Unauthorised Building Works in Singapore: Penalties, Detection and How to Regularise
Unauthorised building works are works carried out without a required approval from BCA (plans or structural permit), SCDF (fire safety works) or URA (planning or conservation permission). They can attract fines of up to S$200,000 under each regime. To keep them, the owner appoints a Qualified Person to survey and assess the works and seek retrospective approval; otherwise they must be rectified or removed.

Unauthorised building works sit quietly in many Singapore properties: a wall removed during a renovation years ago, a steel mezzanine added to a warehouse unit, an enclosed balcony, a roof extension over a back yard, an extra opening punched through a slab for a staircase. They are often invisible in daily use. They become very visible when a building is sold, leased, inspected, insured, or when something fails.
The law treats these works seriously. Building works without approved plans or a permit, fire safety works without SCDF approval, and development without planning permission each carry maximum fines of S$200,000, and continuing offences attract daily fines.2107 More important for most owners is the practical consequence: the authorities can order works to stop, be altered, or be demolished, at the owner’s cost.4
This guide explains what counts as unauthorised, how such works surface, the penalties under each statute, and the regularisation process: the survey, structural assessment, retrospective submissions and rectification needed to bring a building back into compliance. It ends with common patterns and a due diligence checklist for buyers and tenants.
What counts as unauthorised building works
Three regulators, three different questions
“Unauthorised” is not one test. A single alteration can need approval from several agencies, each asking a different question.
| Regulator | The question it asks | Typical trigger | Statute |
|---|---|---|---|
| BCA (Commissioner of Building Control) | Is the work structurally safe and compliant with building regulations? | Building works needing plan approval; structural works needing a permit | Building Control Act 1989, ss 5, 6, 2052 |
| SCDF | Is the building still fire-safe? | Fire safety works; change of use affecting fire safety | Fire Safety Act 1993, ss 56, 6110 |
| URA | Is the use and floor area allowed by planning control? Is heritage protected? | New floor area, change of use, enclosures, works in conservation areas | Planning Act 1998, s 127 |
| HDB, MCST, landlord | Is the work allowed under the lease, by-laws or HDB rules? | Any renovation | Lease, by-laws, HDB renovation rules |
The Building Control Act defines “building works” widely: erection, extension or demolition of a building; alteration, addition or repair; and the provision or alteration of air-conditioning or ventilation systems, including fixed installation works.19 “Structural works” are works in relation to the structural elements of the building works.19
What does not need BCA plan submission
The Building Control Regulations list “insignificant building works” in their First Schedule. These do not need plan submission to BCA.1 The list has changed over time, so check the current First Schedule rather than relying on a contractor’s recollection. Even for exempt works, BCA reminds owners to check whether other authorities (for example URA) must clear the works, and to observe caveats and MCST by-laws.1
The most common misunderstanding is that “no BCA submission” means “no approval needed at all”. It does not. A non-structural partition may not need BCA plans but may affect fire compartments or escape routes, which is SCDF’s concern. See fire safety approvals for fit-outs and the approval navigator.
Offences and penalties
Building Control Act
| Offence | Maximum penalty | Provision |
|---|---|---|
| Commencing, carrying out, permitting or authorising building works without approved plans or without a structural permit | S$200,000, 2 years, or both; plus up to S$1,000 a day while it continues; up to S$2,000 a day after conviction | s 20(1)2 |
| Breaching a condition of plan approval or permit | S$20,000, 12 months, or both; daily fines | s 20(2)2 |
| Material deviation from approved plans (each person directly concerned) | S$100,000, 2 years, or both | s 20(3)2 |
| Failing to comply with Commissioner’s order to stop, alter or demolish | S$20,000, 6 months, or both; up to S$500 a day; S$1,000 a day after conviction | s 19(5)4 |
| Pecuniary penalty instead of or alongside prosecution | Up to 10 times the prescribed plan approval fees | s 21(1)3 |
Section 19 gives the Commissioner power to order works halted, the building demolished, or alterations made to bring it into compliance, at the cost of the person served. For a completed building, the order is served on the owner or occupier; for works in progress, on the developer or builder. If the order is ignored, the Commissioner may do the work and recover the cost.4
Fire Safety Act
Carrying out fire safety works without first obtaining SCDF approval is an offence under section 56 of the Fire Safety Act 1993, punishable by a fine of up to S$200,000, imprisonment of up to 2 years, or both, with a further fine of up to S$1,000 a day if the offence continues after conviction. Failing to apply for a change of use of premises (section 61) carries the same maximum.10 Failing to obtain a Fire Safety Certificate where one is required has been reported to carry a fine of up to S$10,000.11
Planning Act
Development without planning permission, works in a conservation area without conservation permission, and subdivision without permission are offences under section 12. A first offence carries a fine of up to S$200,000, with up to S$10,000 a day if it continues after conviction; repeat offenders face up to S$200,000, 12 months’ imprisonment, or both. Where the contravention involves demolition in a conservation area, the maximum rises to S$500,000, 12 months, or both.7
Two further provisions matter to landlords. Under section 12A, an owner is presumed to have permitted unauthorised development carried out by a tenant or contractor, unless the owner proves reasonable precautions or due diligence.8 Under section 28, URA may serve an enforcement notice requiring buildings or works to be altered, demolished or removed, or a use stopped, with at least 14 days before it takes effect.9
How unauthorised works surface
Periodic structural inspections
Under the Building Control (Periodic Inspection of Buildings and Building Façades) Regulations 2021, the structural engineer carrying out a periodic structural inspection (PSI) must personally survey the condition of the building, the loading on the structure, and “evidence of any structural works” carried out without prior approval of plans.13 PSI is required every 5 years for non-residential buildings and every 10 years for residential buildings, with landed houses used exclusively for residence exempt.14 An engineer who finds unapproved structural works must report them. See the PSI owner’s guide.
Periodic façade inspections
The periodic façade inspection (PFI) regime, in force since 1 January 2022, covers buildings more than 13 metres tall once they are over 20 years old, every seven years.15 A competent person inspecting the façade will see enclosed balconies, added canopies, ledge enclosures and new external fixings. Many exterior items, including awnings, shading devices, signboards installed for more than 36 months and brackets for externally mounted equipment, are prescribed “exterior features” with maintenance obligations.18 Check scope with the PFI checker and the PFI guide.
Sale, purchase and leasing
Conveyancing searches only go so far. BCA states that a legal search by a conveyancing lawyer will only yield unauthorised works that have been brought to BCA’s attention and does not guarantee there are none. BCA recommends that buyers engage a competent person such as an architect or engineer to inspect the property against the approved plans, which can be bought from BCA through its Plan Purchase Application Form.1
Insurance claims, incidents and complaints
After a leak, fire, collapse or injury, loss adjusters and investigators ask whether the affected part was approved. Neighbours’ complaints and feedback to agencies also prompt inspections; in the Desker Road case described below, URA inspected after receiving feedback.12 For new properties, works done without approvals can delay the Certificate of Statutory Completion.1
New A&A works
When an owner later applies for approval of new alterations, the QP surveys the existing building. Unapproved earlier works become the new QP’s problem, because QPs must notify the Commissioner of contraventions they know of or ought reasonably to know of.20 The developer commissioning the new works carries a parallel duty to notify the Commissioner of contraventions it knows of or ought reasonably to know of.6 Many regularisations begin this way. See which approvals A&A works need.
Two sourced public events
Toa Payoh warehouse mezzanine collapse, January 2025 (public event)
On 28 January 2025, a mezzanine floor and storage racks collapsed inside a warehouse unit at 11 Toa Payoh Industrial Park, trapping three people; four people, including two children, were taken to hospital. BCA said it had received no applications for the steel platform and racking system. SCDF inspections found that no Fire Safety Certificate had been obtained for the mezzanine. BCA said the partial collapse did not affect the structural integrity of the building.11
The cost chain in incidents like this runs well beyond fines: emergency response, injuries, investigation, removal of the structure, loss of stock and use of the unit, insurance disputes, and potential liability across tenant, installer and owner.
Unauthorised works to a conserved shophouse, 2026 (public event)
In April 2026, URA announced that an individual and the property owner were fined S$250,000 and S$150,000 respectively for unauthorised works to a conserved shophouse at 32 Desker Road, Little India. The works included demolishing the first-storey residential front, the rear façade and service block, and the original internal timber staircase. The owner must also reinstate and restore the building at its own cost. URA described it as the first prosecution for unauthorised works on a conserved building since the 2017 Planning Act amendments introduced stiffer penalties.12
The regularisation process
Regularisation means bringing unauthorised works into compliance: obtaining retrospective approval where the works can comply, modifying them until they do, or removing them and reinstating the approved condition.
Regularising unauthorised works
- Stop and secure. Stop any further work on the affected area. If there is any sign of distress (cracking, deflection, overloading), restrict use and get an engineer to inspect immediately.
- Appoint a Qualified Person. Appoint a PE (and an architect where planning or layout issues arise) directly, under your own appointment. Verify them on the PEB register. See PE endorsement and independence.
- Obtain the approved plans. Buy the approved plans from BCA, and gather URA and SCDF approvals, the strata plan and any earlier A&A approvals.1
- Measured as-built survey. Survey and draw what is actually built: dimensions, member sizes, connections, openings, finishes, services, and current use and loading.
- Gap analysis. Compare as-built against approved plans and list every deviation, classified by regulator (BCA structural, BCA non-structural, SCDF, URA, MCST or landlord).
- Structural assessment. The PE checks the unauthorised elements and the existing structure that supports them. This often needs intrusive investigation (opening up finishes, rebar scanning, coring, material testing, load tests) because original design information is missing.
- Decide: keep, modify or remove. Based on the assessment and on planning and fire safety constraints, decide what can be retained, what must be strengthened or altered, and what must go.
- Retrospective submissions. The QP submits plans to the Commissioner of Building Control, and the relevant submissions to SCDF and URA. BCA may impose a pecuniary penalty of up to 10 times the plan fees; once accepted, the covered works are treated as not having contravened section 20.3
- Rectification works. Carry out strengthening, alteration or removal under the approvals and permits, supervised by the QP, by a builder with the appropriate licence.
- Completion and records. Obtain completion certification and any Fire Safety Certificate needed, update the building’s records, and file the approved plans where the next buyer, tenant or PSI engineer can find them.
Keep, modify or remove
| Situation | Likely route | Notes |
|---|---|---|
| Works comply structurally, with fire safety and planning control | Retrospective approval | Drawings, calculations, submissions; possible s 21 penalty3 |
| Structurally inadequate but planning and fire acceptable | Strengthen, then approve | Design of strengthening; permit for structural works5 |
| Exceeds allowable floor area or prohibited by planning control | Remove or reduce | URA can require removal by enforcement notice9 |
| Compromises fire compartments or escape routes | Redesign to fire code, or remove | SCDF approval needed before fire safety works10 |
| In a conservation area | Restore, as directed | URA may require restoration to former state9 |
Cost drivers
There is no standard price for regularisation, and any figure quoted before investigation is a guess. The main drivers are:
- Information gap. Missing original drawings mean more survey and testing.
- Access and disruption. Opening up finishes in an occupied unit costs time and reinstatement.
- Structural outcome. Whether the element passes as built, needs strengthening, or must be removed is the single largest variable.
- Number of regulators. Each additional agency adds submissions, fees and time.
- Authority penalties. A pecuniary penalty under section 21 is calculated by reference to plan fees.3
- Business interruption. Lost use of space, overrun on a lease, or delayed sale often exceeds the construction cost. For tenants near lease expiry, see the late-handback cost calculator.
Illustrative example: a tenant discovers a 40 m² steel mezzanine in a leased unit two months before handback. Survey and assessment take three weeks; the engineer concludes connections are inadequate and recommends removal rather than strengthening. If removal and reinstatement push handback back one month at a rent of S$15,000 a month, holding-over costs alone can rival the removal works. Illustrative figures only; actual outcomes depend on the lease and the findings.
Common patterns (composite scenarios)
The scenarios below are composites drawn from common situations, not specific incidents.
Removed or shortened walls
Composite scenario. A previous owner removed a wall between kitchen and living area to create an open plan. It was a load-bearing wall, or a wall that braced the structure. Ten years later, the new owner applies to add a skylight and the QP’s survey flags the missing wall. Regularisation means confirming whether the wall was structural, designing a beam or frame to replace it, and submitting plans. See hacking walls, slabs and household shelters for walls that must never be touched, such as household shelter walls.
Mezzanines and storage platforms
Composite scenario. An industrial tenant installs a steel platform and racking from a catalogue supplier. Nobody checks whether the existing slab can take the column point loads, whether the new floor area is allowed, or whether escape distances still work. Mezzanines raise all three regulators’ questions at once: structure (BCA), fire safety (SCDF), and floor area (URA). The Toa Payoh incident above shows the stakes.11
Roof extensions and covered yards
Composite scenario. A landed house owner roofs over the back yard and adds walls to create a storeroom. What began as a shelter is now enclosed floor area. The structure may be light, but fixings into the existing building, drainage, and floor area under planning control all need checking. Enclosures can also affect natural ventilation and lighting of adjacent rooms.
Enclosed balconies and AC ledges
Composite scenario. A condominium owner encloses a balcony with full-height glass panels for air-conditioning. URA’s guidelines state that balconies are semi-outdoor spaces and shall not be enclosed with walls or glass panels; only approved balcony screens that can be fully opened and allow airflow at all times may be allowed.16 AC ledges have their own floor area rules, and how they are treated for gross floor area depends on whether they are strata area.17 Converting either into indoor space changes the planning position and the façade, and may be picked up at PFI.
Signage and external structures
Composite scenario. A tenant installs a large illuminated sign and a steel canopy above a shopfront. The sign has no licence and the canopy has no engineer’s design; brackets are bolted into cladding rather than the structure behind it. Signboards and canopies are exterior features with maintenance obligations, and a fallen exterior feature that injures someone or damages property must be reported to BCA within 6 hours.18 See signage and structures.
Unapproved openings in slabs and walls
Composite scenario. A fit-out adds an internal staircase between two floors by cutting a slab opening, and later a services contractor cores several large holes through a beam for ductwork. Each opening interrupts load paths. Openings in structural elements are structural works requiring plans and a permit, and coring through beams can cut reinforcement. Regularisation usually requires scanning, recalculation and, often, strengthening with steel trimmers or fibre-reinforced polymer.
How to avoid creating unauthorised works
Preventing unauthorised works on your project
- Before any alteration, ask a QP which approvals are needed (BCA, SCDF, URA, MCST, landlord, HDB) and get the answer in writing. Use the approval navigator as a first pass.
- Appoint the engineer yourself and pay them directly, so the person certifying compliance answers to you.
- Do not let works start until the permit to carry out structural works, where needed, is in force.5
- Treat any on-site change to structure, layout or fire safety as a formal change requiring the QP’s review; material deviation from approved plans is itself an offence.2
- Require your contractor to keep approved plans on site and to stop if a QP leaves the project; the Act requires both.20
- For tenants: obtain landlord consent with the approval requirements stated, and keep copies of all approvals for handback. See the reinstatement guide.
- For landlords: require evidence of approvals before tenant works start and inspect at handback, because owners are presumed to have permitted a tenant’s unauthorised development.8
Buying or leasing: due diligence checklist
Due diligence before you buy or lease
- Ask your lawyer to raise legal requisitions, but do not rely on them alone: they only show unauthorised works known to BCA.1
- Purchase the approved building plans from BCA and, where relevant, obtain the URA approval and strata plan.1
- Engage an architect or PE to walk the property against the approved plans, looking for removed walls, new openings, mezzanines, enclosures, roof extensions and added external structures.
- Ask the seller or landlord for all A&A approvals, permits, completion certificates and Fire Safety Certificates for past works.
- For buildings in the PSI or PFI regimes, ask for the latest inspection reports and check whether unapproved works or defects were reported.1315
- Check the intended use against the approved use; a change of use may need URA and SCDF approval.10
- Price regularisation into your offer or make it a condition, and clarify in the contract who bears rectification if works are later found.
- For leases, record the existing condition (including any unauthorised works) in a schedule of condition so you are not asked to reinstate what you did not build.
Independent engineer's note
Regularisation depends on an engineer whose job is to establish what is really there, even when the answer is expensive. That engineer should be appointed and paid by the owner, not by the contractor who will price the remedial works. RRD recommends owners appoint the engineer directly; the engineer contracts with and invoices the owner, RRD adds no mark-up to engineering fees, and the owner may appoint any PE. RRD’s usual independent engineering partner is CVC Engineers, a Singapore PE consultancy whose work includes regularisation of unauthorised works (15+ regularisation projects), PE endorsement and submissions, and periodic structural inspections. See /independent-engineer/.
How RRD approaches this
At the site survey, RRD records existing conditions that appear to differ from approved plans and tells the owner before quoting, rather than building over them. Where regularisation is needed, RRD recommends the owner appoint the PE directly and prices the rectification or removal works only after the engineer’s assessment, listing cost-risk items in an itemised quotation. Works are carried out under the approvals obtained, with a joint inspection and handover of records at completion.
Questions people ask
What counts as unauthorised building works in Singapore?
Any building works carried out without an approval the law requires. For BCA that means works without approved plans or, for structural works, without a permit to carry them out. For SCDF it means fire safety works without approved plans or without a Fire Safety Certificate where one is needed. For URA it means development, change of use or works in a conservation area without planning or conservation permission. Works listed as insignificant building works do not need BCA plan submission but may still need other clearances.
I bought the property with the unauthorised works already there. Am I responsible?
Usually, yes, for dealing with them. BCA's guidance states that owners with unauthorised additions or alterations commit an offence and are subject to enforcement action, and the Commissioner's orders for a completed building are served on the owner or occupier. Previous owners or contractors may also face action where there is evidence, but the practical burden of rectification or regularisation normally falls on the current owner. This is why pre-purchase inspection matters.
Can unauthorised works be approved after the event?
Often, if they can be shown to comply. BCA's guidance is that an owner who wishes to keep unauthorised works should engage a Qualified Person to submit plans to the Commissioner of Building Control for approval, and obtain other approvals such as URA's. Section 21 of the Building Control Act allows the Commissioner to impose a pecuniary penalty of up to 10 times the plan approval fees; once accepted, the covered works are treated as not having contravened section 20. Works that cannot meet the requirements must be modified or removed.
Will my lawyer's legal requisition reveal unauthorised works?
Only partly. BCA states that a legal search will only show unauthorised building works that have already been brought to BCA's attention, and does not guarantee that there are none. BCA recommends engaging a competent person, such as an architect or engineer, to inspect the property and compare it against the approved plans, which owners can purchase from BCA.
How are unauthorised works usually discovered?
Common routes include periodic structural inspections (the engineer must look for evidence of structural works done without approved plans), periodic façade inspections, buyer or tenant due diligence, insurance claims after an incident, complaints from neighbours or feedback to agencies, agency inspections, and A&A submissions for new works where the Qualified Person surveys existing conditions. Incidents such as a collapse also trigger investigations.
What does regularisation cost?
It depends on what was built and whether it complies. The main cost drivers are the as-built survey, intrusive investigation and testing, the engineer's assessment and submissions, any authority fees or pecuniary penalty, strengthening or rectification works, and the business disruption while works are carried out. A simple non-structural item may only need drawings and a submission; an undersized mezzanine may need strengthening or removal. Get the engineer's assessment before pricing remedial works.
Is a mezzanine in a warehouse unit a building work?
A mezzanine or steel platform that adds floor area or loads the existing structure is a building work under the Building Control Act and generally needs plan approval and a structural permit, along with SCDF approval for fire safety works and possibly URA clearance on floor area. In January 2025 a mezzanine floor collapsed in a Toa Payoh warehouse unit; BCA said it had received no applications for the platform and SCDF found no Fire Safety Certificate had been obtained.
Does the tenant or the landlord bear liability for a tenant's unauthorised works?
Both can be exposed. Under the Planning Act, an owner is presumed to have permitted unauthorised development carried out by a tenant or contractor unless the owner proves reasonable precautions or due diligence. Under the Building Control Act, anyone who carries out, permits or authorises unapproved works commits an offence. Leases normally make tenants liable to the landlord for reinstatement. Landlords should require approvals before works start and check them at handback.
Sources
20 sources. Official sources are marked dark. Links were checked when this guide was last updated.
- bca.gov.sgBuilding and Construction Authority — “Building works not requiring approval” (insignificant building works; checking for unauthorised works; plan purchase; enforcement). https://www1.bca.gov.sg/guidelines-and-requirements/building-works-not-requiring-approval/ (accessed Nov 2026) ↩↩↩↩↩↩↩↩
- lawplayer.comBuilding Control Act 1989, section 20 (Building offences). https://lawplayer.com/sg/act/BCA1989/20 (accessed Nov 2026); official: https://sso.agc.gov.sg/Act/BCA1989 ↩↩↩↩↩↩
- lawplayer.comBuilding Control Act 1989, section 21 (Pecuniary penalty). https://lawplayer.com/sg/act/BCA1989/21 (accessed Nov 2026) ↩↩↩↩
- lawplayer.comBuilding Control Act 1989, section 19 (Commissioner’s orders: stop work, demolish, alter). https://lawplayer.com/sg/act/BCA1989/19 (accessed Nov 2026) ↩↩↩
- lawplayer.comBuilding Control Act 1989, sections 5 and 6 (plan approval; permit to carry out structural works). https://lawplayer.com/sg/act/BCA1989/5 and https://lawplayer.com/sg/act/BCA1989/6 (accessed Nov 2026) ↩↩↩
- lawplayer.comBuilding Control Act 1989, section 8 (Duties of developers, including s 8(3) duty to notify contraventions). https://lawplayer.com/sg/act/BCA1989/8 (accessed Nov 2026) ↩
- lawplayer.comPlanning Act 1998, section 12 (Unauthorised development, works and subdivision). https://lawplayer.com/sg/act/PA1998/12 (accessed Nov 2026) ↩↩↩
- lawplayer.comPlanning Act 1998, section 12A (Presumption of permitting unauthorised development). https://lawplayer.com/sg/act/PA1998/12A (accessed Nov 2026) ↩↩
- lawplayer.comPlanning Act 1998, section 28 (Enforcement notices). https://lawplayer.com/sg/act/PA1998/28 (accessed Nov 2026) ↩↩↩
- police.gov.sgSingapore Police Force — media release of 13 November 2024 on multi-agency enforcement, Annex B (Fire Safety Act 1993, ss 56 and 61 penalties). https://www.police.gov.sg/Media-Hub/News/2024/20241113_15_persons_arrested_and_11_persons_under_investigation_multi-agency_enforcement (accessed Nov 2026) ↩↩↩↩↩
- stomp.sgStomp (reporting The Straits Times) — “Toa Payoh warehouse floor that collapsed and trapped 3 people not approved by SCDF, BCA”, February 2025. https://www.stomp.sg/singapore-seen/toa-payoh-warehouse-floor-that-collapsed-and-trapped-3-people-not-approved-by-scdf (accessed Nov 2026) ↩↩↩
- ura.gov.sgUrban Redevelopment Authority — media release PR26-30, unauthorised works to a conserved shophouse at 32 Desker Road, 22 April 2026. https://www.ura.gov.sg/news/media/pr26-30/ (accessed Nov 2026) ↩↩
- littdb.sfo2.cdn.digitaloceanspaces.comBuilding Control (Periodic Inspection of Buildings and Building Façades) Regulations 2021, regulation 6(2). Mirror of SSO text: https://littdb.sfo2.cdn.digitaloceanspaces.com/litt/SG/SSOStatutes/subsidiary_legislation/BCA1989-S785-2021.html (accessed Nov 2026) ↩↩
- bca.gov.sgBuilding and Construction Authority — “Periodic Structural Inspection”. https://www1.bca.gov.sg/regulatory-info/building-control/periodic-structural-inspection (accessed Nov 2026) ↩
- bca.gov.sgBuilding and Construction Authority — “New Regulations for Periodic Inspection of Building Façades to start from 1 January 2022”. https://www1.bca.gov.sg/resources/newsroom/new-regulations-for-periodic-inspection-of-building-fa-ades-to-start-from-1-january-2022/ (accessed Nov 2026) ↩↩
- ura.gov.sgUrban Redevelopment Authority — Development Control Handbook, “Balconies, Private Enclosed Spaces, Private Roof Terraces and Indoor Recreation Spaces”. https://www.ura.gov.sg/guidelines/development-control/development-control-handbooks/residential/flats-condominiums/balconies-pes-prt/ (accessed Nov 2026) ↩
- ura.gov.sgUrban Redevelopment Authority — Development Control Handbook, Gross Floor Area, “Ledges”. https://www.ura.gov.sg/guidelines/development-control/development-control-handbooks/gross-floor-area/ledges/ (accessed Nov 2026) ↩
- littdb.sfo2.cdn.digitaloceanspaces.comBuilding Control (Meaning of Exterior Features) Regulations 2021, regulation 2; and Building Control (Reportable Matters) Regulations 2025, regulation 6(b) and Second Schedule Part 4. https://littdb.sfo2.cdn.digitaloceanspaces.com/litt/SG/SSOStatutes/subsidiary_legislation/BCA1989-S784-2021.html and https://isomer-user-content.by.gov.sg/338/388b1ec9-0e2e-424e-9087-0c0a66f25535/bc(reportable-matters)_regs_2025-(v03)-printae64b1f1a01e421fb18cd40e205a26d5.pdf (accessed Nov 2026) ↩↩
- lawplayer.comBuilding Control Act 1989, section 2 (definitions of “building works” and “structural works”). https://lawplayer.com/sg/act/BCA1989/2 (accessed Nov 2026) ↩↩
- lawplayer.comBuilding Control Act 1989, sections 9 and 11 (duties of qualified persons and builders). https://lawplayer.com/sg/act/BCA1989/9 and https://lawplayer.com/sg/act/BCA1989/11 (accessed Nov 2026) ↩↩
Use this guide in a report, a tender or a by-law briefing. Please link to the page so readers get the current version.