Resolving Renovation and Construction Disputes in Singapore: CASE, Mediation, Small Claims, SOPA Adjudication, Courts and Arbitration

Updated 9 November 202621 min read16 sources, 11 officialBy RRD Engr & Constr, editorial standards
The short answer

Choose the route by who you are, the dispute type and the amount. Consumers usually start with CASE. Claims up to S$20,000 (S$30,000 by consent) filed within 2 years can go to the Small Claims Tribunals, without lawyers. Contractors owed progress payments under written contracts can use SOPA adjudication. Larger claims go to mediation, the Magistrate's Court (to S$60,000), District Court (to S$250,000) or arbitration.

Most renovation and construction disputes in Singapore are not about law. They are about a missing line in a quotation, a variation agreed on WhatsApp and priced later, a defect the contractor says was caused by someone else, or a final payment withheld for reasons nobody wrote down. The law matters only once talking has failed, and then the most important decision is the forum: where the dispute will be decided, at what cost, and how fast.

This guide compares the main routes: CASE negotiation and mediation, the Small Claims Tribunals (SCT), the Community Disputes Resolution Tribunals (CDRT) for neighbour disputes, mediation at the Singapore Mediation Centre (SMC) and in the courts, adjudication under the Security of Payment Act (SOPA), the State Courts, and arbitration. It finishes with the evidence to keep and a decision table by claim size and type. Every limit and fee below was checked against the judiciary, CASE, SMC or the statute itself in November 2026.

It is written for homeowners, tenants, MCSTs and managing agents, fit-out managers and contractors. A homeowner chasing a S$4,000 defect and a main contractor owed S$400,000 on a fit-out need very different routes.

Step one: identify what kind of dispute you have

Dispute type Typical examples Usual first route
Consumer vs renovation firm Defective tiling, delay, lost deposit, abandoned job Written complaint, then CASE; SCT if within limits
Business vs business on a written construction contract Unpaid progress claim on a fit-out, disputed variations SOPA payment claim and adjudication; then mediation, court or arbitration
Contractor vs homeowner for unpaid balance Final payment withheld for alleged defects Letter of demand; SCT if within limits; court above that
Neighbour vs neighbour Renovation noise, vibration, obstruction MCST or town council, then CDRT
Owner vs developer over new-home defects Defects in the first year after vacant possession SPA defects procedure; see new-property defects
Large or complex claim Delay and LD disputes, design liability Mediation, then court or arbitration as the contract requires

Before any forum: the steps that decide most disputes

Whatever route you take, the same early steps improve your position:

  1. Re-read the contract. Look for a dispute clause: some renovation contracts require mediation or arbitration before litigation.
  2. Put the complaint in writing, item by item, with photographs and the remedy you want.
  3. Give the other side a fair chance to fix or pay. For defects, follow any defects-liability notice procedure in the contract; see defects liability and retention.
  4. Make a written offer to settle. If the dispute reaches the courts, the Rules of Court 2021 require parties to consider amicable resolution before and during proceedings, and to make an offer of amicable resolution before starting an action unless they have reasonable grounds not to. The offer must be in writing and open for at least 14 days unless otherwise agreed, and a refusal may be considered on costs (Order 5).12
  5. Watch the clock. The SCT and CDRT have 2-year filing limits;14 SOPA steps run in days;10 the general limitation period for contract and tort claims is 6 years.15

CASE: negotiation and mediation for consumers

The Consumers Association of Singapore (CASE) handles consumer-to-business disputes. CASE officers can take up a consumer’s complaint with the business and propose mediation when negotiation reaches a deadlock.5

Renovation is a large part of that work. CASE’s 2025/2026 annual report records renovation-related complaints falling from 962 in 2024 to 787 in 2025, and prepayment losses in the sector falling from S$728,813.76 to S$190,667.7

How CASE mediation works

  • It is voluntary and by invitation: CASE invites both parties when a case reaches deadlock or both agree.5
  • Each session runs about two hours; if the parties settle, they sign a settlement agreement.5
  • Both parties pay an administrative fee, which depends on the claim size and the consumer’s membership status. Fees include 9% GST, effective 1 January 2024.5
Claim amount (all industries except real estate) Consumer, CASE member Consumer, non-member CaseTrust business Non-CaseTrust business
Below S$5,000 S$16.35 S$38.15 S$32.70 S$38.15
S$5,001 – S$10,000 S$16.35 S$54.50 S$49.05 S$54.50
S$10,001 – S$20,000 S$27.25 S$109.00 S$98.10 S$109.00
S$20,001 – S$30,000 S$136.25 S$218.00 S$196.20 S$218.00
S$30,001 – S$40,000 S$245.25 S$327.00 S$272.50 S$327.00
Above S$40,000 S$354.25 S$436.00 S$381.50 S$436.00

Source: CASE mediation fee schedule.5

CaseTrust-accredited renovation firms

If the firm is CaseTrust-accredited, the consumer’s position is stronger:

  • An accredited business must attend a CASE mediation the consumer requests, and the mediation charges are borne by CaseTrust.56
  • Accredited renovation businesses must buy a deposit performance bond to protect deposits against non-performance, closure or liquidation, and must use the CaseTrust Standard Renovation Contract.6
  • As at 15 March 2026, 278 renovation businesses were CaseTrust-accredited. CASE launched a higher CaseTrust Renovation Gold tier on 15 March 2026, which adds stronger financial safeguards, including a banker’s guarantee arrangement for prepayments.7

CASE is a mediator, not a tribunal. It cannot compel a non-accredited business to attend or to pay. If mediation fails, the consumer’s next step is usually the SCT.

The Small Claims Tribunals

The Small Claims Tribunals are part of the State Courts and are designed for parties without lawyers.

Singapore Courts, Small Claims Tribunals

The judiciary lists contracts for the provision of services, with a renovation contract as an example, among the claims the SCT can hear. Claims must be filed “within 2 years of the event which creates your cause of action”.1

Limits and eligibility

Rule Detail Source
Claim limit S$20,000; you may abandon the excess to come within it 1
Higher limit by consent Up to S$30,000 if both parties sign a Memorandum of Consent, uploaded when filing 12
Time limit Within 2 years of the event that creates the cause of action 1
Eligible claims Sale of goods; provision of services (e.g. renovation); damage to property; residential tenancies up to 2 years; certain unfair-practice and statutory claims 1
Excluded Property damage involving motor vehicles or caused by a neighbour; employment; industrial and commercial leases; licences of premises; respondents outside Singapore 1
No splitting A claim cannot be divided into several claims to fit under the limit 1
Who may file An individual or a corporate entity with an eligible claim 2
Representation Lawyers are not allowed 23

Two consequences for construction disputes:

  • The 2-year SCT window is shorter than the 6-year limitation period for contract claims in court.115 A defect discovered in year three may be outside the SCT but still within time for a court claim.
  • Commercial fit-outs often fall outside. A tenant’s dispute about its lease is excluded, though a services contract with a fit-out contractor may qualify if within the limit.1

Filing fees

Claim amount Individual Other entity (sole proprietorships, partnerships, companies and others)
Up to S$5,000 S$10 S$50
Above S$5,000 to S$10,000 S$20 S$100
Above S$10,000 to S$30,000 1% of the claim 3% of the claim

Source: Singapore Courts, “How to file and serve a small claim”.2

How an SCT claim runs

Small Claims Tribunals process

  1. Pre-filing assessment. Complete the online assessment on the Community Justice and Tribunals System (CJTS); it gives you an assessment ID needed to file. The assessment is not legal advice.1
  2. Prepare documents as PDFs. Contract, invoices, receipts, photographs, emails and messages; for a business respondent, its ACRA profile obtained within 1 month; for claims over S$20,000, the signed Memorandum of Consent.2
  3. File and serve the claim through CJTS.3
  4. Try to settle online. Parties may use eNegotiation or eMediation; if they agree, they need not attend court.3
  5. Consultation. If unresolved, the parties attend a consultation with a registrar.3
  6. Hearing. If still unresolved, a tribunal magistrate hears the case and decides.3
  7. After the order. A party may appeal, apply to set aside an order made in its absence, or apply to enforce the order.3

Composite scenario: the S$27,000 claim that went to the wrong place

A homeowner’s kitchen and bathroom renovation is abandoned half-finished. The homeowner has paid S$27,000 against work valued by another contractor at S$11,000, and wants the S$16,000 difference plus S$11,000 to complete with someone else. Assuming the SCT will accept it, the homeowner files for S$27,000. The contractor refuses to sign a Memorandum of Consent, so the claim cannot proceed above S$20,000 unless the homeowner abandons S$7,000. Meanwhile, nobody has photographed the work as left, and the replacement contractor has already started. The homeowner must choose between giving up part of the claim and starting again in the Magistrate’s Court, with weaker evidence. This is a composite scenario, not a reported case.

Neighbour disputes: the Community Disputes Resolution Tribunals

Renovation also causes disputes between neighbours. The Community Disputes Resolution Tribunals (CDRT) hear claims about a neighbour’s act or omission that unreasonably interferes with the enjoyment or use of your home, under the Community Disputes Resolution Act 2015.4

  • Limit: the maximum monetary claim is S$20,000; larger claims go to a civil court.4
  • Time: claims must be filed within 2 years of the event that creates the cause of action.4
  • Examples listed by the judiciary include excessive noise, smell, smoke, light or vibration, obstructing your residence, and interfering with your movable property.4

Because property damage caused by a neighbour is excluded from the SCT,1 neighbour disputes belong in the CDRT or the civil courts. In strata developments, the MCST and its renovation by-laws are usually the faster first step; see condo renovation and MCST approval. For leaks from the unit above, the Strata Titles Board has its own jurisdiction; see inter-floor water seepage. Construction noise and permitted hours are covered in construction noise and working hours.

Mediation at the SMC and in the State Courts

Singapore Mediation Centre

For business-to-business construction disputes, or consumer disputes above CASE’s comfort zone, the Singapore Mediation Centre offers mediation with fees that scale with the amount in dispute. Under its Mediation Procedure Rules fee schedule from 1 March 2026 (all amounts include GST):8

Dispute amount Filing fee (non-refundable) Mediation fee per party
Up to S$60,000 S$27.25 Up to S$400 per session of up to 4 hours (up to S$100 per extra hour)
Above S$60,000 to S$250,000 S$272.50 S$1,000 to S$1,350 per full day
Above S$250,000 to S$1,000,000 S$272.50 S$3,000 to S$3,350 per full day

Weekend sessions carry a 20% surcharge.8 If the parties settle, the terms are recorded in a written settlement agreement; have it reviewed before signing if the sums are significant.

Court Dispute Resolution in the State Courts

Once a claim is in the Magistrate’s Court or District Court, mediation is also available through the State Courts’ Court Dispute Resolution Cluster. All parties must agree, or a judge may refer the case. It is free in the Magistrate’s Court; in most District Court cases each party pays S$250. Disputes are often resolved in one to three sessions of about three hours, and a party who fails to attend the first session without valid reason may be treated as unwilling to mediate, which the court can consider on costs.13

SOPA adjudication: for payment disputes under written construction contracts

For contractors, subcontractors and suppliers, the Building and Construction Industry Security of Payment Act 2004 (SOPA) is the fastest way to turn an unpaid progress claim into an enforceable decision. It applies to written construction and supply contracts for work in Singapore, but not to contracts for work on residential property that does not require the approval of the Commissioner of Building Control (s 4(2)(a)).10 Most small home renovations are therefore outside SOPA; commercial fit-outs and A&A works on commercial buildings usually are within it.

The core timetable:

Step Time SOPA section
Payment response due Contract date, capped at 21 days after the claim; or 14 days if the contract is silent s 11(1)
Dispute settlement period 7 days after the payment response deadline s 12(6)
Adjudication application (after notice of intention) Within 7 days after the entitlement first arises s 13(2)–(3)(a)
Determination 7 days in specified default cases, otherwise 14 days, after adjudication commences s 17(1)

Source: SOPA, current version.10 At the SMC, the adjudication application fee is S$654 including GST; adjudicators charge S$327 per hour including GST, capped at S$2,616 per day, and total adjudicator fees cannot exceed 10% of the claimed amount. The claimant pays a deposit of S$2,616 for claims up to S$24,000, or the lower of 10% of the claim and S$33,600 for larger claims (fee schedule, 10th edition, 1 August 2025).9

Adjudication gives temporary finality: the money moves now, and the underlying dispute can still be decided later in court or arbitration. For the full procedure, owners’ obligations and enforcement, see the SOPA guide.

The State Courts: Magistrate’s Court and District Court

If the claim is too big for the SCT, or the other side will not mediate, the civil courts decide.

Court Claim limit Notes
Magistrate’s Court Up to S$60,000 The simplified process in Order 65 applies to all originating claims: upfront production of documents with each pleading, limits on interim applications, and a possible simplified trial
District Court Up to S$250,000 The simplified process applies only if all parties consent
General Division of the High Court Above S$250,000 Full procedure

Sources: State Courts Act 1970, s 2;11 Rules of Court 2021, Order 65.12

Court is slower and more expensive than the tribunals. Parties may use lawyers, and the court deals with costs after deciding the merits, when it can take into account any unreasonable refusal to attempt amicable resolution.12 The general limitation period is 6 years from when the cause of action accrued for claims founded on contract or tort, with special rules for latent negligence damage.15 Note that the State Courts Act allows the District Court and Magistrate’s Court limits to be changed by order, so confirm the current figures before filing.11

Arbitration clauses

Some construction contracts send disputes to arbitration instead of court; the public-sector PSSCOC 2020, for example, has a clause on reference to arbitration (cl 35).16 If one party sues in court on a matter covered by an arbitration agreement, the other may apply to stay the court proceedings under section 6 of the Arbitration Act 2001; the application must be made after filing a notice of intention to contest or not contest and before delivering a pleading or taking any other step. The court will stay the action if there is no sufficient reason why the matter should not go to arbitration and the applicant is ready and willing to arbitrate.14

Factor Arbitration Court
Privacy Private Generally public
Decision-maker Chosen by the parties or an institution; can be a construction specialist Assigned judge
Cost Parties pay the arbitrator and any institution as well as their own lawyers No arbitrator’s fees; lawyers still cost money
Finality and appeal Award is final and binding (s 44); appeal only on a question of law, with all parties’ agreement or the court’s permission, and the parties can exclude it (s 49) Appeals available within the court system
Small claims Often disproportionate SCT and Magistrate’s Court simplified process designed for them

Source for the arbitration rows: Arbitration Act 2001, ss 44 and 49.14

For a small renovation contract, an arbitration clause can make a modest claim uneconomic to pursue. Owners and contractors should consider a tiered clause instead: negotiation, then mediation, then the SCT or courts for small claims, with arbitration reserved for claims above a stated value. This is a drafting suggestion, not a legal requirement; take advice on the wording.

Writing a letter of demand that can double as an offer to settle

A good letter of demand does more than ask for money. Written properly, it also serves as the offer of amicable resolution that the Rules of Court 2021 expect before an action begins, which must be in writing and open for at least 14 days unless the parties agree otherwise.12

What to put in the letter

  • The contract: date, parties, scope and price, with the quotation or contract attached.
  • The facts in order: what was agreed, what was done, what went wrong, and when you raised it before.
  • The items in dispute: a numbered list, each with an amount and the evidence (photograph number, invoice, message).
  • The remedy: payment of a stated sum, rectification of listed items by a date, or both.
  • The offer: a clear proposal to settle, or to mediate at CASE or the SMC, open for at least 14 days.
  • The next step: the forum you will use if there is no reply, for example the SCT within its 2-year window.
  • Tone: factual and specific. Accusations and threats make settlement harder and read badly to a tribunal later.

Keep proof of delivery. If the matter later goes to court, the court can look at how each side responded to offers when it decides costs.12

Common renovation disputes and where they usually go

The same few patterns account for most renovation and fit-out disputes. Recognising the pattern early points to the right forum.

Deposit paid, work never started or abandoned. The risk here is less about proving the claim and more about whether the business can pay. A CaseTrust-accredited renovation firm must protect deposits with a deposit performance bond, which is a reason to check accreditation before paying.6 If the business has closed, see protecting yourself if your contractor goes bust.

Defects after handover. Follow the contract’s defects procedure first: written notice, access to fix, then a claim for the cost if the contractor fails. Claims within the SCT limit and its 2-year window can go there; larger or later claims go to court.115 See defects liability and retention.

Disputed variations and the final bill. Most of these are about extra work agreed verbally and priced later. The evidence is whatever was written at the time. Between businesses on a written construction contract, SOPA adjudication can decide the disputed amount quickly, subject to the residential exclusion.10 See variation orders and provisional sums.

Delay. A claim for late completion depends on whether the contract fixed a completion date and a liquidated damages rate, and whether delays were caused by changes or late decisions on the owner’s side. See liquidated damages and extension of time.

Damage to a neighbour or common property. In a strata development, start with the MCST. Neighbour interference goes to the CDRT; damage claims between neighbours are excluded from the SCT.41

The evidence to keep

Disputes are won on documents made at the time, not on recollection.

Evidence file for any renovation or fit-out job

  • Contract documents: signed quotation or contract, terms and conditions, drawings, specifications, material schedules and approved samples.
  • Changes: every variation instruction and price, in writing. WhatsApp and email count; keep exports, not just screenshots. See variation orders and provisional sums.
  • Payments: invoices, receipts, bank transfer records, and what each payment was for.
  • Progress record: dated photographs and videos at each stage, especially concealed work before it is covered (waterproofing, pipes, wiring, fixings).
  • Approvals and third parties: MCST or landlord approvals, permits, and correspondence with authorities.
  • Defects: a defects register with dates notified, responses and photographs; any joint inspection or handover list.
  • Delay: the agreed programme, notices of delay, and site diaries or attendance records; see liquidated damages and EOT.
  • Expert evidence: an inspection report from an independent inspector or engineer appointed by you, before anything is altered.
  • Communications: letters of demand, offers to settle and replies, kept with their dates.

Keep the file for at least the limitation period. If the dispute may go to the SCT, scan everything to PDF; the tribunal asks for supporting documents in that format.2

How RRD approaches this

RRD’s quotations itemise the scope and list cost-risk items before signing, and variations are agreed in writing before the work is done. Progress is recorded with dated photographs, and each job closes with a joint inspection and signed handover list. That record is usually what lets a disagreement be settled on the facts.

Choosing the route by claim size and type

Claim You are a consumer (homeowner/tenant) vs a business You are a business vs a business, written construction contract You are a contractor owed money by a homeowner
Up to S$20,000 Complaint, CASE mediation (compulsory attendance if CaseTrust), then SCT within 2 years SOPA adjudication if in scope; SCT for services claims within limits; SMC mediation Letter of demand and offer; SCT (entity fees apply)
S$20,000 to S$30,000 CASE; SCT only with the other side’s Memorandum of Consent; otherwise Magistrate’s Court SOPA if in scope; SCT by consent; Magistrate’s Court SCT by consent, otherwise Magistrate’s Court
S$30,000 to S$60,000 CASE or SMC mediation; Magistrate’s Court (simplified process) SOPA if in scope; SMC mediation; Magistrate’s Court or arbitration per contract Magistrate’s Court; SOPA only if the work needed Building Control approval or the property is non-residential
S$60,000 to S$250,000 SMC mediation; District Court SOPA; SMC mediation; District Court or arbitration District Court; SOPA if in scope
Above S$250,000 SMC mediation; High Court or arbitration SOPA for progress payments; arbitration or High Court for the final account High Court or arbitration
Neighbour interference (any size up to S$20,000) MCST or town council, then CDRT Not applicable Not applicable

Notes: the SCT excludes commercial lease disputes and neighbour property damage;1 SOPA excludes residential work not requiring Building Control approval;10 an arbitration clause can displace the courts.14

If the other party is insolvent or has stopped trading, a judgment may be worth little; see protecting yourself if your contractor goes bust. The best dispute strategy remains prevention: verify the contractor’s licences and track record and do not let payments run ahead of work done.

Summary

  • Start with a written complaint and a written offer to settle; the Rules of Court 2021 expect it before litigation.12
  • Consumers with renovation firms can use CASE; CaseTrust-accredited firms must attend mediation and protect deposits with a bond.56
  • The SCT hears renovation-contract claims up to S$20,000, or S$30,000 with consent, filed within 2 years, without lawyers.12
  • Neighbour interference goes to the CDRT (up to S$20,000, 2 years).4
  • Contractors on written, non-excluded construction contracts can use SOPA adjudication; the SMC application fee is S$654.109
  • Larger claims go to mediation, the Magistrate’s Court (to S$60,000), the District Court (to S$250,000), the High Court, or arbitration where the contract requires it.1114

Questions people ask

Can I take my renovation contractor to the Small Claims Tribunals?

Yes, if the claim fits. The Small Claims Tribunals hear claims on contracts for the provision of services, and the judiciary gives a renovation contract as an example. The claim must not exceed S$20,000, or S$30,000 if both parties sign a Memorandum of Consent, and must be filed within 2 years of the event that gave rise to it. Lawyers cannot represent parties. You file online through the Community Justice and Tribunals System.

Can a contractor use the Small Claims Tribunals to recover an unpaid renovation bill?

Yes. The judiciary states that an individual or a corporate entity with an eligible claim may file. A company representing itself needs a letter of authorisation and its ACRA business profile. Filing fees are higher for entities than individuals: S$50 up to S$5,000, S$100 up to S$10,000, and 3% of the claim above S$10,000, compared with S$10, S$20 and 1% for individuals.

Does CASE mediation cost anything?

CASE charges a small administrative fee to both parties, which varies with the claim size and whether the consumer is a CASE member. For example, for a claim between S$10,001 and S$20,000 outside real estate, a member pays S$27.25 and a non-member S$109 (including 9% GST). If the business is CaseTrust-accredited, mediation charges are borne by CaseTrust, and the accredited business must attend if the consumer asks for mediation.

Can a renovation contractor use SOPA against a homeowner?

Often not. The Security of Payment Act does not apply to contracts for work on residential property that does not need approval from the Commissioner of Building Control, so most small home renovations without structural works fall outside it. Commercial fit-outs, A&A works on commercial or industrial buildings, and residential work needing plan approval are generally within SOPA, if the contract is in writing.

My neighbour's renovation is causing noise and damage. Where do I go?

For unreasonable interference with the enjoyment of your home, such as excessive noise, vibration or obstruction by a neighbour, the Community Disputes Resolution Tribunals hear claims up to S$20,000 filed within 2 years. Property damage caused by a neighbour is excluded from the Small Claims Tribunals. In a condominium, also report it to the MCST, which manages the estate under its by-laws.

What happens if my contract has an arbitration clause?

If you sue in court on a matter covered by the clause, the other party can apply to stay the court action under section 6 of the Arbitration Act 2001, and the court will generally send the dispute to arbitration unless there is sufficient reason not to. Arbitration is private and final, but the parties pay the arbitrator and the institution. For small renovation disputes it may cost more than the claim.

Do I need to send a letter of demand before going to court?

Under the Rules of Court 2021, parties must consider amicable resolution before and during proceedings, and a party should make an offer of amicable resolution before starting an action unless it has reasonable grounds not to. The offer must be in writing and open for at least 14 days unless the parties agree otherwise. A refusal to attempt amicable resolution can count against a party when costs are decided.

What evidence do I need for a renovation dispute?

The signed quotation or contract and any drawings; every variation and approval in writing, including WhatsApp messages; payment records; dated photographs and videos of the work at each stage; defect notices and replies; any expert or inspection report; and third-party records such as MCST or landlord correspondence. Organise them by date. The Small Claims Tribunals ask for supporting documents in PDF form when you file.

Sources

16 sources. Official sources are marked dark. Links were checked when this guide was last updated.

  1. judiciary.gov.sgSingapore Courts — “Cases eligible for a small claim”. https://www.judiciary.gov.sg/civil/cases-eligible-small-claim (accessed Nov 2026) ↩↩↩↩↩↩↩↩↩↩↩↩↩↩↩↩
  2. judiciary.gov.sgSingapore Courts — “How to file and serve a small claim” (filing fees and documents). https://www.judiciary.gov.sg/civil/how-to-file-serve-small-claim (accessed Nov 2026) ↩↩↩↩↩↩↩
  3. judiciary.gov.sgSingapore Courts — “File a small claim” (process and representation). https://www.judiciary.gov.sg/civil/file-small-claim (accessed Nov 2026) ↩↩↩↩↩↩
  4. judiciary.gov.sgSingapore Courts — “Cases eligible for a neighbour dispute claim” (Community Disputes Resolution Tribunals). https://judiciary.gov.sg/civil/cases-eligible-neighbour-dispute-claim (accessed Nov 2026) ↩↩↩↩↩↩↩
  5. case.org.sgConsumers Association of Singapore — “Mediation” (process and fee schedule, fees inclusive of 9% GST from 1 January 2024). https://www.case.org.sg/mediation/ (accessed Nov 2026) ↩↩↩↩↩↩↩
  6. case.org.sgCaseTrust — “CaseTrust Accreditation Scheme for Renovation Businesses” information kit (16 February 2023). https://www.case.org.sg/casetrust/wp-content/uploads/2023/02/Info-Kit-Renovation-16-Feb-2023.pdf (accessed Nov 2026) ↩↩↩↩
  7. case.org.sgConsumers Association of Singapore — Annual Report 2025/2026. https://www.case.org.sg/wp-content/uploads/2026/06/CASE-Annual-Report-2025_2026.pdf (accessed Nov 2026) ↩↩
  8. mediation.com.sgSingapore Mediation Centre — “Mediation Procedure Rules: Fee Schedule” (Annex B, 1 March 2026). https://mediation.com.sg/wp-content/uploads/2026/02/Fee-Schedule-Annex-B-1-March-2026.pdf (accessed Nov 2026) ↩↩
  9. mediation.com.sgSingapore Mediation Centre — “Building and Construction Industry Security of Payment Act Fee Schedule” (Annex E, 10th Edition, 1 August 2025). https://mediation.com.sg/wp-content/uploads/2025/08/SMC-Adjudication-Rules-Fee-Schedule-1-Aug-2025.pdf (accessed Nov 2026) ↩↩
  10. sso.agc.gov.sgBuilding and Construction Industry Security of Payment Act 2004 (current version), ss 4, 11, 12, 13 and 17. Singapore Statutes Online. https://sso.agc.gov.sg/Act/BCISPA2004 (accessed Nov 2026) ↩↩↩↩↩↩
  11. sso.agc.gov.sgState Courts Act 1970 (current version), s 2 (definitions of “District Court limit” and “Magistrate’s Court limit”). Singapore Statutes Online. https://sso.agc.gov.sg/Act/SCA1970 (accessed Nov 2026) ↩↩↩
  12. sso.agc.gov.sgRules of Court 2021, Order 5 (amicable resolution) and Order 65 (simplified process for proceedings in the Magistrate’s Court or District Court). Singapore Statutes Online. https://sso.agc.gov.sg/SL/SCJA1969-S914-2021 (accessed Nov 2026) ↩↩↩↩↩↩
  13. judiciary.gov.sgSingapore Courts — “Mediation” (Court Dispute Resolution in the State Courts). https://www.judiciary.gov.sg/alternatives-to-trial/mediation (accessed Nov 2026) ↩
  14. sso.agc.gov.sgArbitration Act 2001 (current version), ss 6, 44 and 49. Singapore Statutes Online. https://sso.agc.gov.sg/Act/AA2001 (accessed Nov 2026) ↩↩↩↩
  15. sso.agc.gov.sgLimitation Act 1959 (current version), ss 6 and 24A. Singapore Statutes Online. https://sso.agc.gov.sg/Act/LA1959 (accessed Nov 2026) ↩↩↩↩
  16. isomer-user-content.by.gov.sgBuilding and Construction Authority — Public Sector Standard Conditions of Contract for Construction Works 2020 (8th edition, July 2020), clause 35 (settlement of disputes). https://isomer-user-content.by.gov.sg/338/5349d125-0337-4dc3-a36d-623e599f2865/1-psscoc-for-construction-works-2020.pdf (accessed Nov 2026) ↩
Cite or link to this guide

Use this guide in a report, a tender or a by-law briefing. Please link to the page so readers get the current version.

RRD Engr & Constr. (2026). Resolving Renovation and Construction Disputes in Singapore: CASE, Mediation, Small Claims, SOPA Adjudication, Courts and Arbitration. RRD Field Guide. Updated 9 November 2026. https://rrd.sg/guides/renovation-disputes-resolution-singapore/
Report a correction