A&A and Fit-Out Approvals in Singapore: Who Approves What, and When
Most Singapore fit-outs and A&A works need several separate clearances: BCA for structural and non-exempt building works, SCDF for anything touching fire safety (plan approval, or a $90 minor A&A lodgement for small works), URA for change of use or external changes, the landlord, JTC or MCST, plus licensed electrical workers, licensed plumbers and gas workers for services. A Qualified Person coordinates the statutory submissions.

Addition and alteration (A&A) works and interior fit-outs in Singapore are regulated by at least five agencies and one private gatekeeper, and each of them asks a different question. The Building and Construction Authority (BCA) asks whether the building will still stand up and whether the works are of a kind that needs plans at all. The Singapore Civil Defence Force (SCDF) asks whether people can still escape and whether fire protection still works. The Urban Redevelopment Authority (URA) asks whether the use and the outside of the building are still what was planned. The landlord, JTC or the Management Corporation Strata Title (MCST) asks whether you are allowed to touch their building at all. Then EMA, PUB and the Ministry of Manpower (MOM) govern who may do the electrical, plumbing, gas and high-risk work.
The mistake owners and tenants most often make is to treat “approval” as a single event. It is a set of parallel and sequential clearances, some of which (a $90 SCDF lodgement, a no-submission insignificant building work) are quick, and some of which (structural plan approval, change of use, conservation permission) shape the whole programme. This guide maps them: which works trigger which approval, who prepares and submits each one, what the published processing times are, and where projects typically go wrong.
It is written for non-residential premises (offices, retail, industrial and institutional buildings) with notes for condominium units. It reflects the rules as at 9 November 2026, including the expanded list of insignificant building works that took effect on 1 April 2025 and BCA’s outdoor signage changes that took effect on 2 November 2026. If you want a quick first pass for your own project, the Approval Navigator lets you tick the kinds of work you plan and shows the approvals likely to apply.
64% of the construction sector’s fatal and major injuries in 2025 happened on smaller-scale works such as A&A and renovation (95 of 148), against 45 on regular construction sites34
Small jobs are where the risk concentrates. MOM’s 2025 figures show that injuries on A&A and renovation works fell only slightly year on year (103 to 95), while regular construction sites improved faster (60 to 45).34 The same pattern shows up in buildings: the mezzanine that collapsed in a Toa Payoh warehouse in January 2025, trapping three people, had been installed without BCA or SCDF approval.32 Approvals and an independent engineer are not paperwork reserved for big projects; on a small job they are often the only check there is.
The cast: who does what on an A&A project
Before the agencies, the people. Almost every statutory submission in Singapore must come from a Qualified Person (QP): a Registered Architect with the Board of Architects or a Professional Engineer (PE) with the Professional Engineers Board, holding a valid practising certificate.6 The QP prepares and signs the plans, submits them, and supervises the works the plans cover. Which QP is “appropriate” depends on the work; for structural plans, only a PE in the civil or structural discipline can apply.4
| Role | Who they are | What they do on an A&A job |
|---|---|---|
| Qualified Person (QP) | Registered Architect or PE with a practising certificate | Prepares and submits BCA, SCDF and other plans; supervises the works; certifies completion |
| PE (civil/structural) | PE registered in civil or structural engineering | Structural assessment, structural plans, Appendix D certificate for A&A that does not affect structural stability |
| Accredited Checker (AC) | Independent checking engineer accredited by BCA | Certifies structural plans where works materially affect key structural elements, e.g. strengthening4 |
| Registered Inspector (RI) | Senior architect or PE registered with SCDF | Inspects completed fire safety works before the TFP or FSC is issued13 |
| Licensed builder | BCA-licensed General Builder (GB1 or GB2) or Specialist Builder | Required for building works whose plans need BCA approval; GB2 limited to projects of S$6 million or less8 |
| Licensed electrical worker (LEW) | EMA-licensed electrician, technician or engineer | All electrical work; the “appointed LEW” takes charge of a licensed installation23 |
| Licensed plumber (LP) | PUB-licensed plumber | Regulated water service and sanitary plumbing works22 |
| Licensed gas service worker (LGSW) | EMA-licensed | Installation, testing, maintenance and repair of gas appliances on piped gas24 |
| Fire Safety Manager (FSM) | Building’s appointed FSM, where the building requires one | Building-side fire safety oversight; usually vets tenant works in practice |
A practical point: the QP’s statutory duties run to the regulator and the public, not just to whoever pays the fee. That is why the question of who appoints the engineer matters, and why we cover it in PE endorsement explained.
BCA: building works, structural works and what is exempt
The default rule and the penalties behind it
Under the Building Control Act, building works need approved plans and, for structural works, a permit. Section 20(1) makes it an offence to commence or carry out, or to permit or authorise, building works whose plans have not been approved, or for which no permit under section 6 is in force. The maximum is a fine of S$200,000, imprisonment of up to two years, or both, plus up to S$1,000 a day while the contravention continues and S$2,000 a day if it continues after conviction.7 Breaching a condition of an approval or permit carries up to S$20,000 or 12 months.7 Separately, section 21 lets the Commissioner of Building Control impose a pecuniary penalty of up to 10 times the prescribed plan fees, whether or not there is a prosecution.7
Insignificant building works: the exemption list
The exemption is narrower than many contractors assume. BCA calls works that need no plan submission insignificant building works, and they are exactly the items in the First Schedule of the Building Control Regulations 2003 — nothing more.1 That list was expanded for works carried out on or after 1 April 2025.3 The items that matter most for fit-outs are:
| First Schedule item | What is exempt | Key conditions |
|---|---|---|
| 1(o) | Creating an opening in a non-load-bearing wall, or sealing up a wall opening | Wall must carry no load other than its own weight |
| 1(p) | Demolition, restoration or reinstatement of a non-load-bearing wall | As above |
| 2 | Replacing windows and doors | — |
| 3 | Replacing existing floor and wall finishes | — |
| 4 | Installing or replacing a false ceiling | Suspended from the structural ceiling; lightweight; purely aesthetic (incl. concealing services); not accessible to any person; supporting system spans no more than 6 m |
| 4A | Demolishing a suspended false ceiling | — |
| 6 | Erecting or altering partitions up to 10 m high | Outside landed houses, partitions must be lightweight material |
| 7 | Raised floors and topping up balconies | Lightweight materials |
| 9 | Roller shutters or grilled doors | — |
| 12 | All air-conditioning works | — |
| 15 | Forming an opening in a slab for building services | Not in a cantilever slab, flat slab or prestressed element; at-grade slab, or opening no more than 150 mm (diameter or side) and at least 450 mm from the edge of any existing opening |
| 1(za) | Single-level storage platform in an industrial building | Not public; max 4 m high and 50 m²; beam/slab spans max 6 m, cantilever max 3 m |
Source for the table: the First Schedule as currently in force.2 “Lightweight material” is defined to include timber board, plywood, plasterboard, gypsum board, calcium silicate board, fibre-based cement board, metal sheet, lightweight-aggregate concrete products, and hollow or autoclaved aerated concrete blocks.2 A “non-load bearing wall” is one that supports no load other than its own weight.2
Two cautions. First, “exempt from BCA plan submission” does not mean exempt from anything else. BCA itself reminds owners that insignificant works must still comply with safety and good practice, other agencies’ requirements such as URA’s, caveats and MCST by-laws.1 Second, the exemption depends on facts the contractor often cannot see: whether a wall is really non-load-bearing, or whether a slab is post-tensioned. Item 15 expressly excludes flat slabs and prestressed elements for a reason. Our companion guide on hacking walls, slabs and household shelters covers how to tell.
When the works are structural
If the works touch structure — new openings in reinforced concrete walls or slabs beyond item 15, removing beams or columns, new mezzanines outside item 1(za), new heavy plant loads, strengthening — you need structural plan approval and a permit to carry out structural works.45
- Only a QP who is a PE in the civil or structural discipline can apply for structural plan approval.4
- For A&A works where the building’s structural stability or integrity is not affected, BCA asks for PE-endorsed plans with a certificate in the form of its “Appendix D”.4
- Where works materially affect key structural elements (BCA gives strengthening works as an example), an Accredited Checker’s certificate is required.4
- Plans without AC certification are processed within 7 working days of a complete submission; plans with AC certification within 10 days for a first submission and 14 working days for subsequent ones; joint submissions in CORENET X’s Construction Gateway within 20 working days.4
- The permit is applied for jointly by the developer, the QP and the builder, together with or after plan approval, and is processed within 7 working days of complete documents.5
BCA’s pages note that CORENET X was to be mandatory for all new projects by 1 October 2026,5 so confirm with your QP which portal your submission now uses.
Some small structures can use BCA’s lodgment scheme instead of full approval: works listed in the Ninth Schedule, such as certain single-level platforms up to 4 m high and 100 m², lodged by a QP who declares compliance. False declarations are offences, and supervision and permit requirements still apply.30
Building plans for non-structural A&A
Works that are neither insignificant nor structural (for example, changes to escape staircases, accessibility provisions or building envelope) need building plan approval through a QP. BCA requires the QP to obtain URA’s written permission first where planning permission is needed.6 Since 1 April 2023, civil defence shelter aspects are included in building plan and structural plan submissions rather than submitted separately.6
SCDF: fire safety plan approval, minor A&A lodgement, and the FSC
What counts as “fire safety works”
SCDF requires plan approval for fire safety works, which it describes as including: installing, altering, removing or relocating fire protection systems such as hose reels, sprinklers and fire doors; design or layout changes affecting escape routes or fire compartments; works involving combustible materials, air-conditioning or ventilation, or LPG for non-residential use; and change of use where the new use affects fire safety requirements.9 Under section 55 of the Fire Safety Act, the person for whom the works are proposed applies for plan approval through an appropriate QP; carrying out fire safety works before approval, or otherwise than in accordance with approved plans, carries a maximum fine of S$200,000, two years’ jail, or both.12
The minor A&A lodgement route
For small works in buildings that already hold a Temporary Fire Permit (TFP) or Fire Safety Certificate (FSC), regulation 4(4) of the Fire Safety (Building and Pipeline Fire Safety) Regulations replaces plan approval with a lodgement, as long as the works fall within the regulations’ Schedule.10 The QP (a Registered Architect, or a PE in civil, structural, mechanical or electrical engineering) lodges the plans on CORENET before work starts, and SCDF says works may proceed after lodgement.11 The fee is S$90.10 The applicant or tenant must obtain consent from the building owner or MCST first.11
| Typically lodgeable (subject to conditions) | Not lodgeable — needs full SCDF plan approval |
|---|---|
| Internal partitions within an individual unit (a shop, an office, or a room up to 200 m² on the approved plan) | Anything affecting fire resistance of elements of structure, or compartment walls and fire doors |
| False ceiling replacement, relocation or addition | Works posing additional fire hazard |
| Raised floor up to 150 mm deep, total within the unit not exceeding 200 m² | Anything affecting wet or dry risers or landing valves |
| Up to 9 sprinkler heads replaced, relocated or added (not OH3 or high hazard) | More than 9 sprinkler heads, or OH3/high-hazard sprinklers |
| Detectors, alarm bells, call points, exit signs, emergency lights, extinguishers, hose reels | Sprinklers or detectors along common areas of buildings with sleeping risk (hospitals, hotels, dormitories) |
| Non-fire-rated ACMV ducts and fans | ACMV works in exit staircases, smoke-free or fire lift lobbies, pump or generator rooms, engineered smoke control or smoke purging |
| Ancillary pantry, toilet, store up to 20 m² or ancillary office, without increasing occupancy load | Any other change of use, any increase in floor area, any conservation project |
Source: the Schedule, paragraphs 1, 2 and 4 to 7.10 For partition works in units other than shops and offices, the result must not be a room larger than 200 m².10 Paragraph 2 items (such as sprinklers and detectors) are not available for “excluded buildings”: places of large public congregation such as religious premises, childcare and healthcare premises, and buildings with high fire loads or hazards.10
The QP’s title-block certification on the lodged plans is a real undertaking: either that the works do not affect the existing fire protection system, or that the QP supervised the modification of the sprinkler or fire alarm system.11
Completion: TFP, FSC and the Registered Inspector
Where fire safety works went through plan approval, the building cannot simply be reoccupied when the contractor leaves. The owner must engage a Registered Inspector (RI) to inspect and certify the works; the QP then applies on CORENET for the TFP or FSC. There is no application fee, SCDF responds within three working days, and it may select the project for inspection, usually within 10 days.13 Using or occupying premises without the FSC is an offence.13 Our SCDF fire safety guide for fit-outs covers this stage, the common failure points and the RI’s role in detail.
S$90 SCDF fee per minor A&A lodgement10
URA: planning permission, change of use and conserved buildings
Planning permission and its exemptions
URA’s starting point is that planning permission is required for development and building works, including changing the use of premises.14 Its exemption list removes most interior fit-out from that net. For non-residential buildings, the list exempts re-partitioning or re-arranging approved uses within tenanted areas (as long as there is no change in primary use, quantum or floor area, and common areas are not affected), lightweight partitions, false ceiling replacement, floor and wall finishes, air-conditioning works, external painting, and works that do not materially affect the external appearance or floor area.15 Replacement windows and doors are exempt where there is no GFA increase or setback reduction.15 Signboards are exempt except on the façade of national monuments or buildings in a conservation area.15 The list carries carve-outs, notably for conserved buildings and monuments, and URA tells owners to check other authorities and comply with caveats, by-laws and MCST rules.15
So the URA triggers on a fit-out are usually three: a change of use, anything that changes the external appearance or adds floor area (a new shopfront projection, enclosing a terrace, a mezzanine that counts as GFA), and any work to a conserved building.
Change of use
URA’s guide gives a simple example — shop to commercial school — and says such a change may require planning permission, assessed against Master Plan zoning, prevailing guidelines and the impact on neighbours.16 The owner, landlord, consultant or QP applies through GoBusiness with the owner’s letter of consent (and JTC’s, HDB’s or SLA’s where they are the landlord). The processing fee is S$500, non-refundable, and decisions generally take 10 working days, longer if the submission is incomplete or other agencies are consulted.16 URA’s most practical advice is easy to skip: do not commit to the tenancy or renovation works before you have URA’s decision.16
A change of use is also a fire safety event. Section 61 of the Fire Safety Act requires prior approval for a change of use that would make the existing fire safety measures inadequate, with a maximum of S$200,000, two years’ jail, or both.12 An office converted to a classroom or a store converted to a showroom changes occupant load, exit capacity and sometimes sprinkler hazard class, so the QP should assess SCDF requirements at the same time as the URA application.
Conserved buildings
Work on a building in a conservation area needs Conservation Permission from URA, regardless of whether BCA plans are required.17 URA sorts works into three categories:
| Category | Examples | Who submits | Published decision time |
|---|---|---|---|
| 1 — affects key elements | Roof profile restoration, rear extension, changing an entire upper floor, structural strengthening | QP who is a Registered Architect | Within 20 working days |
| 2 — lesser effect on key elements | Pergola with non-load-bearing cover, airwell window, internal staircase or lift | QP (Registered Architect or PE) | Within 20 working days |
| 3 — minimal, localised or repair | One-for-one doors/windows, security grilles, repainting façade, changing business signs | Owner or contractor (no QP needed) | About two weeks; free of charge |
Source: URA conservation submission guidance.17 For Category 3 works, no work may start before Conservation Permission is issued; for Category 1 and 2 works, BCA building plan approval and the permit follow URA’s permission.17
The bar that was a restaurant
In Public Prosecutor v Project Lifestyle Pte Ltd [2015] SGHC 251, a café operator in the Kampong Glam conservation area changed the premises from a restaurant to a bar without conservation permission, after earlier assurances to URA. It pleaded guilty under section 12 of the Planning Act and was fined S$20,000; on the prosecution’s appeal the High Court raised the fine to S$35,000, noting persistent offending and likely profits, and observing that a non-aggravated change of use typically starts at around S$5,000 to S$10,000.19 The cost chain here is not just the fine: it is the period of non-compliant trading, the regulatory attention, and a tenancy built around a use that was never approved. Today, section 12(4) of the Planning Act allows fines of up to S$200,000 plus up to S$10,000 a day for continuing offences after conviction.18
The private gatekeepers: landlord, JTC and MCST
Statutory approval does not give you the right to work in someone else’s building. Every commercial lease, JTC tenancy and strata development adds its own layer, and it usually comes first.
Commercial landlords typically require a fit-out submission with drawings, method statements, insurances, a deposit and the contractor’s credentials before any work. SCDF’s minor A&A guidance makes landlord or MCST consent an express precondition of lodgement.11 Building managers commonly run their own permit-to-work and hot-work systems and set working hours for noisy trades; these are contractual, not statutory, but a breach can stop a job as effectively as a regulator. See working in live premises for how this plays out in occupied malls, offices and fabs.
JTC requires tenants carrying out A&A works in its buildings to obtain JTC’s plan consent and clearances from the relevant authorities. Its handbook sorts works into List A (no JTC consent needed, but other authorities’ submissions still required), List B (QP endorsement on plans required) and List C (no QP endorsement), and submissions go through CORENET.21 For new partitions, JTC asks for deadweight, thickness and height, a PE (civil) endorsement, and for works affecting fire protection installations, SCDF’s notice of approval.21
MCSTs regulate works through by-laws. BCA’s strata management guide explains that MCSTs may require approval before works in a lot, PE endorsement for structural works, and evidence of URA, SCDF and Commissioner of Building Control approvals; works affecting the appearance or structural integrity of the building need MCST authorisation under section 37(4) of the Building Maintenance and Strata Management Act (renamed the Building (Strata Management) Act from 1 October 2025, when its maintenance duties moved into the Building Control Act); and works that affect gross floor area need a 90% resolution at a general meeting.20
Before you sign a fit-out contract
- Obtain the landlord’s, JTC’s or MCST’s fit-out rules, by-laws and submission checklist, and diarise their review period.
- Confirm the approved use of the unit (URA’s Enquiry on Approved Use) and whether your intended use is in the same use class.
- Ask the building owner for the latest approved floor plan and fire protection layout, and whether the building holds a TFP or FSC.
- Have a QP or PE confirm in writing which items are insignificant building works, which need BCA submission, and whether SCDF lodgement or full plan approval applies.
- Identify any structural works early (openings, coring, mezzanines, heavy equipment) and get a PE’s view before finalising the layout.
- Check whether the electrical load change affects the building’s or your own electrical installation licence and who the appointed LEW is.
- Allow for licensed plumber, gas worker and LEW engagement in the contractor’s scope.
- Build agency processing times and resubmission risk into the programme before committing to a handover or opening date.
Services: electrical, plumbing and gas
Electrical works (EMA)
EMA’s licensing regime is about who may do the work and who is responsible for the installation. Only licensed electrical workers may design, install, repair, maintain, inspect and test electrical installations, within their class: licensed electricians up to 45 kVA at 1,000 V and below; licensed electrical technicians up to 150 kVA (design) and 500 kVA (operation); licensed electrical engineers without load limit, subject to licence conditions.23 Non-domestic installations with an approved load above 45 kVA (equivalent to 63 A three-phase at 400 V) need an electrical installation licence, and the licensee must appoint an LEW of the appropriate class, inform the appointed LEW of any modification, and ensure that any electrical work is carried out only by an LEW.23 A different LEW may carry out fit-out modifications, but must coordinate connection and disconnection with the appointed LEW and hand over the completed works.23 Tenants who buy electricity en bloc through the landlord or MCST are generally covered by the landlord’s licence.23
Plumbing and sanitary works (PUB)
PUB requires all regulated water service and sanitary plumbing works to be carried out by PUB-licensed plumbers, and since 1 April 2018 it has been an offence for anyone to engage an unlicensed plumber for such works.22 A short list of simple works (replacing taps and mixers, some cistern parts, installing or replacing wash basins and floor traps, clearing blockages) may be done by handymen.22 New sanitary works can also need PUB clearance through a QP; ask your QP or licensed plumber which applies before the layout is fixed, because toilet and pantry positions are often constrained by existing stacks and floor traps.
Gas works (EMA)
Since 14 February 2008, the installation, testing, maintenance and repair of gas appliances connected to piped gas must be done by a licensed gas service worker, who certifies the appliance safe for use; employing or instructing an unlicensed worker is an offence with a maximum fine of S$10,000, imprisonment, or both.24 For F&B fit-outs, gas and LPG installations are also fire safety matters for SCDF.9
Site safety and environmental requirements
Fit-outs are construction work, and the Workplace Safety and Health (WSH) regime applies.
- Work at height. Under the WSH (Work at Heights) Regulations, a permit-to-work is required for work where a person could fall more than 3 metres, in workplaces defined as factories, which include construction worksites.26 Where the fall risk is controlled by adequate edge protection, a permit may not be required.26 See work-at-height law and occupier liability.
- Scaffolds. Scaffolds with a height of 4 metres or more at the uppermost lift (excluding handrails) must be erected, altered and dismantled by an MOM-approved scaffold contractor; tower and trestle scaffolds are excluded from this requirement.27
- Asbestos. In older buildings, suspected asbestos-containing materials must be removed by an approved asbestos-removal contractor, who must notify MOM at least one week before removal starts, with a plan of work and survey results.28
- Noise. NEA sets noise limits for construction sites, progressively stricter after 7 pm and 10 pm; for residential buildings within 150 m the Monday-to-Saturday limits are 75 dBA (Leq 12 hours) from 7 am to 7 pm, 65 dBA (Leq 1 hour) from 7 pm to 10 pm, and 55 dBA (Leq 1 hour) from 10 pm to 7 am.25 In occupied commercial buildings the binding constraint is usually the landlord’s house rules. Our guide to construction noise and working hours has the detail.
Signage and façade changes
Outdoor signs are a separate licensing system run by BCA. A licence is needed to display an outdoor advertising sign or signboard; a single signboard or series of related signboards with a total area of not more than 5 m² is exempt by declaration.29 Applications go through BCA’s Advertisement Licensing System with the owner’s and MCST’s endorsement; BCA typically assesses complete applications in 7 working days, with about two more weeks if URA evaluation is needed.29 Amendments in force from 2 November 2026 redefine “signboard” as a structure displaying only informational content about the premises, introduce an express approval scheme, and raise the maximum fine from S$5,000 to S$20,000 with up to 12 months’ imprisonment.33 Heavier signs and their supports also raise structural questions; see signboards and structures needing PE endorsement.
The big matrix: who approves what
This is the summary most readers want. “Likely” means the approval is commonly triggered by that kind of work; whether it applies to your job depends on the specific conditions discussed above, and a QP should confirm.
| Kind of work | BCA | SCDF | URA | Landlord / JTC / MCST | Licensed worker / other |
|---|---|---|---|---|---|
| Lightweight partitions (non-landed, up to 10 m) | Exempt (First Schedule item 6) | Minor A&A lodgement, or plan approval if exits, compartments or >9 sprinklers affected | Exempt if no change in use or floor area | Consent required | — |
| Remove or open a non-load-bearing wall | Exempt (items 1(o), 1(p)) — if truly non-load-bearing | As above if layout or escape affected | Exempt | Consent required | PE check advisable |
| Openings in RC walls, beams, columns; coring beyond item 15 | Structural plan approval + permit; AC if key elements materially affected | Plan approval if compartment floors or walls are breached | — | Consent; MCST authorisation for structural works | PE (civil/structural) as QP |
| False ceiling change | Exempt if item 4 conditions met | Lodgement (ceiling, up to 9 sprinklers) or plan approval | Exempt (replacement) | Consent | — |
| Exits, escape routes, fire doors, compartment walls | Building plan approval may apply | Full plan approval; RI inspection; TFP/FSC | — | Consent | — |
| Change of use (e.g. office to school, store to showroom) | Possibly (if building works) | Prior approval if fire safety measures become inadequate | Change-of-use application (S$500) if use class changes | Owner’s letter of consent; JTC/HDB/SLA letter | Business licences follow |
| Mezzanine, platform or occupant-accessible racking | Structural plans + permit, unless lodgment scheme or item 1(za) applies | Plan approval (treated as a floor under the Fire Code) | May add GFA | Consent | PE |
| Shopfront, façade, windows, awnings | Exempt for like-for-like windows/doors; else plans | If external wall fire separation affected | Planning permission if external appearance or GFA materially changed | Consent; MCST for appearance | — |
| Outdoor signboard | Signage licence (unless ≤5 m² exempt) | — | Evaluation for some signs; conservation areas | Endorsement | PE if structural support needed |
| Electrical (new DBs, circuits, sockets) | — | Fire alarm interfaces may need SCDF | — | Landlord’s LEW coordination | LEW; EI licence above 45 kVA non-domestic |
| Plumbing and sanitary | — | — | — | Consent | PUB-licensed plumber; PUB clearance for some sanitary works |
| Gas appliances and piping | — | LPG/gas fire safety works | — | Consent | Licensed gas service worker |
| Work in a conserved building | Plans as applicable | As applicable | Conservation Permission (Category 1, 2 or 3) | Consent | — |
| Asbestos removal in strip-out | — | — | — | Consent | Approved asbestos-removal contractor; MOM notification ≥1 week |
| Work at height above 3 m; scaffolds ≥4 m | — | — | — | Building permit-to-work | MOM permit-to-work; approved scaffold contractor |
| Household or storey shelter | Plans for shelter A&A in houses | SCDF permission needed for any impairing work | — | MCST | See shelter guide |
Sequencing: a realistic order of play
How a well-run A&A approval sequence usually runs
- Collect the record information: approved floor plans, approved use, fire protection layouts, structural drawings, and the landlord’s or MCST’s rules. Gaps here are the single biggest cause of later redesign.
- Freeze the use and the layout concept, then have the QP classify every work item: insignificant, BCA submission, SCDF lodgement or approval, URA, licensed-worker only.
- If the use changes, apply to URA for change of use first and do not sign the tenancy or start works until URA decides; in parallel, have the QP assess SCDF implications.
- Submit to the landlord, JTC or MCST for their technical review; their comments often change details that the statutory plans must reflect.
- Have the PE survey and, where needed, scan structure before submitting structural plans; obtain structural plan approval and the permit before any structural works start.
- Submit SCDF plans (or lodge minor A&A works) and obtain approval or complete lodgement before the affected works start.
- Mobilise with the safety documentation in place: risk assessment, permits-to-work, scaffold contractor, LEW, licensed plumber, and any asbestos notification.
- Build to the approved plans, with QP supervision; route any design change back through the QP before it is built.
- On completion, the RI inspects fire safety works and the QP applies for the TFP or FSC; LEW, plumber and gas worker certify their works; the landlord or MCST conducts its handover inspection.
How long does this take? The published agency service standards are short: 7 working days for a complete structural plan without AC certification, 7 working days for the permit,45 around 10 working days for a URA change of use,16 20 working days for URA Category 1 and 2 conservation decisions,17 and 3 working days for SCDF’s response to a TFP or FSC application.13 What makes approvals feel slow is everything around those clocks: incomplete submissions, landlord review cycles, written directions and resubmissions, and design changes after submission. The guide on realistic fit-out timelines quantifies where those weeks go.
How RRD approaches this
On A&A and fit-out jobs, RRD’s site survey and itemised quotation list the approval-dependent items separately — structural openings, coring, sprinkler and ceiling changes, signage — so the owner can see which costs and dates depend on approvals before signing. Where a QP or PE is needed, RRD recommends that the owner appoint the engineer directly, and RRD does not mark up engineering fees. Works that need an approval are not started until the approval or permit is in hand.
Independent engineer's note
The QP signs the statutory certificates and owes duties to the Commissioner and the public. When the engineer is appointed and paid by the owner, the engineer’s findings (for example, that a wall is structural after all, or that sprinkler changes exceed the lodgement limit) reach the owner directly and early, while there is still time to adjust the layout. RRD’s usual independent engineering partner is CVC Engineers, a Singapore PE consultancy covering civil and structural design, PE endorsement and submissions, SCDF submissions and regularisation of unauthorised works; owners are free to appoint any PE. More on this model on our independent engineer page.
What goes wrong, and how to avoid it
Starting before the permit
The most common and most expensive error is mobilising the hacking crew before the structural permit is issued, usually because the handover date was fixed before the approvals plan was. Section 20 exposure attaches to whoever permits or authorises the works, not only the contractor.7 If you discover works that should have been approved, our guide to regularising unauthorised works sets out the route.
Assuming “lightweight partition” means “no approval”
A drywall partition is a BCA insignificant work, but it can still be an SCDF matter if it creates a new room that pushes travel distance beyond the Fire Code limit, blocks sprinkler coverage, or encloses an exit route. SCDF’s own enforcement material lists unapproved partitions among common offences and highlights escape routes, sprinkler and detector coverage and travel distances as the points a QP must assess.31
Mezzanines and racking
SCDF treats racking systems, platforms and mezzanines accessible to occupants as a floor or storey under the Fire Code, so they need QP assessment and plan approval before installation.31
The mezzanine nobody approved (sourced public event)
On 28 January 2025, a mezzanine floor and storage racks in a warehouse unit at 11 Toa Payoh Industrial Park collapsed, trapping three people, including two children, under rugs and racks; four people were taken to hospital. The Straits Times later reported that SCDF found no Fire Safety Certificate for the mezzanine, and that BCA had received no applications for the steel platform and racking system; the tenant said a vendor had installed it in May 2024.32 Both agencies said investigations were ongoing. The cost chain of an unapproved mezzanine runs from injury and rescue, through stop-work and investigation, to removal or regularisation of the structure, before any question of liability between tenant, vendor and landlord is even reached.
Change of use discovered at licensing stage
Tenants sometimes complete a fit-out and only then apply for the operating licence, only to learn the use is not approved for the unit. URA’s guidance to secure its decision before committing to tenancy or renovation exists precisely to avoid that.16
Services done by the wrong people
Sockets added by a general worker, a water heater installed by a handyman, a gas hob connected by the kitchen supplier: each is a licensed-worker breach.222324 They also tend to surface at the worst time, during the landlord’s handover inspection or an insurer’s claim review.
Conservation buildings treated like any shophouse
Changing a business sign or repainting a shophouse façade in a conservation area is a Category 3 matter needing Conservation Permission before the work.17 Owners who treat these as routine maintenance often learn otherwise from a URA notice.
Using this guide
Approvals are where programme risk and legal risk meet. The safest approach is to classify every work item at the design stage, get the QP’s written classification, and keep the approval status visible in the programme. For a structured first pass, use the Approval Navigator; for terms used here, see the glossary; and for the specific technical areas, continue with structural hacking and household shelters and SCDF fire safety for fit-outs. If you are planning A&A works, our addition and alteration services page describes how we scope them.
Questions people ask
Do I need BCA approval to put up office partitions?
Usually not. Under the First Schedule of the Building Control Regulations, erecting or altering a partition up to 10 metres high is an insignificant building work if, outside landed houses, it is built of lightweight material such as gypsum board, calcium silicate board or hollow blocks. Insignificant works need no BCA plan submission. The partitions may still need SCDF lodgement or approval if they change rooms, exits, sprinkler coverage or compartmentation, and they always need your landlord's or MCST's consent.
What is the SCDF minor A&A lodgement, and when can I use it?
It is a lodgement route for small fire safety works listed in the Schedule to the Fire Safety (Building and Pipeline Fire Safety) Regulations, in a building that already has a Temporary Fire Permit or Fire Safety Certificate. A Registered Architect or Professional Engineer lodges the plans through CORENET for a S$90 fee and works may proceed after lodgement. It cannot be used if the works affect compartmentation, fire-rated elements, risers, floor area, conservation buildings, or involve more than 9 sprinkler heads.
My new tenant wants to turn an office into a tuition centre. Who needs to approve?
Several parties. URA must approve a change of use that moves the premises into a different use class, through a GoBusiness application costing S$500 that generally takes 10 working days. Under the Fire Safety Act, a change of use that makes existing fire safety measures inadequate needs SCDF approval before it happens, so a QP should assess occupant load and exits. The landlord or MCST must consent, and licensing agencies follow. URA advises not committing to tenancy or renovation before its decision.
Can my contractor submit the plans instead of a QP?
For statutory building plans, structural plans and SCDF fire safety plans, no. Submissions must be made by a Qualified Person, meaning a Registered Architect or Professional Engineer of the appropriate discipline holding a valid practising certificate. Structural plans can only be submitted by a PE in the civil or structural discipline. Contractors may lodge some non-QP items, such as URA Category 3 conservation works or JTC 'List C' submissions, and can coordinate the process, but they cannot replace the QP's statutory role.
How long do approvals for a typical office fit-out take?
There is no single answer because each agency runs its own clock. Published BCA service standards are 7 working days for a complete structural plan without an Accredited Checker and 7 working days for the structural works permit; URA's change-of-use decisions generally take 10 working days; SCDF responds to TFP and FSC applications within 3 working days. Landlord reviews, resubmissions, design changes and the time taken to prepare a complete submission usually dominate, so build float into the programme.
Are approvals needed for electrical and plumbing changes in a fit-out?
Yes, in the form of licensed workers rather than plan approvals. EMA requires electrical work to be done by a licensed electrical worker, and non-domestic installations above 45 kVA must hold an electrical installation licence with an appointed LEW who must be told of modifications. PUB requires regulated water service and sanitary plumbing works to be done by a PUB-licensed plumber, and engaging an unlicensed plumber has been an offence since 1 April 2018.
What happens if works start before approval?
Carrying out building works without approved plans or a permit is an offence under section 20 of the Building Control Act, with a maximum fine of S$200,000, two years' jail, or both, plus daily fines for continuing offences. Fire safety works without SCDF approval carry similar maximums under the Fire Safety Act. Authorities can order works stopped, corrected or removed, and regularisation after the fact usually costs more than doing it in sequence.
Does a condo owner need MCST approval for internal renovations?
Often, yes. BCA's strata guide explains that MCSTs can make by-laws requiring approval before works in a lot, including PE endorsement for structural works and proof of URA, SCDF and BCA approvals. Works affecting the building's appearance or structural integrity need MCST authorisation, and works that increase gross floor area need a 90% resolution at a general meeting. Check your development's by-laws and renovation rules before engaging a contractor.
Sources
34 sources. Official sources are marked dark. Links were checked when this guide was last updated.
- bca.gov.sgBuilding and Construction Authority — “Building works not requiring approval”. https://www1.bca.gov.sg/guidelines-and-requirements/building-works-not-requiring-approval/ (accessed Nov 2026) ↩↩
- sso.agc.gov.sgBuilding Control Regulations 2003, First Schedule (Insignificant building works), as in force. Singapore Statutes Online. https://sso.agc.gov.sg/SL/BCA1989-S666-2003?ProvIds=Sc1- (accessed Nov 2026) ↩↩↩
- isomer-user-content.by.gov.sgBuilding and Construction Authority — Circular APPBCA-2025-01, “Notification of Changes to the Building Control Regulations 2003 – Building Control (Amendment No. 3) Regulations 2024”, 2 January 2025. https://isomer-user-content.by.gov.sg/338/8e92ce63-64fa-4540-ac71-0ce1f8fe1803/circular-on-notification-of-changes-to-the-building-control-regulations-2003—building-control-(amendment-no-3)-regulations-2024.pdf (accessed Nov 2026) ↩
- bca.gov.sgBuilding and Construction Authority — “Permit for structural works”. https://www1.bca.gov.sg/safety-and-standards/applications-and-licenses/permit-for-structural-works/ (accessed Nov 2026) ↩↩↩↩
- bca.gov.sgBuilding and Construction Authority — “Building plan submission”. https://www1.bca.gov.sg/safety-and-standards/applications-and-licenses/building-plan-submission/ (accessed Nov 2026) ↩↩↩
- lawplayer.comBuilding Control Act 1989, sections 20 (building offences) and 21 (pecuniary penalty), compiled text. https://lawplayer.com/sg/act/BCA1989/20 and https://lawplayer.com/sg/act/BCA1989/21 (accessed Nov 2026) ↩↩↩↩↩
- bca.gov.sgBuilding and Construction Authority — “Builders Licensing Scheme (BLS)”. https://www1.bca.gov.sg/safety-and-standards/applications-and-licenses/builders-licensing-scheme-bls/ (accessed Nov 2026) ↩
- scdf.gov.sgSingapore Civil Defence Force — “Plans and consultations”. https://www.scdf.gov.sg/home/fire-safety/plans-and-consultations (accessed Nov 2026) ↩↩
- scdf.gov.sgSingapore Civil Defence Force — “Minor Addition & Alteration Works”. https://scdf.gov.sg/home/fire-safety/plans-and-consultations/minor-addition-alteration-works (accessed Nov 2026) ↩↩↩↩
- lawplayer.comFire Safety Act 1993, Part 4 (sections 55 to 62), compiled text. https://lawplayer.com/sg/act/FSA1993 (accessed Nov 2026) ↩↩
- scdf.gov.sgSingapore Civil Defence Force — “Fire Safety Certificate & Temporary Fire Permit”. https://www.scdf.gov.sg/home/fire-safety/permits-and-certifications/fire-safety-certificate-temporary-fire-permit (accessed Nov 2026) ↩↩↩↩
- ura.gov.sgUrban Redevelopment Authority — “Planning Permission”. https://www.ura.gov.sg/guidelines/development-control/planning-permission/ (accessed Nov 2026) ↩
- ura.gov.sgUrban Redevelopment Authority — “Exemptions from planning permission”. https://www.ura.gov.sg/guidelines/development-control/planning-permission/dasub/exemption/ (accessed Nov 2026) ↩↩↩↩
- lawplayer.comPlanning Act 1998, section 12, compiled text. https://lawplayer.com/sg/act/PA1998/12 (accessed Nov 2026) ↩
- elitigation.sgPublic Prosecutor v Project Lifestyle Pte Ltd [2015] SGHC 251. https://www.elitigation.sg/gd/s/2015_SGHC_251 (accessed Nov 2026) ↩
- isomer-user-content.by.gov.sgBuilding and Construction Authority — Strata Management Guide 14, “Carrying Out Works in Lots – What You Should Know” (November 2023). https://isomer-user-content.by.gov.sg/338/6ab15b7b-0fbc-49fe-b2d0-c937e709dcf1/bca_guide-14_carrying_out_works_in_lots.pdf (accessed Nov 2026) ↩
- jtc.gov.sgJTC Corporation — “Space Submission Handbook” (PCP-WI-09). https://www.jtc.gov.sg/-/media/project/jtc-cx/corpweb/assets/get-help/space-submission-handbook.pdf (accessed Nov 2026) ↩↩
- pub.gov.sgPUB, Singapore’s National Water Agency — “Plumbing Works”. https://www.pub.gov.sg/Professionals/Requirements/Licensed-Plumbers/Plumbing-Works (accessed Nov 2026) ↩↩↩↩
- ema.gov.sgEnergy Market Authority — “Handbook for Application of Electrical Installation Licence”. https://www.ema.gov.sg/content/dam/corporate/resources/educational-materials/handbook/handbook-pdfs/english/EMA-Resources-Educational-Materials-Handbook-Application-Electrical-Installation-Licence.pdf (accessed Nov 2026) ↩↩↩↩↩↩
- ema.gov.sgEnergy Market Authority — Press release, “New Requirements under the Gas Act and Gas (Supply) Regulations (with effect from 14 February 2008)”, 13 February 2008. https://www.ema.gov.sg/content/dam/corporate/news/media-releases/2008/1254366042New%20Requirements%20under%20the%20Gas%20Act%20and%20Gas%20_Supply_%20Regula.pdf.coredownload.pdf (accessed Nov 2026) ↩↩↩
- nea.gov.sgNational Environment Agency — “Construction Noise Control”. https://www.nea.gov.sg/our-services/pollution-control/noise-pollution/construction-noise-control (accessed Nov 2026) ↩
- mom.gov.sgMinistry of Manpower — Factsheet, “Workplace Safety and Health (Work at Heights) (Amendment) Regulations 2014”. https://www.mom.gov.sg/~/media/mom/documents/safety-health/factsheet%20on%20wahamendmentregulations.pdf (accessed Nov 2026) ↩↩
- mom.gov.sgMinistry of Manpower — “Apply to be an approved scaffold contractor”. https://www.mom.gov.sg/workplace-safety-and-health/wsh-service-providers/scaffold-contractor/apply-to-be-an-approved-scaffold-contractor (accessed Nov 2026) ↩
- mom.gov.sgMinistry of Manpower — “Notify for asbestos work”. https://www.mom.gov.sg/workplace-safety-and-health/wsh-service-providers/asbestos-removal-contractor/notify-mom-for-hazardous-work/notify-for-asbestos-work (accessed Nov 2026) ↩
- bca.gov.sgBuilding and Construction Authority — “Outdoor advertising sign / signboard licence application”. https://www1.bca.gov.sg/safety-and-standards/applications-and-licenses/outdoor-advertising-sign-signboard-licence-application/ (accessed Nov 2026) ↩↩
- bca.gov.sgBuilding and Construction Authority — “Lodgment scheme” (building plan submission). https://www1.bca.gov.sg/safety-and-standards/applications-and-licenses/building-plan-submission/lodgment-scheme/ (accessed Nov 2026) ↩
- scdf.gov.sgSingapore Civil Defence Force — “Common Fire Safety Enforcement Findings”, FSM Seminar 2025. https://www.scdf.gov.sg/docs/default-source/fire-safety-docs/fire-safety-manager-(fsm)/fsm-2025/common-fire-safety-enforcement-findings.pdf (accessed Nov 2026) ↩↩
- stomp.sgThe Straits Times (republished by Stomp), “Toa Payoh warehouse floor that collapsed and trapped 3 people not approved by SCDF, BCA”, 9–10 February 2025. https://www.stomp.sg/singapore-seen/toa-payoh-warehouse-floor-that-collapsed-and-trapped-3-people-not-approved-by-scdf (accessed Nov 2026) ↩↩
- isomer-user-content.by.gov.sgBuilding and Construction Authority — Circular APPBCA-2026-08, “New Requirements under the Building Control (Outdoor Advertising) (Amendment) Regulations 2026”, 12 May 2026. https://isomer-user-content.by.gov.sg/338/16b862a8-af5d-46ba-be39-49fdd818ca38/NEW%20REQUIREMENTS%20UNDER%20THE%20BUILDING%20CONTROL%20(OUTDOOR%20ADVERTISING)%20(AMENDMENT)%20REGULATIONS%202026.pdf (accessed Nov 2026) ↩
- mom.gov.sgMinistry of Manpower — “Workplace Safety and Health Report 2025”, Key Facts and Tables (ii), (iii) and 3a. https://www.mom.gov.sg/-/media/mom/documents/safety-health/reports-stats/wsh-national-statistics/wsh-national-stats-2025.pdf (accessed Nov 2026) ↩↩
Use this guide in a report, a tender or a by-law briefing. Please link to the page so readers get the current version.