Variation Orders and Provisional Sums: How to Stop Surprise VOs on Singapore Building Works
Surprise variation orders usually come from scope that was never fully defined, items excluded from the quote, provisional sums used as placeholders, and concealed site conditions. Owners reduce them by defining scope in drawings and an itemised schedule, pricing exclusions when comparing quotes, requiring written instructions and quotations before varied work starts, and agreeing valuation rules in the contract.

Ask owners what they dislike most about building works and many will say the same thing: the job came in at one price and finished at another. The difference arrives as a stream of variation orders (VOs), some expected, many not, often with an argument attached about whether the work was “in the original scope”.
Surprise VOs are rarely a mystery. They come from a short list of causes: scope that was never fully defined, items quietly excluded from the quotation, provisional sums used as placeholders for decisions not yet made, and conditions hidden behind walls, ceilings and floors. Economists who study procurement call this the cost of incomplete contracts, and they have measured it.
This guide explains where VOs come from, how the main pricing methods allocate the risk, the difference between provisional sums, prime cost sums and contingency, how variations should be instructed and valued, and how to compare quotes so that the lowest price is really the lowest. It refers to the public sector form PSSCOC (Public Sector Standard Conditions of Contract) where its wording is a useful model, and to Singapore case law on written instructions.
Why surprise VOs happen
Contracts are always incomplete
No drawing set or specification describes every detail of a building job. Bajari, Houghton and Tadelis studied highway paving contracts and found that contracts are routinely renegotiated after award because changes are needed. They estimated that the resulting adaptation costs were 7.5–14% of the winning bid, and that bidders anticipate this and adjust their bids strategically.2 On small refurbishment work, where the existing building is part of the unknown, the incompleteness is usually greater, not smaller.
7.5–14% of the winning bid absorbed by post-award adaptation costs in a study of highway contracts2
Change also drives time. In a survey of large construction projects, Assaf and Al-Hejji found that “change order” was the most common cause of delay identified by owners, consultants and contractors.1 Our guide on the cheapest quote vs delay risk shows how scope growth and delay combine in the owner’s total cost.
The five usual sources
| Source | Typical example in A&A or fit-out | Who can prevent it |
|---|---|---|
| Undefined scope | “Supply and install ceiling” without a ceiling layout, grid type or access-panel count | Owner and designer, before tender |
| Exclusions and assumptions | “Excludes M&E modifications”, “assumes existing sprinklers adequate” | Owner, by reading and pricing them |
| Provisional sums used as placeholders | “Provisional sum for signage S$5,000” with no specification | Owner, by defining or fixing them early |
| Concealed conditions | Corroded embedded pipes, uneven slab, asbestos-free status unknown, undocumented previous works | Survey and opening-up before tender; clear risk allocation |
| Owner changes and third-party requirements | Additional meeting room; building management requires fire-rated board or after-hours works | Owner, by freezing the brief; by obtaining building rules early |
The winner’s curse makes the second and fourth sources worse. The term comes from a 1971 study of oil-lease auctions, which observed that the winning bidder tends to be the one whose estimate erred most in the optimistic direction.8 In construction tendering, the lowest bid is correspondingly more likely to have under-estimated the uncertain parts of the work. Dyer and Kagel found that experienced construction executives fell prey to the curse in laboratory auctions but did well in real tendering, partly because the industry has mechanisms that let a contractor recover after bidding too low.9 Variations are one of those mechanisms.
How the pricing basis allocates the risk
Lump sum, remeasurement and the alternatives
| Pricing basis | How the price works | Who carries quantity risk | Suits |
|---|---|---|---|
| Lump sum (drawings and specification) | Fixed price for the described scope, adjusted only as the contract allows | Contractor, for the described scope | Well-defined fit-out and A&A |
| Lump sum with bills of quantities | Fixed price, but the bills form part of the contract; errors and differences in quantity are corrected as variations | Owner, for errors in the bills | Larger jobs with a quantity surveyor |
| Remeasurement (schedule of rates / provisional quantities) | Work is measured as built and paid at tendered rates | Owner | Uncertain scope, repair works |
| Cost reimbursable (cost plus fee) | Actual cost plus an agreed fee or percentage | Owner | Emergency or highly uncertain work |
Under PSSCOC 2020, the Contract Sum is a lump sum that is “fixed subject only to adjustments expressly provided for” in the conditions, and the contractor is deemed to have satisfied itself of the sufficiency of its tender.3 Where the optional bills of quantities module is used, the quantities are treated as estimates: differences in quantity or description are treated as variations and valued at bill rates or rates analogous to them, and items marked as provisional quantities are remeasured on completion.3
The private-sector SIA suite similarly distinguishes the SIA Building Contract 2016 Without Quantities and With Quantities forms.5 The practical distinction for an owner: in a “without quantities” contract, the contractor takes the risk of measuring the work from the drawings; in a “with quantities” contract, the owner (through its quantity surveyor) takes the risk of errors in the bills.
The itemised quotation as a mini bill of quantities
Most small A&A and fit-out jobs are let on a contractor’s quotation, not on bills prepared by a quantity surveyor. An itemised quotation (each trade broken into items with quantity, unit and rate) does three useful things:
- It shows what is included, so gaps are visible.
- It provides rates for valuing variations.
- It allows like-for-like comparison between contractors.
A single-line quotation (“Renovation works as discussed: S$85,000”) does none of these, and every later dispute about scope becomes an argument about what was “discussed”.
Provisional sums, prime cost sums and contingency
These three are often confused, and the confusion is a common source of surprise.
| Allowance | What it is for | How it adjusts | Mark-up and attendance |
|---|---|---|---|
| Provisional sum (PS) | Work not defined well enough to price at tender | Replaced by the value of work actually instructed | Valued under the contract’s variation rules |
| Prime cost (PC) sum | Work or materials from a specialist the owner will nominate or select | Adjusted to the actual price of that specialist | Contractor’s agreed mark-up and attendance usually added |
| Contingency | Owner’s reserve for the unknown | Not part of the contractor’s price unless the contract says so | n/a |
A provisional sum stands in for work that cannot yet be priced; it is replaced by a valuation of the work actually done, so the final account can go up or down.6 Industry practice distinguishes “defined” provisional sums (described enough for the contractor to allow for programme and preliminaries) from “undefined” ones (where the contractor cannot reasonably make that allowance).6 The distinction matters for time as well as cost.
PSSCOC 2020 defines “Provisional Sum Items” as items of work executed only on the Superintending Officer’s written instruction, who may decide the work is to be done in whole, in part, or not at all; instructed provisional sum work is valued under the normal variation rules. An instruction on a provisional sum item gives an extension of time only to the extent that it varies the work described.3
A prime cost sum is an allowance for a nominated or selected specialist’s work or goods. The contract sum is adjusted to the specialist’s actual price, plus the contractor’s agreed percentage for overheads and profit and its attendance.6 Owners are often surprised by attendance costs (scaffolding, power, hoisting, protection, coordination) that the main contractor adds for a specialist it did not choose.
Provisional sum hygiene
- Keep provisional sums to items that genuinely cannot be defined at tender
- Describe each one as fully as possible (location, extent, standard) so it is a “defined” provisional sum
- Use identical provisional sums in every tender so that quotes are comparable
- For each PC sum, state what attendance the main contractor must provide and how it is priced
- Track provisional sum expenditure in a simple register against each original allowance
- Set decision dates for the owner’s selections, so placeholders do not hold up the programme
Scope definition before tender
The cheapest variation is the one that never arises. For a typical A&A or fit-out job, a tender package that minimises VOs includes:
- Drawings: layout, reflected ceiling plan, partition types, elevations of feature walls, M&E layouts.
- Finishes schedule: every surface, by room, with product, colour and standard.
- Specification or preambles: workmanship standards, testing, protection, cleaning.
- Inclusions and exclusions list: written by the owner, not left to each contractor.
- Interfaces: what the landlord, building management or other contractors provide, and what this contractor must coordinate.
- Statutory items: which approvals the contractor must obtain and which the owner’s consultants will handle (see which approvals A&A works need and fire safety approvals for fit-outs).
- Building rules: working hours, noise restrictions, loading-bay bookings, protection requirements and deposits.
- Reinstatement obligations: for tenants, what must be removed at lease end (see office reinstatement).
Site surveys and concealed conditions
Who carries the risk of what cannot be seen?
On A&A and refurbishment work, the existing building is the largest unknown. Typical concealed conditions include services embedded in walls and slabs, previous unauthorised works, non-standard construction, deteriorated substrates behind finishes, and structural elements that differ from record drawings.
Standard forms deal with ground risk more clearly than with building-fabric risk. PSSCOC 2020 deems the contractor to have inspected the site and satisfied itself before tendering, but its adverse physical conditions clause (clause 5.2) allows extra time and cost for physical conditions that could not reasonably have been foreseen by an experienced contractor, encountered in the course of sub-surface works, subject to notice.3 That wording does not obviously extend to conditions hidden above ground in an existing building.
For a fit-out or A&A contract, the practical answer is to allocate concealed-condition risk expressly:
- carry out a joint site survey, and record it with photographs;
- where the risk is significant, pay for opening-up works before tender (small inspection openings in walls, ceilings or floors);
- name the conditions the contractor is deemed to have priced (for example, “making good existing plaster up to X m²”) and those that will be treated as variations;
- set a re-measurable provisional quantity for the uncertain item instead of a vague provisional sum.
Independent engineer's note
Where concealed conditions involve structure (hacking walls, cutting slabs, new openings, corrosion of embedded steel), the scope, method and any remedial design need a Professional Engineer. Appointing the PE directly, rather than through the contractor, means the investigation and its conclusions serve the owner: the PE defines what is needed, and the contractor prices it. RRD’s usual independent engineering partner is CVC Engineers, a Singapore PE consultancy that contracts with and invoices the owner directly; owners are free to appoint any PE. See PE endorsement and independence and hacking walls and structural elements.
How variations should be instructed
Written instructions
A variation should be instructed in writing by a person with authority under the contract, before the work is done. PSSCOC 2020 is a useful model:3
- A variation is any change in the original contract intention as deduced from the contract as a whole, including changes in quantity, additions or omissions, changes in character or quality, changes in levels and dimensions, removal of work no longer wanted, and acceleration to an earlier completion date. Work needed to cure the contractor’s own default is excluded.
- The Superintending Officer may instruct a variation in writing at any time. If the contractor considers that an instruction not labelled as a variation does require one, it must say so in writing within 14 days, and the Superintending Officer may then confirm, modify or rescind the instruction.
- Before instructing, the Superintending Officer may require the contractor to submit a quotation at its own cost. If the quotation is accepted, it fixes the valuation, and the contractor cannot also claim loss and expense for that instruction.
The quotation-first route is the single most effective protection against surprise VOs. It turns an open-ended claim into an agreed price, before the owner is committed.
What Singapore courts say about oral instructions
Many contracts say variations must be instructed in writing. Whether that bars payment for work done on oral instructions depends on the drafting.
Earlier High Court decisions went the other way on different wording: in Fongsoon Engineering v Kensteel Engineering [2011] SGHC 82, a written variation order was held to be a condition precedent and the variation claims failed.4 The lessons are symmetrical:
- Owners who want written instructions to be a precondition to payment must say so expressly, state the consequence, and set a deadline for the contractor to seek written confirmation.
- Contractors should not rely on courts reading an unclear clause in their favour. Confirm every verbal instruction in writing, the same day if possible.
A clean variation procedure for small jobs
- Owner (or its representative) describes the proposed change in writing, with any sketch or product data.
- Contractor returns a written quotation within an agreed time, stating the price, the effect on the completion date, and any items excluded.
- Owner accepts, negotiates or withdraws the change, in writing.
- Owner issues a numbered variation instruction referring to the accepted quotation and the revised completion date.
- Contractor carries out the work and includes it in the next progress claim as a separate line.
- Both parties keep a variation register: number, description, quoted amount, agreed amount, time effect, status.
How variations are valued
The valuation hierarchy
Where no quotation has been agreed, the contract’s valuation rules apply. PSSCOC 2020 clause 20.1 sets a typical hierarchy:3
| Situation | PSSCOC 2020 valuation rule |
|---|---|
| Similar work, similar conditions, no significant change in quantity | Contract rates |
| Similar work but different conditions or significantly different quantity | Contract rates as the basis, with a fair allowance for the difference |
| Neither applies | Measurement and valuation at fair market rates and prices |
| None of the above appropriate | Cost of plant, materials, goods, labour and equipment, plus 15% for supervision, overheads, profit and all other costs |
| Omissions | Contract rates; remaining work re-valued if the omission changes its conditions |
PSSCOC also requires the contractor to carry out instructed variations pending valuation, sets 30-day and 60-day steps for submitting and certifying the valuation once the varied work is substantially complete, and deems the contractor to accept the Superintending Officer’s valuation if it does not give notice of disagreement within 30 days.3 A later amendment allows the Superintending Officer to replace a schedule-of-rates rate that is grossly excessive or inadequate with a fair market rate.3
Where a contract is silent on valuation, the Security of Payment Act’s default for progress claims is to value work having regard to the contract price, other contract rates, and agreed variations, or failing those, prevailing industry rates.7
Dayworks
Dayworks pay for work by recorded resources (hours of labour, plant and materials) rather than by measurement. They suit small, unforeseeable tasks that cannot be priced in advance, such as investigating a leak or removing an unexpected obstruction. They are expensive, because the owner pays for time rather than output.
Under PSSCOC 2020, the Superintending Officer may order variation work on a daywork basis in writing, the contractor must give advance notice whenever it proposes to carry out daywork, and submitting daywork sheets (man-hours per day, plant and materials) within 3 days is a condition precedent to payment.3 A private contract can borrow these rules: written authorisation, advance notice, daily signed sheets, and agreed daywork rates in the quotation.
Comparing quotes properly
Normalisation
Quotes are only comparable if they cover the same scope. Normalising means adjusting each quote so that it does.
How to normalise three quotations
- Build a single list of every item, exclusion, assumption and provisional sum appearing in any of the quotes.
- Mark, for each quote, whether each item is included, excluded, or provisional.
- For each excluded item, add an estimated cost (from another contractor’s rate, a supplier quote, or your consultant).
- Replace each contractor’s provisional sums with the same owner-set figure.
- Adjust for differences in specification (for example, board thickness or paint system) where they are material.
- Compare the normalised totals, and then consider time and delivery record.
Worked example (Illustrative)
All figures are Illustrative.
| Item | Quote X | Quote Y | Quote Z |
|---|---|---|---|
| Headline price | S$92,000 | S$104,500 | S$98,000 |
| After-hours noisy works premium | Excluded (+S$4,500) | Included | Included |
| Fire-rated board to server room | Excluded (+S$3,200) | Included | Excluded (+S$3,200) |
| Electrical modifications | PS S$2,000 (owner sets S$6,000: +S$4,000) | Included | PS S$6,000 (no change) |
| Ceiling access panels (12 no.) | Excluded (+S$1,800) | Included | Included |
| Disposal of debris | Included | Included | Excluded (+S$1,500) |
| Preliminaries: protection of common areas | Excluded (+S$2,000) | Included | Included |
| Normalised total | S$107,500 | S$104,500 | S$102,700 |
The lowest headline price becomes the highest once exclusions are priced. Quote Z is lowest after normalisation, and Quote Y, the highest headline, is within 2% of it. The next step is to weigh delivery record and programme, as in our cheap quote vs delay risk guide and the delay-risk simulator.
Red flags in quotations
Red flags to query before signing
- A single lump sum with no itemised breakdown
- Long or vague exclusion lists (“all M&E works”, “all authority requirements”, “making good by others”)
- Low provisional sums for items you know are significant
- “Subject to site measurement” on work that could have been measured at the site visit
- No allowance for building-management requirements, after-hours work or protection of common areas
- Rates for variations not stated, or “to be agreed”
- Payment terms front-loaded far ahead of work done
- No programme, or a programme much shorter than other bidders’ without explanation
- No reference to approvals, PE endorsement or submissions where your works need them
- A quotation validity of only a few days, used to pressure a decision
Composite scenario: the quote that grew 31%
A clinic owner accepted the lowest of three quotes, S$118,000, for converting a shop unit. The quote excluded “plumbing beyond existing points”, “electrical upgrading if required” and “all making good”. Within four weeks the contractor submitted VOs for new sanitary points (S$9,800), a three-phase electrical upgrade (S$14,200), making good after hacking (S$6,400) and after-hours works the building required (S$6,300). None was priced before work started; each was presented after it was done. The final account was S$154,700, 31% above the quote and 9% above the next-highest bid, which had included most of those items. Opening was also delayed by three weeks while the electrical upgrade was approved. This is a composite scenario; figures are Illustrative.
Variations, payment and SOPA
In Singapore, variation claims usually flow through progress payment claims subject to the Building and Construction Industry Security of Payment Act. A respondent who disputes a variation must say so, with reasons, in the payment response; objections not raised there generally cannot be raised later in adjudication.7 Claims for damage, loss or expense must be supported by an agreement on quantum or a certificate required by the contract, or the adjudicator must disregard them.7 Keeping a variation register with agreed amounts makes both sides’ SOPA position clearer. See SOPA for owners and contractors.
How RRD approaches this
RRD surveys the site before quoting and issues an itemised quotation that lists cost-risk items (such as concealed conditions, building-management requirements and authority items) before the owner signs. Changes are quoted in writing, with their effect on time, before the varied work starts. Works end with a joint inspection and handover against the agreed scope.
Summary
- Surprise VOs come from incomplete scope, exclusions, placeholder provisional sums, concealed conditions and owner changes. Research estimates post-award adaptation costs at 7.5–14% of the winning bid on highway contracts.
- A lump sum is fixed only for the scope described. The more complete the description, the more fixed the price.
- Provisional sums replace undefined work; PC sums cover selected specialists plus mark-up and attendance; contingency is the owner’s reserve.
- Allocate concealed-condition risk expressly on A&A work; standard ground-condition clauses may not cover it.
- Instruct variations in writing, priced before the work starts. Whether a written-instruction clause bars payment for oral instructions depends on stringent drafting.
- Compare quotes on normalised totals, not headline prices.
Questions people ask
What is a variation order?
A variation order (VO) is an instruction that changes the work described in the contract: adding or omitting work, changing quantities, quality, specification, levels or positions, or changing the sequence or timing. Under PSSCOC 2020, a variation is any change in the original contract intention as deduced from the contract as a whole. A properly instructed variation adjusts the contract sum and may entitle the contractor to more time.
What is the difference between a provisional sum and a prime cost sum?
A provisional sum is an allowance for work that is not defined well enough to price at tender; it is replaced by the value of the work actually instructed and done. A prime cost (PC) sum is an allowance for work or materials to be supplied by a specialist the owner will nominate or select; it is adjusted to the actual price, with the contractor's agreed mark-up and attendance. Neither is a fixed price.
Is a lump-sum quotation fixed no matter what?
No. A lump sum fixes the price for the scope described, not for whatever the owner ends up wanting. It is adjusted for variations, provisional sums, and any other adjustments the contract allows. How fixed it really is depends on how completely the scope was described, how many items are provisional or excluded, and how the contract allocates the risk of site conditions.
Can a contractor claim for variations done on verbal instructions?
Sometimes. Singapore courts have held that a clause makes written instructions a condition precedent to payment only if it is drafted stringently, for example by expressly forfeiting payment or setting a time limit for written notice. In Vim Engineering v Deluge Fire Protection [2023] SGHC(A) 2 the Appellate Division allowed the claim because the clause was not drafted that way. Both parties should still confirm instructions in writing.
How are variations valued?
The contract usually sets a hierarchy: use contract rates where the varied work is similar; adapt those rates where conditions or quantities differ; use fair market rates where there are no relevant rates; and, as a last resort, use actual cost plus a percentage. PSSCOC 2020 clause 20.1 follows this pattern, with cost plus 15% as the fallback. Agreeing a quotation before the work starts avoids the argument.
What are dayworks?
Dayworks are a method of paying for work that cannot be measured or priced in advance, using recorded hours of labour, plant and materials at agreed daywork rates. They are useful for small unforeseen tasks but expensive and hard to control. Under PSSCOC 2020, daywork must be ordered in writing, the contractor must inform the Superintending Officer in advance, and signed daywork sheets within 3 days are a condition precedent to payment.
How should I compare quotations with different exclusions?
Normalise them. List every exclusion, assumption and provisional item across all quotes, then add an estimated cost for each item a quote leaves out, so that each total covers the same scope. Use identical provisional sums in each quote where possible. The lowest normalised total, not the lowest headline price, is the fair comparison.
Who bears the cost of concealed conditions found during A&A works?
Whoever the contract says. If the contract is silent, the contractor that priced a lump sum after inspecting the site may be taken to have accepted much of the risk, but disputes are common. Standard forms vary: PSSCOC's adverse physical conditions clause addresses sub-surface works. For A&A works, allocate concealed-condition risk expressly, and consider opening-up or survey work before tender.
Sources
9 sources. Official sources are marked dark. Links were checked when this guide was last updated.
- doi.orgAssaf, S. A. and Al-Hejji, S. (2006). “Causes of delay in large construction projects.” International Journal of Project Management, 24(4), 349–357. https://doi.org/10.1016/j.ijproman.2005.11.010 (accessed Nov 2026) ↩
- aeaweb.orgBajari, P., Houghton, S. and Tadelis, S. (2014). “Bidding for Incomplete Contracts: An Empirical Analysis of Adaptation Costs.” American Economic Review, 104(4), 1288–1319. https://www.aeaweb.org/articles?id=10.1257/aer.104.4.1288 (accessed Nov 2026) ↩↩
- isomer-user-content.by.gov.sgBuilding and Construction Authority — Public Sector Standard Conditions of Contract for Construction Works 2020 (8th edition, July 2020): definitions (Contract Sum, Provisional Sum Items), clauses 4.6, 5.1, 5.2, 14.2(i), 19.1–19.3, 20.1–20.5, Option Module A (Bills of Quantities). https://isomer-user-content.by.gov.sg/338/5349d125-0337-4dc3-a36d-623e599f2865/1-psscoc-for-construction-works-2020.pdf (accessed Nov 2026) ↩↩↩↩↩↩↩↩↩
- scl.org.sgTan Xian Ying and Yap Xuan Wei (Chancery Law Corporation), Society of Construction Law (Singapore) — “When is a written instruction not a condition precedent for a successful variation claim?” (April 2023), discussing Vim Engineering Pte Ltd v Deluge Fire Protection (S.E.A.) Pte Ltd [2023] SGHC(A) 2, Mansource Interior Pte Ltd v CSG Group Pte Ltd [2017] 5 SLR 203 and Fongsoon Engineering (S) Pte Ltd v Kensteel Engineering Pte Ltd [2011] SGHC 82. https://scl.org.sg/public-resources/articles-menu/923-when-is-a-written-instruction-not-a-condition-precedent-for-a-successful-variation-claim (accessed Nov 2026) ↩↩
- sia.org.sgSingapore Institute of Architects — Building Contracts Committee (SIA Building Contract 2016 suite). https://sia.org.sg/building-contracts-committee/ (accessed Nov 2026) ↩
- designingbuildings.co.ukDesigning Buildings Wiki — “The difference between a prime cost sum and a provisional sum.” https://www.designingbuildings.co.uk/wiki/The_difference_between_a_prime_cost_sum_and_a_provisional_sum (accessed Nov 2026) ↩↩↩
- sso.agc.gov.sgBuilding and Construction Industry Security of Payment Act 2004, ss 7, 11(3), 15(3), 17(3). Singapore Statutes Online. https://sso.agc.gov.sg/Act/BCISPA2004 (accessed Nov 2026) ↩↩↩
- bibbase.orgCapen, E. C., Clapp, R. V. and Campbell, W. M. (1971). “Competitive Bidding in High-Risk Situations.” Journal of Petroleum Technology, 23, 641–653. Bibliographic record: https://bibbase.org/network/publication/capen-clapp-campbell-competitivebiddinginhighrisksituations-1971 (accessed Nov 2026) ↩
- ideas.repec.orgDyer, D. and Kagel, J. H. (1996). “Bidding in Common Value Auctions: How the Commercial Construction Industry Corrects for the Winner’s Curse.” Management Science, 42(10), 1463–1475. https://ideas.repec.org/a/inm/ormnsc/v42y1996i10p1463-1475.html (accessed Nov 2026) ↩
Use this guide in a report, a tender or a by-law briefing. Please link to the page so readers get the current version.