies of construction schedule overruns found the data are skewed and non-Gaussian, and research on IT projects and the Olympics found power-law tails. In practice this means the average delay understates the risk: a few bad outcomes dominate the expected cost.

Do liquidated damages solve the delay risk?

Only partly. Liquidated damages transfer a pre-agreed daily or weekly sum to the contractor, but they are usually capped, they stop where the contractor is entitled to an extension of time, and they must be collectable. If the true cost of delay is higher than the LD rate, or the delay runs past the cap, the owner bears the difference. LDs are a lever, not insurance.

How can a contractor's on-time record be checked?

Ask for references from comparable completed jobs and call them. Ask what the contract period was, when practical completion was certified, and how many variations were claimed. For larger public jobs, Singapore's Price-Quality Method scores past timeliness. For private work, look at the contractor's BCA registration and licences, and ask for a sample programme from a previous job.

Should I just add a contingency to the cheapest quote?

A contingency covers cost, but it does not buy back time. If the cheaper contractor is more likely to finish late, the contingency must also cover a probability-weighted allowance for weeks of delay cost, plus a buffer for the tail. Once that allowance is included, the comparison often changes. The worked Illustrative example in this guide shows how.

Sources

16 sources. Official sources are marked dark. Links were checked when this guide was last updated.

  1. arxiv.orgFlyvbjerg, B., Skamris Holm, M. and Buhl, S. (2002). “Underestimating Costs in Public Works Projects: Error or Lie?” Journal of the American Planning Association, 68(3), 279–295. Preprint: https://arxiv.org/abs/1303.6604 (accessed Nov 2026) ↩
  2. strategy-business.comAkst, D. (19 June 2023). “Why do large projects go over budget?” strategy+business, reviewing Flyvbjerg, B. and Gardner, D., How Big Things Get Done (Currency, 2023). https://www.strategy-business.com/article/Why-do-large-projects-go-over-budget (accessed Nov 2026) ↩↩
  3. doi.orgAssaf, S. A. and Al-Hejji, S. (2006). “Causes of delay in large construction projects.” International Journal of Project Management, 24(4), 349–357. https://doi.org/10.1016/j.ijproman.2005.11.010 (accessed Nov 2026) ↩
  4. doi.orgKahneman, D. and Lovallo, D. (1993). “Timid Choices and Bold Forecasts: A Cognitive Perspective on Risk Taking.” Management Science, 39(1), 17–31. https://doi.org/10.1287/mnsc.39.1.17 (accessed Nov 2026) ↩
  5. arxiv.orgFlyvbjerg, B. (2006). “From Nobel Prize to Project Management: Getting Risks Right.” Project Management Journal, 37(3), 5–15. Preprint: https://arxiv.org/abs/1302.3642 (accessed Nov 2026) ↩
  6. doi.orgLove, P. E. D., Sing, C. P., Wang, X., Edwards, D. J. and Odeyinka, H. (2013). “Probability distribution fitting of schedule overruns in construction projects.” Journal of the Operational Research Society, 64(8), 1231–1247. https://doi.org/10.1057/jors.2013.29 (accessed Nov 2026) ↩↩
  7. arxiv.orgFlyvbjerg, B., Budzier, A., Lee, J. S., Keil, M., Lunn, D. and Bester, D. W. (2022). “The Empirical Reality of IT Project Cost Overruns: Discovering A Power-Law Distribution.” Journal of Management Information Systems, 39(3), 607–639; author’s clarification in 40(4) (2023). https://arxiv.org/abs/2210.01573 and https://ora.ox.ac.uk/objects/uuid:a6ea9269-366c-4c7a-8b05-782f5fa3b0d2 (accessed Nov 2026) ↩↩
  8. arxiv.orgFlyvbjerg, B., Budzier, A. and Lunn, D. (2021). “Regression to the tail: Why the Olympics blow up.” Environment and Planning A: Economy and Space, 53(2), 233–260. Preprint: https://arxiv.org/abs/2009.14682 (accessed Nov 2026) ↩
  9. bibbase.orgCapen, E. C., Clapp, R. V. and Campbell, W. M. (1971). “Competitive Bidding in High-Risk Situations.” Journal of Petroleum Technology, 23, 641–653. Bibliographic record: https://bibbase.org/network/publication/capen-clapp-campbell-competitivebiddinginhighrisksituations-1971 (accessed Nov 2026) ↩
  10. ideas.repec.orgDyer, D. and Kagel, J. H. (1996). “Bidding in Common Value Auctions: How the Commercial Construction Industry Corrects for the Winner’s Curse.” Management Science, 42(10), 1463–1475. https://ideas.repec.org/a/inm/ormnsc/v42y1996i10p1463-1475.html (accessed Nov 2026) ↩
  11. aeaweb.orgBajari, P., Houghton, S. and Tadelis, S. (2014). “Bidding for Incomplete Contracts: An Empirical Analysis of Adaptation Costs.” American Economic Review, 104(4), 1288–1319. https://www.aeaweb.org/articles?id=10.1257/aer.104.4.1288 (accessed Nov 2026) ↩↩
  12. risk.netRockafellar, R. T. and Uryasev, S. (2000). “Optimization of conditional value-at-risk.” Journal of Risk, 2(3), 21–41. https://www.risk.net/journal-risk/2161159/optimization-conditional-value-risk (accessed Nov 2026) ↩
  13. bca.gov.sgBuilding and Construction Authority (22 January 2026). “Steady construction demand in 2026 as Singapore steps up support for built environment firms through collaboration and innovation.” https://www1.bca.gov.sg/resources/newsroom/steady-construction-demand-in-2026-as-singapore-steps-up-support-for-built-environment-firms-through-collaboration-and-innovation/ (accessed Nov 2026) ↩
  14. mom.gov.sgMinistry of Manpower — “Levy and quota requirements” (sector dependency ratio ceilings; last updated 19 February 2026). https://www.mom.gov.sg/passes-and-permits/s-pass/quota-and-levy/levy-and-quota-requirements (accessed Nov 2026) ↩
  15. bca.gov.sgBuilding and Construction Authority — “Price Quality Method (PQM) Framework.” https://www1.bca.gov.sg/growth-and-transformation/procurement/procurement-and-legal-frameworks/price-quality-method-pqm-framework/ (accessed Nov 2026) ↩
  16. isomer-user-content.by.gov.sgBuilding and Construction Authority — Public Sector Standard Conditions of Contract for Construction Works 2020 (8th edition, July 2020), clauses 9.1–9.4 and 16. https://isomer-user-content.by.gov.sg/338/5349d125-0337-4dc3-a36d-623e599f2865/1-psscoc-for-construction-works-2020.pdf (accessed Nov 2026) ↩
Cite or link to this guide

Use this guide in a report, a tender or a by-law briefing. Please link to the page so readers get the current version.

RRD Engr & Constr. (2026). Cheapest Quote vs Delay Risk: The Economics of Choosing a Contractor in Singapore. RRD Field Guide. Updated 9 November 2026. https://rrd.sg/guides/cheap-quote-vs-delay-economics/