Condo Renovation in Singapore: MCST Approval, By-Laws, Deposits and Prohibited Works

Updated 9 November 202622 min read20 sources, 17 officialBy RRD Engr & Constr, editorial standards
The short answer

Condo renovations need MCST approval under the development's by-laws, and MCST authorisation under section 37 of the Building (Strata Management) Act for anything that affects the building's appearance or structure. Works adding floor area need a 90% resolution and URA permission. Structural works need a PE and BCA approval; household shelters, façades and balconies are tightly restricted.

Renovating a condominium unit in Singapore means working inside a building you only partly own. Your lot is yours to use, but the structure that holds it up, the external walls that define how the building looks, the pipes that serve your neighbours and even the waterproof membrane on the roof belong to everyone through the management corporation (MCST). The law that balances those interests is the Building (Strata Management) Act 2004, known until 30 September 2025 as the Building Maintenance and Strata Management Act (BMSMA), together with the by-laws made under it.

That is why a condo renovation has an extra approval that landed and commercial projects do not: the MCST’s. It sits alongside, not instead of, the statutory approvals from the Building and Construction Authority (BCA), the Urban Redevelopment Authority (URA) and the Singapore Civil Defence Force (SCDF). Most disputes come from treating one as a substitute for another, for example assuming that because a balcony enclosure is exempt from BCA plans, nobody else can object.

This guide explains what the Act and the prescribed by-laws actually say, what a typical MCST renovation application involves (with two real examples, clearly labelled as such), which works are prohibited or need more than MCST approval, the BCA and SCDF position inside a unit, waterproofing, common-property issues, and how disputes reach the Strata Titles Boards. It reflects the law as at 9 November 2026.

The law in one page

The Act was renamed in 2025

With effect from 1 October 2025, the BMSMA was renamed the Building (Strata Management) Act 2004, often abbreviated B(SM)A.1 The section numbers relevant to renovation did not change, so older MCST forms and articles citing “BMSMA section 37” still point to the right provision. The regulations are now the Building (Strata Management) Regulations 2005.4

What counts as common property

The Act’s definition of common property is wider than many owners assume. Besides the parts of the land and building not comprised in any lot and used by two or more lots, it includes, whether or not they sit inside a lot, shared pipes, wires, cables and ducts, any structural element of the building, and the waterproof membrane attached to an external wall or a roof.1 The Act’s examples include foundations, load-bearing walls, columns, beams and slabs, though for slabs it excludes any layer that is the underlayment or the flooring finishing; external walls, roofs and façades used by two or more lots; and central air-conditioning and sprinkler systems.1 So when you hack a beam or core through a slab inside your own unit, you are working on common property.

The prescribed by-laws: what the Second Schedule actually says

Every strata development is governed by by-laws. For developments whose MCST was constituted on or after 1 April 2005, the by-laws prescribed by regulations apply automatically, and any by-law the MCST makes must not be inconsistent with them.2 They are set out in the Second Schedule to the Building (Strata Management) Regulations 2005. There are 21, and none is headed “renovation”. The ones that bite on renovation are these:

Prescribed by-law Heading What it means for a renovation
1 Noise No noise likely to interfere with others’ peaceful enjoyment4
3 Obstruction of common property No obstruction except temporarily; if the MCST has resolved how furniture or large objects are moved through common property, you must follow it4
5 Alteration or damage to common property No marking, painting, nails or screws into, or damage to, any common-property structure without prior written approval; approval does not authorise additions to common property; locks, safety devices, insect screens, child-safety devices and fixings for decorations on internal walls are allowed if competently installed and in keeping with MCST guidelines4
9 Depositing rubbish on common property No rubbish, dirt, dust or discarded items on common property without approval4
12 Storage of flammable materials No flammable chemicals, liquids or gases (beyond domestic use) without prior written approval4
15 Duty to maintain lot Keep the lot, including sanitary fittings and water, gas, electrical and air-conditioning pipes and apparatus, in good condition so as not to annoy others4
17 Change in use of lot Notify the MCST without delay of any change in use4
18 Prevention of fire and other hazards Do nothing that affects fire safety devices or reduces fire safety; nothing placed on windows or balconies that could fall and cause damage or injury4
21 Fire sprinkler system on lot Installing or altering sprinklers in the lot needs MCST consent; repair any common-property damage; install competently and in keeping with the building (since 1 February 2019)4

Additional by-laws: where renovation rules live

Section 32 lets an MCST, by special resolution, make additional by-laws for controlling the use and enjoyment of the development, expressly including safety and security, floor coverings, behaviour, and “architectural and landscaping guidelines” to be observed by all owners.2 BCA’s strata management guide explains that MCSTs may use these to require approval before works, to require PE endorsement for structural works, and to require proof of approvals from URA, SCDF and the Commissioner of Building Control.5 A by-law, or any amendment to one, has no effect until it is lodged with the Commissioner of Buildings, which the MCST must do within 45 days of the resolution.2 The MCST must display its by-laws on a notice board and make them available.2 Before you sign with a contractor, ask the managing agent for the current lodged by-laws and the renovation rules, and check which is which: a “house rule” that was never passed and lodged as a by-law is weaker than one that was.

Section 37: appearance, structure and floor area

Section 37 is the core statutory control on renovation.

  • Floor area. An owner must not make an improvement that increases, or is likely to increase, the floor area of the land and building in the strata title plan, unless the MCST authorises it by 90% resolution. Planning Act requirements still apply on top.2 URA’s guidance for strata homes asks for a letter from the MCST secretary or council chairperson confirming the 90% resolution with the planning application.7
  • Appearance and structure. An owner must not make any other improvement that affects the appearance of any building in the development without MCST authorisation (or unless section 37A permits it). The MCST may authorise it only if satisfied that the improvement will not detract from the appearance of the buildings, or will be in keeping with them, and will not affect the structural integrity of any building.2
  • Remedy. Where the MCST is satisfied that an improvement contravenes these rules, it may by written notice require the owner, whether or not the owner did the work, to carry out remedial works at the owner’s own cost within a reasonable time.2 That last point matters to buyers: an unauthorised enclosure built by a previous owner becomes the current owner’s problem.

Building (Strata Management) Act 2004, section 37(4)

The MCST may authorise an improvement affecting the building’s appearance only if satisfied it “will not affect the structural integrity” of any building in the plan, and that it will not detract from, or will be in keeping with, the appearance of the buildings.2 Both conditions must be met. BCA’s guide adds that the MCST may set design guidelines through by-laws so that such works stay uniform.5

Section 37A: safety equipment you are entitled to install

Section 37A allows an owner to install safety equipment despite any by-law to the contrary: window grilles or screens, balustrades, railings and fences to prevent falls from outdoor-facing balconies, terraces, windows, doors and openings; devices restricting how far windows or doors open; insect and animal screens; intruder alarms; and locks.2 The owner must repair any damage to common property and ensure the equipment is installed competently and looks in keeping with the building.2 BCA’s guide puts the balance plainly: the MCST cannot prevent the installation but can introduce design guidelines for uniform appearance.5

What a typical MCST renovation application looks like

Each MCST sets its own process, deposit and hours, so the only reliable source is your own development’s by-laws and forms. To show what these look like in practice, the table below summarises two publicly available renovation forms from real Singapore developments. They are examples, not norms; other MCSTs set different figures.

Item Example A: Casuarina Cove, MCST Plan 2205 (by-law edition 2018)12 Example B: Evergreen Park, MCST Plan 2521 (form V5; by-law extracts as at May 2014)13
Renovation deposit S$1,000 minimum, refunded without interest subject to compliance and any claims S$500 (minor works) or S$2,000 (major works), refundable 30 days after completion if debris removed and no damage
Other charges S$25 a day if common water or power is used with consent S$53.50 administrative fee including lift padding; S$107 a day penalty for uncleared debris
Maximum duration One month Four weeks; extensions case by case
Permitted hours Monday to Friday 9 am to 5 pm; Saturday, Sunday and public holidays no work Monday to Friday 9 am to 5 pm; Saturday and eve of holidays 9 am to 1 pm; Sunday and public holidays no work
Structural works Not addressed on the form Hacking of structural slabs, columns and beams strictly prohibited; wall demolition needs plans with PE endorsement and authority approval
Façade and windows No alteration to windows in external walls, and no balcony alterations, without written approval No works affecting the external façade, including windows, without written approval
Other conditions Lift protection and a 5-minute limit on holding lifts; materials kept inside the unit; public liability and work injury insurance; grilles in a set pattern and colour Main entrance door replacement to be a half-hour fire-rated door; electrical and fire system changes cleared by the MCST’s engineer; unit entrance boxed up; renovation permit displayed

Both forms reflect the prescribed by-laws (noise, obstruction, damage to common property) and add development-specific rules. Note how Example B builds in statutory requirements: PE endorsement for wall demolition, a fire-rated entrance door, and authority approvals before work starts.13

Documents an MCST typically asks for

Drawing on BCA’s guidance and the examples above, a complete renovation application usually includes:51213

  • the application form signed by the owner (and by the owner as well as the tenant, if a tenant applies);
  • a description and schedule of works, with layout drawings showing walls removed or added;
  • the contractor’s company details, the list of workers, and insurance (public liability and work injury compensation);
  • PE-endorsed drawings and BCA approval for any structural works, and other authority approvals where needed;
  • for electrical, sprinkler or alarm changes, clearance by the MCST’s engineer or the relevant licensed professional;
  • the deposit and any administrative fee, and a signed undertaking or indemnity.

Before you submit to the MCST

  • Obtain the lodged by-laws, the renovation rules, the design guidelines (grilles, screens, blinds, awnings) and the application form.
  • Mark on your layout every wall to be removed, and have a PE confirm whether each is load-bearing and whether any is part of the household shelter.
  • List any work on windows, the main door, the balcony, the AC ledge, the façade or the roof terrace; each needs specific MCST authorisation.
  • Identify any change to sprinklers, detectors or the unit’s entrance door, and ask a Qualified Person about SCDF.
  • Specify waterproofing and a water-ponding test for wet areas in the contract.
  • Plan deliveries and debris removal to the MCST’s hours and lift rules, and price the deposit risk into the contract.

Works that are prohibited or need more than MCST approval

Structural walls, columns, beams and slabs

Load-bearing elements are common property and their alteration affects structural integrity, so section 37(4) applies, alongside prescribed by-law 5.124 Statutorily, structural works need a PE (civil or structural) to submit structural plans to BCA and a permit before works start; complete plans without an Accredited Checker are processed in 7 working days.19 Doing structural work without approved plans or a permit is an offence carrying a fine of up to S$200,000, two years’ imprisonment, or both, and it applies to anyone who “permits or authorises” the works.17 Many MCSTs go further and prohibit hacking structural elements outright, as Example B does.13 Non-load-bearing walls are different: creating openings in them or demolishing them is an insignificant building work under the First Schedule, items 1(o) and 1(p), though the MCST still needs to approve.8 How to tell the difference, and how post-tensioned slabs change the picture, is covered in our guide to hacking walls, slabs and household shelters.

The household shelter

The household shelter (HS) has strengthened walls, floor, ceiling and door designed for civil defence. SCDF’s rules list what owners may and may not do.9

Permitted (summary) Not permitted (summary)
Floor tiles on wet cement mortar, total finish and screed thickness up to 50 mm Wall tiles, rock-tone, cement-sand or gypsum plaster on internal faces
Skirting up to 100 mm high Floor tiles laid with adhesive; a second layer of tiles
Vinyl or linoleum flooring; painting walls, ceiling and door (not over the door notice, bolts or seal) Cornices inside the HS
Drilling the internal face up to 50 mm deep for inserts and removable screws; fixtures to be removed within 48 hours on notification Power-driven nails into internal walls; hacking or drilling beyond the permitted limits
Power-driven nails up to 75 mm on the external face only Hacking either face to form a key for tiles or panels
Covering ventilation openings with removable finishes, leaving at least 25% of the area open Modifying, removing or tampering with the HS door, frame, door notice or ventilation sleeves

Source: SCDF, “Permitted and not permitted works for household shelters”.9 Hacking a shelter wall to enlarge a room is not a matter the MCST can approve.

Façade, windows and the building’s appearance

Anything visible from outside, such as window frames, glass colour, external grilles, awnings, balcony fittings and AC condenser positions, affects appearance and needs MCST authorisation under section 37(3).2 Replacing windows and doors is an insignificant work for BCA purposes,8 but the MCST can and usually does prescribe the design. Safety grilles are the one category the MCST cannot refuse outright, under section 37A, though they must follow its design guidelines.2

Enclosing balconies: three regimes, one answer

This is the most misunderstood rule in condo renovation.

  • BCA: The First Schedule lists “the enclosing of any sides of a balcony, yard or terrace with windows and glass panels in residential buildings” as an insignificant building work, so no BCA plan is needed (item 1(n)).8
  • URA: URA’s guidelines state that balconies shall not be enclosed with walls or glass panels. Screens such as vertical fins or louvres are allowed only if they can be fully drawn open or retracted and allow natural ventilation even when fully closed; owners of existing developments must follow their MCST’s design guidelines. Blinds are treated as furnishing, and safety grilles are not balcony screens.6
  • MCST: Enclosure changes the building’s appearance, so it needs MCST authorisation under section 37(3) and (4) and must follow any design guidelines the MCST has made.25

The BCA exemption does not override the other two. A contractor who says “no approval needed” is describing only one of the three.

The glass balcony that had to come out (composite scenario)

Composite scenario, not a specific case. A buyer of a resale unit wants the balcony glazed in to enlarge the living room. The contractor points out that glass enclosures are BCA-exempt and installs frameless sliding glass panels over a weekend, without an MCST application. The MCST, citing section 37 and its façade guidelines, issues a written notice under section 37(4A) requiring removal at the owner’s cost. The cost chain: the glazing, the removal, making good the balcony edge and soffit, forfeiture of part of the renovation deposit, and months of correspondence. Had the owner checked URA’s balcony rule, the MCST’s approved screen design would have been the only lawful option from the start.

Air-conditioning ledges

Air-conditioning works themselves are BCA-insignificant (item 12).8 Enclosing or roofing an AC ledge is a different matter: it changes the façade and needs MCST authorisation under section 37(3).2 Ledges also matter for fire safety in taller blocks: the Fire Code lets balconies and AC ledges count as part of the horizontal projection used for façade fire separation in residential buildings over 24 m in habitable height, where they protrude at least 600 mm and have at least 1-hour fire-rated construction.11 Check your MCST’s design guidelines for condenser positions and screens before the air-conditioning contractor fixes anything to the ledge.

Covers over private enclosed spaces and roof terraces

Open-sided covers over private enclosed spaces (PES), private roof terraces and balconies do not need URA planning permission, but they need MCST consent and must meet BCA and SCDF requirements where applicable.7 For PES in newer developments, URA expects developers to install part of the cover and homeowners to choose the rest from approved designs, with MCST clearance; PES fencing must not exceed 1.3 m.6 BCA’s strata guide recommends that an awning over a PES be certified by a QP or PE for structural adequacy and checked for any increase in gross floor area.5

BCA and SCDF inside a unit

BCA: what needs no plans

For a condo interior, the First Schedule items that matter most are: openings in or demolition of non-load-bearing walls (1(o), 1(p)); replacing windows and doors (2); replacing a window-integrated safety barrier in a residential building to the standardised design (2A); replacing floor and wall finishes (3); lightweight false ceilings (4); partitions of lightweight material (6, outside landed houses); raised floors and topping up balconies with lightweight materials (7); air-conditioning works (12); and small service openings in slabs, excluding flat slabs, cantilevers and prestressed elements, no more than 150 mm and at least 450 mm from other openings (15).8 BCA reminds owners that insignificant works still need any other approvals and must comply with MCST by-laws.20

SCDF: the residential exemption and its edges

The Fire Safety (Exemption) Order exempts alterations or additions in existing residential flats, maisonettes and townhouses from SCDF plan approval, provided they do not increase floor area and do not affect the common areas, the doors that give entry to or exit from the unit, the walls separating the unit from the common areas, or the roofing.10 Those four exclusions were refined with effect from 24 November 2023.10

Two items in particular take a job outside the exemption:

  • The main entrance door and corridor wall. The Fire Code requires each residential unit to be compartmented from adjoining units and other parts of the building by construction of at least 1-hour fire resistance, with the unit’s exit access door rated at least ½ hour (unless an exception in the Code applies).11 Replacing the entrance door with a non-rated design, or cutting into the corridor wall, affects that compartment.
  • Sprinklers and detectors. Where a unit has sprinklers, altering them needs MCST consent under prescribed by-law 21, and prescribed by-law 18 forbids doing anything that affects fire safety devices.4 The MCST will usually require its own engineer’s clearance, as Example B does.13

For those items, ask a Qualified Person whether SCDF plan approval or a minor A&A lodgement applies; our guide to SCDF fire safety approvals explains both routes.

Waterproofing in wet areas

Wet-area failures are the most common cause of disputes between neighbours in strata buildings, and they usually trace back to renovation.

Who owns what. The Act lists the waterproof membrane attached to an external wall or roof as common property, and treats slabs as structural common property but excludes the underlayment and flooring finishes.1 A bathroom’s screed, membrane and tiles inside a unit are generally treated as part of the owner’s finishes; confirm with your MCST or lawyer if your development’s strata plan or by-laws say otherwise. Prescribed by-law 15 requires owners to maintain their lot, including sanitary fittings and water pipes, so as not to annoy other owners.4

Who bears the burden of proof. In Strata Titles Board proceedings about a defect in a lot that sits above another lot, the Act presumes, unless proven otherwise, that the defect lies in the lot above if there is evidence of dampness, moisture or water penetration on the ceiling below or on finishes attached to it.3 Hacking a bathroom floor and re-tiling it without a properly detailed membrane exposes the owner to that presumption for years afterwards. The guide on water seepage between condo floors covers testing and claims.

Doing it properly. BCA publishes a good-practice guide, “Good Industry Practices: Waterproofing for Internal Wet Areas”, covering design, materials, preparation, installation, protection and defect rectification.16 Contractually, specify the membrane system, its upturns at walls and around floor traps and pipe penetrations, protection before screeding, and a water-ponding test before tiling, with the duration and acceptance criteria written into the contract. A 24-hour ponding test is a common contract specification (illustrative; the duration is a matter for your specification, not a statutory figure).

Common-property issues during works

Most friction between renovating owners and MCSTs is about common property rather than the unit itself.

  • Corridors and lifts. Materials must be kept inside the unit; obstruction of common property is allowed only temporarily (prescribed by-law 3).4 MCSTs commonly require lift padding and limit how long a lift can be held.1213
  • Drilling into common property. Fixing anything to an external wall, corridor wall or ceiling that forms part of the common property needs prior written approval (by-law 5), and that approval does not authorise additions to common property.4 Where the works permanently use common property, such as anchor points for a covering on an external wall, BCA’s guide says MCST approval is needed and the MCST can grant rights through an exclusive use by-law.5 Under section 33, such by-laws need an ordinary resolution for up to one year, a special resolution for over one and up to three years, and a 90% resolution beyond three years.2
  • Debris and utilities. Debris cannot be left on common property (by-law 9), and tapping common water or power without consent is commonly prohibited or charged for.412
  • Noise. By-law 1 is the statutory baseline; the MCST’s renovation hours are the practical limit. For the separate NEA construction-noise rules, see construction noise and working hours.

Disputes: the MCST, the Strata Titles Boards and the courts

Talk first, then the STB

The Strata Titles Boards (STB) hear most strata disputes. Section 101 of the Act lets a Board make orders to settle disputes about defects in a lot or common property, an owner’s liability for the cost of works done by the MCST, and the MCST’s exercise of, or failure to exercise, its powers and duties.3 Two rules matter for renovation:

  • Deemed refusal. Where an owner asks the MCST to exercise a discretion and it neither acts nor replies within 2 months, it is deemed to have decided not to act, which opens the way to an application.3
  • Unreasonable refusal. Section 111 allows a Board to order the MCST to consent where it has unreasonably refused consent to alterations to common property, or unreasonably refused to authorise an improvement affecting appearance under section 37(4).3

There are limits: the Board cannot override the MCST on matters that the Act or by-laws reserve for a special, 90%, unanimous or comprehensive resolution.3 So a refused GFA-increasing enclosure, which needs a 90% resolution, is not something the Board can simply order.

Process and fees

STB proceedings run through application, mandatory mediation, a hearing if mediation fails, and post-hearing orders that bind the parties and can be enforced through the State Courts.15 The application fee is S$500; the first two mediation attendances are free and later ones cost S$150 a day; hearings cost S$300 a day; and the Boards cannot refund fees.14 The STB suggests approaching the other party first and offers a pre-filing check of applications.15 Separately, any owner or the MCST can apply to court to enforce by-laws or recover damages for loss caused by a breach.2 For a comparison of the routes, see resolving renovation disputes.

BCA consulted from 9 March to 8 April 2026 on proposed amendments to the Act, including a possible mechanism to refer prolonged disputes to the STB; these were proposals at the time of the consultation and should be checked for status before you rely on them.18

A realistic sequence for a condo renovation

From idea to handover

  1. Collect the rules. Get the lodged by-laws, renovation rules, design guidelines and application form from the managing agent, plus the unit’s approved floor plan.
  2. Survey and classify. Have the contractor and, where any wall or slab is involved, a PE survey the unit. Classify each item: MCST only; MCST and BCA structural approval; MCST with section 37 authorisation; MCST and URA (any floor area increase); SCDF check (entrance door, corridor wall, sprinklers).
  3. Statutory approvals. The PE obtains BCA structural plan approval and the permit for structural works; URA permission with the 90% resolution letter if floor area increases.
  4. MCST application. Submit the form, drawings, approvals, insurance, worker list and deposit. Allow for the MCST’s review and any council or general meeting decision.
  5. Mobilise. Protect lifts and corridors, box up the entrance, display the permit, and brief workers on the hours and by-laws.
  6. Build. Follow the approved drawings; ponding-test wet areas before tiling; keep debris off common property daily.
  7. Complete. Joint inspection of common property with the managing agent; claim the deposit back within the MCST’s refund timeline; keep the approvals, PE certificates and waterproofing records with the unit’s documents.

Independent engineer's note

In a condo, the PE’s role is narrower than on a landed job but higher-stakes: confirming whether a wall is load-bearing, whether a slab is post-tensioned before any coring, and whether the household shelter is affected. Those answers decide whether the MCST can approve at all. When the PE is appointed and paid by the owner rather than the contractor, the finding goes straight to the person who must apply to the MCST and BCA. RRD’s usual independent engineering partner is CVC Engineers, a Singapore PE consultancy providing PE endorsement and submissions; owners are free to appoint any PE. See PE endorsement and independence.

How RRD approaches this

RRD has carried out works in an Orchard condominium among other occupied buildings. On condo jobs RRD reads the development’s by-laws and renovation rules before quoting, lists MCST-, BCA- and SCDF-dependent items separately in the itemised quotation, and plans deliveries and noisy works to the MCST’s hours. Where a PE is needed, RRD recommends the owner appoint the engineer directly, with no mark-up on engineering fees.

For a first pass at which approvals your works need, use the Approval Navigator; for wider context on approvals in non-residential buildings, see the master A&A approvals guide; and for terms, see the glossary.

Questions people ask

Is there a prescribed by-law on renovation in Singapore condos?

No. The 21 prescribed by-laws in the Second Schedule to the Building (Strata Management) Regulations 2005 cover matters such as noise, alteration or damage to common property, fire hazards and the duty to maintain the lot, but none is headed renovation. Renovation rules, deposits and working hours come from additional by-laws or house rules that each MCST makes under section 32 of the Act, which must be passed by special resolution and lodged with the Commissioner of Buildings to take effect.

Can my MCST stop me from installing window grilles?

No. Section 37A of the Building (Strata Management) Act allows a subsidiary proprietor to install safety equipment, including window grilles or screens, balustrades and railings, devices restricting how far a window opens, insect screens, intruder alarms and locks, despite any by-law that prohibits it. You must install it competently, repair any damage to common property, and give it an appearance in keeping with the building, which in practice means following the MCST's design guidelines.

Can I enclose my condo balcony with glass?

Generally not. URA's guidelines say balconies shall not be enclosed with walls or glass panels. Screens are allowed only if they can be fully opened or retracted and still allow natural ventilation when closed, and owners must follow the MCST's design guidelines. Although glass enclosure of a residential balcony is listed as an insignificant work for BCA purposes, that exemption does not override URA's rule or the MCST's authority over the building's appearance.

Can I hack a wall in my condo unit?

Only if it is non-load-bearing and outside the household shelter, and the MCST approves. Load-bearing walls, columns, beams and slabs are structural elements and form part of the common property under the Act. Altering them needs a Professional Engineer, BCA structural plan approval and a permit, and MCST authorisation because the works affect structural integrity. Many MCSTs prohibit hacking structural elements outright in their by-laws.

How much is a typical condo renovation deposit?

It varies by development and is set by each MCST, so check your own by-laws and forms. As real examples: Casuarina Cove (MCST Plan 2205) asks for a minimum deposit of S$1,000 with work limited to one month, and Evergreen Park (MCST Plan 2521) asks for S$500 for minor works or S$2,000 for major works, refundable 30 days after completion if debris is cleared and there is no damage, plus a S$53.50 administrative fee.

Who is responsible for waterproofing in my condo bathroom?

The Act lists the waterproof membrane attached to an external wall or roof as common property, and treats structural slabs as common property but not the underlayment or flooring finishes. Wet-area finishes inside a unit are therefore usually the owner's to maintain, and prescribed by-law 15 requires owners to keep sanitary fittings and pipes in good condition. If water damages the unit below, the Strata Titles Board presumes the defect lies in the unit above unless proven otherwise.

What can I do if the MCST unreasonably rejects my renovation?

Section 111 of the Building (Strata Management) Act allows a Strata Titles Board to order the MCST to consent if it has unreasonably refused consent to alterations to common property, or unreasonably refused to authorise an improvement affecting the building's appearance. If the MCST simply does not reply within 2 months, it is deemed to have decided not to act. Applications cost S$500, and the parties must attend mediation before any hearing.

Does a condo renovation need SCDF approval?

Usually not for ordinary internal works. The Fire Safety (Exemption) Order exempts alterations in existing residential flats that do not increase floor area and do not affect common areas, the unit's entrance or exit doors, the walls separating the unit from common areas, or the roofing. Works touching any of those, or the building's sprinkler or alarm systems, fall outside the exemption, so a Qualified Person should advise before they start.

Sources

20 sources. Official sources are marked dark. Links were checked when this guide was last updated.

  1. sso.agc.gov.sgBuilding (Strata Management) Act 2004 (formerly the Building Maintenance and Strata Management Act), short title and section 2 (definition of “common property”), current version as at 9 November 2026; renamed by Act 12 of 2020 with effect from 1 October 2025. Singapore Statutes Online. https://sso.agc.gov.sg/Act/BSMA2004 (accessed Nov 2026) ↩↩↩↩↩
  2. sso.agc.gov.sgBuilding (Strata Management) Act 2004, sections 32, 33, 37 and 37A, current version as at 9 November 2026. Singapore Statutes Online. https://sso.agc.gov.sg/Act/BSMA2004?ProvIds=pr32-,pr33-,pr37-,pr37A- (accessed Nov 2026) ↩↩↩↩↩↩↩↩↩↩↩↩↩↩↩↩↩
  3. sso.agc.gov.sgBuilding (Strata Management) Act 2004, sections 101 and 111, current version as at 9 November 2026. Singapore Statutes Online. https://sso.agc.gov.sg/Act/BSMA2004?ProvIds=pr101-,pr111- (accessed Nov 2026) ↩↩↩↩↩
  4. sso.agc.gov.sgBuilding (Strata Management) Regulations 2005, Second Schedule (“Prescribed by-laws”), current version as at 9 November 2026. Singapore Statutes Online. https://sso.agc.gov.sg/SL/BSMA2004-S192-2005?ProvIds=Sc2- (accessed Nov 2026) ↩↩↩↩↩↩↩↩↩↩↩↩↩↩↩↩
  5. isomer-user-content.by.gov.sgBuilding and Construction Authority — Strata Management Guide 14, “Carrying Out Works in Lots – What You Should Know” (November 2023). https://isomer-user-content.by.gov.sg/338/6ab15b7b-0fbc-49fe-b2d0-c937e709dcf1/bca_guide-14_carrying_out_works_in_lots.pdf (accessed Nov 2026) ↩↩↩↩↩↩↩
  6. ura.gov.sgUrban Redevelopment Authority — “Balconies, Private Enclosed Spaces, Private Roof Terraces and Indoor Recreation Spaces” (Development Control Handbook, Flats and Condominiums). https://www.ura.gov.sg/Corporate/Guidelines/Development-Control/Residential/Flats-Condominiums/Balconies-PES-PRT (accessed Nov 2026) ↩↩
  7. ura.gov.sgUrban Redevelopment Authority — “Strata-titled Residential” (renovating private residential property). https://www.ura.gov.sg/guidelines/property-and-business-owners/property/renovating-private-residential-property/strata-titled-residential/ (accessed Nov 2026) ↩↩
  8. sso.agc.gov.sgBuilding Control Regulations 2003, First Schedule (“Insignificant building works”), current version as at 9 November 2026. Singapore Statutes Online. https://sso.agc.gov.sg/SL/BCA1989-S666-2003?ProvIds=Sc1- (accessed Nov 2026) ↩↩↩↩↩
  9. scdf.gov.sgSingapore Civil Defence Force — “Permitted and Not Permitted Works for Household Shelters (HS)”. https://scdf.gov.sg/docs/default-source/cd-shelter-(docs)/permitted_and_not_permitted_works_for_hs31fc3b53-7baf-4b88-9546-2f8072adf802.pdf (accessed Nov 2026) ↩↩
  10. sso.agc.gov.sgFire Safety (Exemption) Order, paragraph 2 and First Schedule, item 2 (as amended by S 757/2023 with effect from 24 November 2023), current version as at 9 November 2026. Singapore Statutes Online. https://sso.agc.gov.sg/SL/FSA1993-OR1?ProvIds=Sc1- (accessed Nov 2026) ↩↩
  11. scdf.gov.sgSingapore Civil Defence Force — Fire Code 2023, Clause 9.2 “Purpose Group II Occupancy” (cl. 9.2.1b). https://www.scdf.gov.sg/fire-safety-services-listing/fire-code-2023/table-of-content/chapter-9-additional-requirements-for-each-purpose-group/clause-9.2-purpose-group-ii-occupancy (accessed Nov 2026) ↩↩
  12. cascove.sgThe Management Corporation Strata Title Plan No. 2205 (Casuarina Cove) — “Application Form for Addition/Alteration/Repairs/Renovation Work” and Notice to All Contractors (by-law edition 2018). https://cascove.sg/cms/form?f=Renovation_Form.pdf (accessed Nov 2026) ↩↩↩↩
  13. evergreenparkcondo.comThe Management Corporation Strata Title Plan No. 2521 (Evergreen Park) — “Application for Renovation / Moval” (form V5), including extracts from by-laws as at May 2014. https://evergreenparkcondo.com/cms/form?f=Application_for_Renovation_-_Moval_Form.pdf (accessed Nov 2026) ↩↩↩↩↩↩
  14. stratatb.gov.sgStrata Titles Boards — “Fees: BSMA” (last updated 8 June 2026). https://www.stratatb.gov.sg/resources/fees/bsma/ (accessed Nov 2026) ↩
  15. stratatb.gov.sgStrata Titles Boards — “General Proceedings”. https://www.stratatb.gov.sg/general-proceedings/ (accessed Nov 2026) ↩↩
  16. bca.gov.sgBuilding and Construction Authority — “Good Industry Practices: Waterproofing for Internal Wet Areas” (2nd edition), CONQUAS 21 Enhancement Series. https://www.bca.gov.sg/Publications/EnhancementSeries/water.html (accessed Nov 2026) ↩
  17. sso.agc.gov.sgBuilding Control Act 1989, section 20 (building offences), current version as at 9 November 2026. Singapore Statutes Online. https://sso.agc.gov.sg/Act/BCA1989?ProvIds=pr20- (accessed Nov 2026) ↩
  18. allenandgledhill.comAllen & Gledhill — “BCA consults on review of strata management regime to enable MCSTs to maintain and run estates better”, 19 March 2026. https://www.allenandgledhill.com/sg/perspectives/articles/32566/sgkh-bca-consults-on-review-of-strata-management-regime-to-enable-mcsts-to-maintain-and-run-estates-better (accessed Nov 2026) ↩
  19. bca.gov.sgBuilding and Construction Authority — “Structural plan submission”. https://www1.bca.gov.sg/safety-and-standards/applications-and-licenses/structural-plan-submission/ (accessed Nov 2026) ↩
  20. bca.gov.sgBuilding and Construction Authority — “Building works not requiring approval”. https://www1.bca.gov.sg/guidelines-and-requirements/building-works-not-requiring-approval/ (accessed Nov 2026) ↩
Cite or link to this guide

Use this guide in a report, a tender or a by-law briefing. Please link to the page so readers get the current version.

RRD Engr & Constr. (2026). Condo Renovation in Singapore: MCST Approval, By-Laws, Deposits and Prohibited Works. RRD Field Guide. Updated 9 November 2026. https://rrd.sg/guides/condo-renovation-mcst-approval/