Defects in a New Condo or Landed Home Bought from a Developer: The 12-Month DLP, Your Rights and How to Claim
A private home bought from a licensed developer has a 12-month defects liability period under the prescribed Sale and Purchase Agreement, starting from vacant possession or 15 days after you receive the TOP or CSC papers, if earlier. The developer must fix notified defects within one month; if not, give 14 days' notice with a quotation, then rectify and deduct the cost from the 5% stakeholding.

Collecting the keys to a new home is the start of a 12-month clock that most buyers do not realise is running. Within that period, the developer must fix defects you report, and you have a statutory-form contract that tells both sides exactly what to do if it does not. After that, your leverage drops sharply: the money held back for defects is released, the contractors move to other projects, and every remaining issue becomes a negotiation or a claim.
This guide explains the defects regime for private homes bought from a licensed housing developer in Singapore, using the prescribed Sale and Purchase Agreement (SPA) in the Housing Developers Rules. It covers the 12-month defects liability period (DLP), the one-month rule, your right to rectify and deduct, common-property defects and the management corporation’s role, what BCA can and cannot do, CONQUAS and the Quality Mark, how to document defects, and the routes to resolve a dispute through the Strata Titles Boards or the courts.
Two points of scope. HDB flats bought from HDB are not sold under these Rules and are outside this guide. And clause numbers below are those in the current prescribed forms; SPAs signed under earlier versions of the Rules may number clauses differently, so check your own agreement.
The legal framework: the Housing Developers Rules and the prescribed SPA
Licensed housing developers must use the SPA forms prescribed by the Housing Developers Rules:
- Form 4 for a unit not intended to be a lot in a strata title plan (typically landed homes in a non-strata development); and
- Form 5 for a unit intended to be a lot in a strata title plan (condominiums, apartments and strata landed homes).1
The forms cannot be changed except with the Controller of Housing’s prior written approval, or where the form itself permits it; unapproved changes are void (rule 12(3)–(4)). The Singapore Academy of Law (SAL) acts as stakeholder under both forms (rule 12(5)).1 That makes the defects clause a statutory-standard term: buyers of different projects get the same core protection.
The key definitions in Form 5:
- The developer must build the unit and the common property “in a good and workmanlike manner” according to the Specifications and the approved plans (cl 9.1).1
- A defect is any fault in the building due to defective workmanship or materials, or to the building not being constructed according to the Specifications.1
The 12-month DLP: when it starts and what it covers
Clause 17.1 of Form 5 requires the developer to make good, at its own cost, any defect in the unit, the housing project, the common property or limited common property that becomes apparent within the DLP. The DLP is 12 months after the earlier of:
- (a) the date the developer actually delivers vacant possession; or
- (b) the 15th day after the buyer receives the documents in item 3 of the Payment Schedule, namely the TOP or CSC (or a certified copy) and the notice that the building, roads, drainage and sewerage are complete and utilities connected.1
So the DLP does not always start on key collection. If you delay collecting keys after receiving the TOP papers, the DLP still starts on the 15th day. When vacant possession is delivered, the developer must give a Notice of Vacant Possession stating the date (cl 12.3).1 Maintenance charges start on the same trigger date (cl 13.1).1
Form 4 for non-strata homes has the same 12-month structure for defects “in the Building”.1
12 months defects liability period in the prescribed developer SPA1
What counts, and what does not
BCA’s CONQUAS fact sheet notes that some things owners see as defects may not be treated as major defects in BCA’s assessments: subjective views (for example the tonality of timber or natural stone), design preferences and material durability outside CONQUAS scope, and damage from failing to protect or maintain the unit after completion.6 Under the SPA, the test is the contractual one: defective workmanship or materials, or departure from the Specifications. A hairline variation in stone colour is unlikely to qualify; hollow tiles, water seepage, faulty windows and failing sealant usually will.
The developer’s duty to rectify and your right to step in
Clauses 17.2 to 17.4 of Form 5 set out a precise sequence.1
| Step | Who | Time allowed | SPA clause |
|---|---|---|---|
| 1. Notice requiring the developer to make good a defect | Buyer | Any time within the DLP | 17.1–17.2 |
| 2. Developer makes good | Developer | Within 1 month of receiving the notice | 17.2 |
| 3. If not done: second notice with estimated cost (from a building or renovation contractor’s quotation) and the buyer’s intention to have the work done | Buyer | After the 1 month | 17.2(a)–(b), 17.3 |
| 4. Developer’s last chance | Developer | 14 days immediately after the date of the notice | 17.2(b) |
| 5. Buyer rectifies and recovers the cost; may deduct it from the SAL stakeholding | Buyer | After the 14 days | 17.4 |
Source: Housing Developers Rules, Form 5, cl 17.1
Using the step-in right correctly
- Notify in writing. List each defect with location and photographs. The SPA requires every notice to be in writing (cl 1.2.1), and allows delivery to a party’s solicitors (cl 1.2.2).1
- Give the developer access. Record the dates offered and whether its contractor attended.
- Count one month from the developer’s receipt of the notice, not from the date you sent it.
- Get a written quotation from a building or renovation contractor for each unremedied item.
- Serve the second notice with a copy of the quotation and your statement that you will have the works done if the developer does not complete them within 14 days.
- Wait 14 days. If the developer still has not fixed the defect, engage your contractor and keep invoices and before-and-after photographs.
- Recover the cost, either by deduction from the stakeholding (below) or as a claim against the developer.
Two cautions from the courts. First, a defects clause does not take away your right to damages at common law unless it says so expressly. Second, a buyer who unreasonably blocks the developer’s attempts to rectify can breach the clause. In Thio Keng Thay v Sandy Island Pte Ltd [2019] SGHC 175, the buyer of a Sentosa bungalow under the prescribed SPA alleged 492 defects, of which the developer admitted over 200. The High Court found the developer in breach, but also held that the buyer had breached the defects clause by unreasonably rejecting rectification method statements, which was relevant to how much he could recover.9 Follow the sequence; do not short-circuit it.
The 5% stakeholding and the notice of deductions
The last 15% of the purchase price is paid around completion and CSC. Under the Form 5 Payment Schedule, part of it goes to the SAL as stakeholder, and 5% is held until the Final Payment Date: 12 months after the same trigger that starts the DLP. On that date the stakeholder pays the developer the 5%, or the 5% less all authorised deductions.1 The exact flow depends on whether legal completion and the CSC come before or after the Final Payment Date; in some sequences the buyer pays the 5% directly after the developer’s notice of the Final Payment Date, with any notified deductions going to the stakeholder instead. Either way, the deduction mechanism is the same.1
To make a deduction:
- Serve a notice of deductions on the stakeholder and the developer on the same day, and at least 7 working days before the Final Payment Date (cl 5.4–5.5).1
- If the developer disputes all or part, it must serve its own notice on the stakeholder and buyer at least one working day before the Final Payment Date (cl 5.6–5.7).1
- The stakeholder then pays the undisputed deductions to the buyer and keeps the disputed amount pending settlement of the dispute (cl 5.8).1
Illustrative example: on a S$1,500,000 condominium unit, the 5% stakeholding is S$75,000. If the buyer has validly rectified window-seal and bathroom-waterproofing defects at a quoted S$9,800 after the developer failed to act, a notice of deductions served in time can recover that sum from the stakeholding instead of through a lawsuit. Miss the 7-working-day deadline, and the S$75,000 is paid out to the developer on the Final Payment Date.
Composite scenario: the deadline that cost the leverage
A buyer collects keys and moves straight into renovation. The carpenter covers a hollow-sounding section of floor tiles with built-in cabinets, and a slow leak at the shower screen is sealed over by the renovation contractor. Eleven months later, tiles near the cabinets crack and the leak returns. The buyer emails the developer, but has no photographs from handover, no written notices from the first year, and does not know about the notice of deductions. The Final Payment Date passes and the 5% stakeholding is released. The developer says the tiles were disturbed by the carpentry works and the leak by the renovation contractor’s sealant. The buyer is left with a negotiation, not a deduction. This is a composite scenario, not a reported case.
Defects found after the DLP
The DLP is not the end of the developer’s liability.
- Notified but unfixed defects stay with the developer. BCA’s guidance for condo owners says a defect reported during the DLP remains the developer’s responsibility if it is still unresolved after the period.8 The SPA also provides that unfulfilled terms remain in effect after completion (cl 16.8).1
- New defects after the DLP can still found a claim for damages for breach of the developer’s building obligations, since the defects clause does not exclude common-law damages without express words.9
- Time limits apply. An action founded on contract or tort must generally be brought within 6 years of the cause of action accruing. For negligence and breach of duty, the period is the later of 6 years from accrual or 3 years from the date the claimant had the required knowledge, subject to a 15-year long-stop.10 For construction defects, the Appellate Division has described damage as occurring when defects manifest as physical damage to the building, and the knowledge required as “reasonable rather than absolute or certain”.11
The defects liability and retention guide explains these limitation rules in more detail.
Common-property defects and the MCST’s role
Defects in lobbies, roofs, façades, car parks, pools and external walls are often more expensive than anything inside a unit. Several layers of law apply.
The SPA. Form 5 clause 17.1 expressly covers defects in the housing project, the common property and limited common property, so each buyer can notify them during that buyer’s DLP.1 Because each buyer’s DLP is triggered by their own vacant possession or document date, start dates can differ across the estate. Owners and the management council should coordinate so that common-property notices are served while the earliest DLPs are still running.
The Building (Strata Management) Act 2004. This Act was formerly called the Building Maintenance and Strata Management Act; its short title changed on 1 October 2025.2 Relevant provisions:
- Section 21: appointing a managing agent to run the maintenance fund does not relieve the developer of its obligations towards purchasers to repair common property and make good defects in it, or to carry out works so that the development complies with the approved plans and with authorities’ requirements before the CSC.2
- Section 85: where owners are jointly entitled to take proceedings about the common property, the proceedings may be taken by the management corporation, but it must not institute them unless authorised by an ordinary resolution of the general body.2
- Section 86: gives the management corporation power to take proceedings as agent for an owner in certain cases of structural defects affecting support or shelter.2
Negligence. In RSP Architects, Planners & Engineers v Ocean Front Pte Ltd [1995] 3 SLR(R) 653, the Court of Appeal allowed a management corporation to recover pure economic loss for defective construction of a condominium, and RSP Architects v MCST Plan No 1075 (Eastern Lagoon) [1999] 2 SLR(R) 134 extended this to the building consultants.12 In MCST Plan No 4099 v KTP Consultants [2024] SGHC(A) 32, the Appellate Division allowed an MCST’s negligence claim against a structural engineer to proceed to trial on the limitation question.11
For a new MCST or management council: common-property defects
- Obtain the as-built drawings, warranties, test certificates and the developer’s defects log for the common property.
- Commission an independent survey of the common property early in the first year, while buyers’ DLPs are still running.
- Record each common-property defect with location, photographs and the date notified to the developer.
- Encourage owners to include common-property items in their own SPA notices before their DLPs expire.
- Track the developer’s responses in one register; escalate items not fixed within the SPA’s one-month period.
- If court or arbitration proceedings may be needed, put an ordinary resolution to the general body (s 85(1A)) and check limitation dates.
Independent engineer's note
For structural, waterproofing or façade defects in common property, the MCST’s survey should be done by a Professional Engineer or specialist the MCST appoints and pays directly, not by the developer’s builder or a contractor who hopes to win the repair work. An independent report is more persuasive in negotiations with the developer and before a tribunal or court. RRD’s usual independent engineering partner is CVC Engineers; MCSTs are free to appoint any PE. See the independent-engineer model.
Leaks between units are a special case. Under the Strata Management Act, in Strata Titles Board proceedings about a defect, dampness or water penetration on a ceiling raises a presumption that the defect is in the lot or common property above (s 101(8)).2 See inter-floor water seepage in condos.
BCA’s role and its limits
Buyers often expect BCA to order the developer to fix defects. That is not how the system works.
The answer also notes that TOP and CSC depend on the building meeting regulatory requirements, such as SCDF fire safety, BCA structural safety and PUB drainage and sewerage.3 A TOP is not a certificate that every tile and window is free of workmanship defects.
BCA’s influence on workmanship is indirect but real:
| Body | What it does on defects | What it does not do |
|---|---|---|
| Developer | Builds in a good and workmanlike manner; fixes notified defects within 1 month during the DLP | Its obligations are not displaced by appointing a managing agent (s 21) |
| Buyer | Notifies in writing; allows access; may step in after the cl 17.2 notices; serves notice of deductions | Cannot deduct without following the SPA steps and deadlines |
| Singapore Academy of Law | Holds the 5% stakeholding; pays out undisputed deductions; retains disputed sums | Does not decide who is right |
| MCST | Manages common property; may take proceedings with an ordinary resolution | Cannot sue on owners’ behalf without the resolution |
| BCA | Runs CONQUAS and the Quality Mark; publishes developer and builder bands; may facilitate meetings | Cannot intervene in private contractual disputes |
| URA (Controller of Housing) and BCA | Since 22 May 2026, may disqualify developers with consecutive projects with major defects from land sales or suspend sales | Does not order rectification in individual units |
| Strata Titles Board | Settles disputes about defects in lots and common property among owners, occupiers and the MCST | Orders are made on those parties, not on outsiders |
| Courts or arbitration | Decide contract and negligence claims, including against the developer | Require evidence and are slower and costlier |
Sources: Housing Developers Rules Form 5;1 Building (Strata Management) Act;2 MND;3 BCA;46 URA/BCA circular.7
The May 2026 measures against developers with major defects
On 22 May 2026, URA and BCA announced measures to strengthen deterrence of errant developer behaviour. Developers with consecutive projects with major defects, or with severe safety-related non-compliances, may be disqualified from land sales with a residential component, or placed on a sales-suspension list, for up to five years. The measures can extend to directors, substantial shareholders and related parties.7
“Major defects” here means defects attributable to the developer that were not promptly rectified and that significantly affect liveability or functionality under CONQUAS, such as broken window panes, shower screens, mirrors and glass, and visibly cracked tiles. The measures apply to defects the developer had sufficient and reasonable notice to rectify on or after 22 May 2026.7 For buyers, the practical point is that prompt written notice now matters beyond the SPA: it is the start of the record that regulators look at.
CONQUAS and the Quality Mark
Both are BCA schemes, and both are often misunderstood.
| CONQUAS | Quality Mark (QM) | |
|---|---|---|
| What it is | National standard for assessing construction workmanship quality, introduced 1989 | Certification of good workmanship for private homes, launched 1 July 2002 |
| What is assessed | A sample of units; internal finishes, installation methods and functional tests (e.g. bathroom waterproofing, windows), external finishes | Every unit of the project; internal finishes, plus ponding tests for bathrooms and toilets |
| Output | Project score and, since 25 May 2023, a band for developers and builders from Band 1 to Band 6 | Certificate listing units scoring at least 85 out of 100 and free of major defects and water seepage |
| Mandatory? | Required on Government Land Sales sites since 1992, public projects above S$5 million since 1998, and new or poorly performing developers since November 2019 | Mandatory for residential GLS sites sold on or after 30 June 2022 and certain incentive schemes; otherwise voluntary |
| Where to check | BCA’s Quality Housing Portal | Ask the developer for the QM certificate for your unit |
Sources: BCA CONQUAS page;5 BCA CONQUAS banding fact sheet;6 BCA Quality Mark page.4
Points worth knowing:
- Banding reflects track record. A firm’s band is based on its average CONQUAS scores over the past six years. BCA’s data show Band 1 projects averaging 0.6 dwelling units with major defects per 1,000 units.6
- Homeowner feedback counts. BCA validates homebuyer feedback on major defects after inspection, and that feedback is considered in project bands.6 A project’s QM rating may also be downgraded if BCA receives valid complaints about major workmanship defects.4
- CONQUAS keeps changing. BCA enhanced the scheme on 1 June 2022 to address water seepage, ponding at common areas and glass shattering, introduced a 3-tier scheme for private residential applications from 9 October 2019, and launched CONQUAS (Private Residential) in November 2025.65
- Neither is a warranty. CONQUAS assesses at the point of inspection, mostly on a sample; minor and aesthetic defects can still arise, and latent defects such as seepage or unexplained glass shattering may appear after the DLP.6
How to document defects
Good evidence turns a disagreement into a deduction. The standard is simple: a stranger reading your file a year later should be able to see what the defect was, where, when you reported it, and what the developer did.
Documenting defects from key collection onwards
- At handover, walk the unit with the developer’s representative using a room-by-room checklist; tap floor and wall tiles, run every tap and shower, fill basins and floor traps, open and lock every window and door, and test every switch and socket.
- Photograph and video everything with date stamps, including concealed areas (behind where cabinets will go, under sinks, inside DB boxes) before your renovation covers them.
- Keep a defects register: item number, location, description, photo reference, date notified, date acknowledged, developer’s proposed fix, date fixed, and your sign-off.
- Send notices in writing, keep the delivery record, and note the one-month and 14-day dates in a calendar.
- Re-inspect after rain for window and wall seepage, and after heavy shower use for wet-area leaks.
- Do not renovate over a defect that is still open. Under the SPA, you also need the developer’s consent for alterations before the CSC if they would depart from the approved plans (cl 10.2).1
- Diarise the Final Payment Date and the last day to serve a notice of deductions (7 working days earlier).
- Use an independent inspector if you are not confident about testing; keep the report with your register.
Specific defect types have their own tests and failure patterns. See popped and hollow tiles, tempered glass breakage and glass railings, cracks in walls and ceilings and façade and window leak diagnosis. If you plan to renovate in the first year, read condo renovation and MCST approvals first so that renovation work does not muddy the defects record.
How RRD approaches this
When a buyer exercises the SPA step-in right, the quotation served on the developer needs to be itemised by defect. RRD prepares itemised quotations from a site survey, and photographs the defects before, during and after rectification so the owner has the record needed for a notice of deductions. For common-property works, RRD works under the MCST’s appointed engineer where one is required.
Routes to resolve a dispute
1. Negotiation under the SPA
Most defect disputes are resolved by following clauses 17 and 5 properly. The written notices, quotations and deduction notice are themselves the escalation path.
2. Mediation
Clause 20 of Form 5 says the parties shall consider mediation at the Singapore Mediation Centre (SMC) before going to arbitration or court, but clause 20.2 makes clear this is not a legal obligation to mediate.1 Under SMC’s Mediation Procedure Rules fee schedule from 1 March 2026, disputes up to S$60,000 carry a non-refundable filing fee of S$27.25 and a mediation fee of up to S$400 per party per session; disputes above S$60,000 up to S$250,000 carry a filing fee of S$272.50 and a mediation fee of S$1,000 to S$1,350 per party per full day (all including GST).13 MND has also referred to the REDAS Conciliation Panel for disputes arising during the DLP; check the current scheme and eligibility with REDAS before relying on it.3
3. The Strata Titles Board
Under section 101 of the Building (Strata Management) Act, a Strata Titles Board may make an order to settle a dispute or rectify a complaint about any defect in a lot, a subdivided building, or its common property or limited common property. Applications may be made by the MCST, a subsidiary proprietor, a mortgagee in possession, a lessee or an occupier, and orders may be made on any of them or on the MCST’s chairperson, secretary, treasurer or council.2 Except for orders about the MCST’s exercise of its powers, an order may include damages up to the amount a District Court could award, currently S$250,000.214
That makes the Board well suited to disputes within the estate: a leak from the unit above, or an MCST’s refusal to repair common property. It is less suited to claims against a developer as seller under the SPA, which are contract claims.
4. Court or arbitration
Contract and negligence claims against a developer go to court, or to arbitration if the parties have agreed to arbitrate. In the State Courts, the Magistrate’s Court hears claims up to S$60,000 and the District Court up to S$250,000; larger claims go to the High Court.14 The Rules of Court 2021 require parties to consider amicable resolution, and to make an offer of amicable resolution before starting an action unless there are reasonable grounds not to (Order 5, rule 1).15 See the renovation and construction disputes guide for how the courts, tribunals and mediation compare.
| Situation | First step | Likely forum if unresolved |
|---|---|---|
| Unit defect within the DLP, developer responsive | Written notice under cl 17.2 | None needed |
| Unit defect within the DLP, developer unresponsive | Second notice with quotation; rectify; notice of deductions | Stakeholder retains disputed sum; mediation, then court |
| Defect found after the DLP | Written claim to developer with evidence | Mediation, then court; check limitation |
| Common-property defect | Owners’ SPA notices plus MCST register | MCST proceedings with ordinary resolution |
| Leak from the unit above or a dispute with the MCST | Written notice to owner or MCST | Strata Titles Board |
Summary
- The prescribed SPA gives a 12-month DLP from the earlier of actual vacant possession or 15 days after you receive the TOP/CSC papers, covering your unit, the development and the common property.1
- The developer must fix a notified defect within one month. If it does not, serve a second notice with a contractor’s quotation; after 14 days you may rectify and recover the cost.1
- 5% of the price stays with the Singapore Academy of Law until the Final Payment Date. Serve a notice of deductions at least 7 working days before that date.1
- Reported but unfixed defects remain the developer’s responsibility after the DLP, and later defects can found a claim within the limitation periods.810
- BCA cannot intervene in private contractual disputes, but CONQUAS, the Quality Mark and the May 2026 land-sales measures give developers strong reasons to fix defects promptly.37
- Common-property claims run through the MCST with an ordinary resolution; disputes within the estate can go to the Strata Titles Board.2
Questions people ask
How long is the defects liability period for a new condo in Singapore?
Twelve months under the prescribed Sale and Purchase Agreement for strata units (Form 5 of the Housing Developers Rules). It runs from the earlier of the date the developer actually delivers vacant possession, or the 15th day after you receive the TOP or CSC and the developer's completion notice. The DLP covers defects in your unit, the development, the common property and any limited common property that become apparent within that period.
How long does the developer have to fix defects?
Under clause 17.2 of the prescribed SPA, the developer must make good a defect within one month of receiving your notice requiring it to do so. If it does not, you can send a second written notice with a contractor's quotation and your intention to have the work done yourself if the developer fails to act within 14 days. After that, you may rectify and recover the cost from the developer.
Can I deduct rectification costs from the money held by the Singapore Academy of Law?
Yes, if you follow the SPA procedure. The Singapore Academy of Law holds 5% of the purchase price as stakeholder until the Final Payment Date. Clause 17.4 lets you deduct the cost of rectification works you were entitled to carry out from that sum. You must serve a notice of deductions on the stakeholder and the developer on the same day, at least 7 working days before the Final Payment Date. If the developer disputes it, the stakeholder holds the disputed amount.
What happens to defects I reported but the developer did not fix before the DLP ended?
They remain the developer's responsibility. BCA's guidance for condo owners says a defect reported during the DLP stays with the developer if it is still unresolved when the period ends. The prescribed SPA also says unfulfilled terms survive completion. Keep your notices and records, because you may need them to deduct from the stakeholding or to claim damages.
Who deals with defects in the common property of a new condo?
The developer's obligation under the SPA covers common property, and the Building (Strata Management) Act says appointing a managing agent does not relieve the developer of its duty to repair or make good common property defects. Individual buyers can notify them under the SPA. Once the management corporation (MCST) exists, it can take proceedings about common property on behalf of owners, but must first obtain an ordinary resolution of the general body.
Does BCA force developers to fix defects?
Not directly. The Ministry of National Development has said defect disputes are governed by the Sale and Purchase Agreement, and that BCA cannot intervene in private contractual disputes, although it may facilitate meetings. BCA's levers are indirect: CONQUAS assessments and banding, the Quality Mark, and since 22 May 2026, URA and BCA measures that can bar developers whose consecutive projects have major defects that were not promptly fixed from land sales.
Can the Strata Titles Board order the developer to fix defects?
The Board can make orders to settle disputes about defects in a lot or in common property, and can award damages up to the District Court limit. But it makes orders on management corporations, subsidiary proprietors, mortgagees, lessees, occupiers and MCST officers. It is therefore most useful for disputes within the estate, such as leaks from the unit above. Contract claims against the developer under the SPA normally go to mediation, then court or arbitration.
What is a good CONQUAS band or Quality Mark?
BCA rates developers and builders from Band 1, a very low incidence of major defects, to Band 6, a higher incidence, based on their six-year CONQUAS record. The bands are published on BCA's Quality Housing Portal. A Quality Mark certificate lists units that scored at least 85 out of 100 on internal finishes and were free of major defects and water seepage. Neither guarantees a defect-free home, and neither covers minor, aesthetic or design issues.
Sources
15 sources. Official sources are marked dark. Links were checked when this guide was last updated.
- mnd.gov.sgMinistry of National Development — “Written Answer by Ministry of National Development on disputes involving design and construction defects, and Temporary Occupation Permit” (17 August 2015). https://www.mnd.gov.sg/newsroom/parliament-matters/q-as/view/written-answer-by-ministry-of-national-development-on-disputes-involving-design-and-construction-defects-and-temporary-occupation-permit (accessed Nov 2026) ↩↩↩↩↩
- bca.gov.sgBuilding and Construction Authority — “Quality Mark”. https://www1.bca.gov.sg/buildsg/quality/quality-mark (accessed Nov 2026) ↩↩↩
- bca.gov.sgBuilding and Construction Authority — “CONQUAS®: Construction Quality Assessment System”. https://www1.bca.gov.sg/buildsg/quality/conquas (accessed Nov 2026) ↩↩
- isomer-user-content.by.gov.sgBuilding and Construction Authority — “Annex A: Fact sheet on Construction Quality Assessment System (CONQUAS) and CONQUAS banding” (May 2023). https://isomer-user-content.by.gov.sg/338/85c760f9-2fbd-4e19-8825-beb028059ee5/annex-a—fact-sheet—conquas-banding.pdf (accessed Nov 2026) ↩↩↩↩↩↩↩
- ura.gov.sgUrban Redevelopment Authority and Building and Construction Authority — Circular URA/COH/Circular-2026-01, “New measures to enhance protection of home buyers’ interests through strengthening deterrence of errant developer behaviour” (22 May 2026). https://www.ura.gov.sg/Corporate/Guidelines/Circulars/coh26-01 (accessed Nov 2026) ↩↩↩↩
- bca.gov.sgBuilding and Construction Authority — “What to know as a condo owner”. https://www1.bca.gov.sg/home-and-building-owners/condo-strata/condo-living-be-condo-savvy/what-to-know-as-a-condo-owner/ (accessed Nov 2026) ↩↩
- elitigation.sgThio Keng Thay v Sandy Island Pte Ltd [2019] SGHC 175 (High Court). https://www.elitigation.sg/gd/s/2019_SGHC_175 (accessed Nov 2026) ↩↩
- sso.agc.gov.sgLimitation Act 1959 (current version), ss 6, 24A and 24B. Singapore Statutes Online. https://sso.agc.gov.sg/Act/LA1959 (accessed Nov 2026) ↩↩
- elitigation.sgManagement Corporation Strata Title Plan No 4099 v KTP Consultants Pte Ltd [2024] SGHC(A) 32 (Appellate Division, 9 October 2024). https://www.elitigation.sg/gd/s/2024_SGHCA_32 (accessed Nov 2026) ↩↩
- singaporelawwatch.sgSingapore Law Watch / Singapore Academy of Law — “Singapore Law: Chapter 20, The Law of Negligence”, paras 20.2.9 and 20.3.12, discussing RSP Architects, Planners & Engineers v Ocean Front Pte Ltd [1995] 3 SLR(R) 653 and RSP Architects v MCST Plan No 1075 [1999] 2 SLR(R) 134. https://singaporelawwatch.sg/Results/ch-20-the-law-of-negligence (accessed Nov 2026) ↩
- mediation.com.sgSingapore Mediation Centre — “Mediation Procedure Rules: Fee Schedule” (Annex B, 1 March 2026). https://mediation.com.sg/wp-content/uploads/2026/02/Fee-Schedule-Annex-B-1-March-2026.pdf (accessed Nov 2026) ↩
- sso.agc.gov.sgState Courts Act 1970 (current version), s 2 (definitions of “District Court limit” and “Magistrate’s Court limit”). Singapore Statutes Online. https://sso.agc.gov.sg/Act/SCA1970 (accessed Nov 2026) ↩↩
- sso.agc.gov.sgRules of Court 2021, Order 5, rules 1–3 (amicable resolution). Singapore Statutes Online. https://sso.agc.gov.sg/SL/SCJA1969-S914-2021 (accessed Nov 2026) ↩
Use this guide in a report, a tender or a by-law briefing. Please link to the page so readers get the current version.