Mezzanines, Lofts and Storage Platforms in Singapore: BCA, SCDF, URA and JTC Approvals
Most mezzanines need approval. BCA exempts only a single-level storage platform in an industrial building up to 4 m high and 50 m² (spans up to 6 m), and timber lofts up to 5 m². Platforms up to 100 m² may use BCA's lodgment route. SCDF treats any platform people use as a storey, so a QP must get fire safety plan approval and an FSC.

A mezzanine looks like furniture. It arrives on a lorry as steel columns, beams and decking, goes up in a few days, and doubles the storage in a warehouse unit or adds an office above a workshop. That is exactly why so many are installed without approval: the buyer thinks of it as equipment, and the vendor sells it that way.
Singapore law does not. A platform people walk on is a floor. Under the Building Control Regulations, a “floor” includes a horizontal platform forming the surface of a storey, whatever it is made of.1 Under SCDF’s Fire Code, a “storey” includes platforms, mezzanines and attic levels.7 And URA counts intermediate load-bearing floors as gross floor area.16 Three regulators, three separate questions, and one structure that has to satisfy all of them, plus JTC or the landlord.
This guide sets out when a mezzanine, loft or storage platform is exempt from BCA approval and when it is not, what SCDF requires for escape, fire resistance and sprinklers, how URA treats the floor area, what JTC and landlords ask for, how to think about loads and racking standards, and what to check before you buy or lease premises that already have one. It draws on the January 2025 Toa Payoh collapse, where a mezzanine installed without approval came down on the people under it.
What counts as a mezzanine, loft or platform
The terms are used loosely in the trade. The regulators care about function, not names.
- Mezzanine: an intermediate floor within a storey, usually over part of the floor plate. In factories and warehouses it is typically steel-framed with a steel or timber deck, used for storage or an ancillary office.
- Storage platform: a single-level raised deck used to store goods, often with goods stored underneath as well.
- Loft: in homes and small shops, a raised storage or sleeping deck within a room.
- Rack-supported platform: a walkway or picking floor carried on the racking itself, so the racking becomes the structure.
- Racking: shelving for goods that people do not walk on, except to store and retrieve goods.
If people stand or walk on it, treat it as a floor until a Qualified Person (QP) tells you otherwise. That single rule would have prevented most of the cases that reach the news.
Who asks what: the approval map
| Who | Question they ask | Typical trigger for a mezzanine | Who submits |
|---|---|---|---|
| BCA | Is the structure safe, and is it building works needing plans and a permit? | Any platform outside the First Schedule exemptions | QP (PE civil/structural) |
| SCDF | Is it a storey that affects escape, fire resistance, sprinklers and alarms? | Any platform, mezzanine or racking accessible by occupants | QP for fire safety works; Registered Inspector at completion |
| URA | Does it add gross floor area or change use? | Most occupied mezzanines; offices in industrial units | QP or owner via URA’s channels |
| JTC or private landlord | Does the lease allow it, and will the base building carry it? | Mezzanines, storage platforms, tall racks, any fixing into the slab | Tenant, with PE endorsement where listed |
| MOM (WSH) | Are racks and platforms designed, used and maintained safely? | Every workplace with storage racks | Occupier and employer |
Sources: Building Control Regulations,1 Fire Code,7 SCDF,13 URA,1516 JTC,17 MOM.19
BCA: when structural approval is needed
The Building Control Act requires approved plans and, for structural works, a permit before building works start. Section 20 makes it an offence for any person who commences or carries out, or permits or authorises, building works without approved (or deemed approved) plans or without a required permit. The maximum penalty is a fine of S$200,000, two years’ imprisonment, or both, plus daily fines for a continuing contravention.5 Note the words “permits or authorises”: the owner or tenant who orders the work is within reach of the offence, not just the installer.
There are three routes: exempt, lodgment, and full plan approval.
Route 1: exempt “insignificant building works”
The First Schedule of the Building Control Regulations lists works that need no plan approval. Two items matter here. Both were revised or added for works from 1 April 2025.1
| First Schedule item | What is exempt | Conditions (all must be met) |
|---|---|---|
| 1(za) Storage platform | A single-level platform, including the space below it | Used solely for storing goods; in an industrial building or part of one; not accessible to the public; height not more than 4 m; area not more than 50 m²; no beam or slab span over 6 m; no cantilever span over 3 m |
| 1(zb) Access to that platform | A staircase, ladder or similar device | Used solely to give access to a platform that meets item 1(za) |
| 1(v) Loft | A loft | Only timber flooring; area not more than 5 m² |
| 1(w) Loft removal | Removing a loft | Loft of timber or steel construction |
Source: Building Control Regulations 2003, First Schedule.1
Read the storage-platform conditions literally. “Solely for storage of goods” rules out a platform with desks on it, a packing station, or an office. “Industrial building” rules out a shop, an office unit or a home. “Not accessible to the public” rules out showrooms. And every one of the dimensional limits must be met, not most of them.
BCA’s guidance on exempt works adds two cautions: owners should consult a QP when in doubt, and exempt works still need approvals from other authorities where those apply.6 An exemption from BCA is not an exemption from SCDF, URA or the landlord.
Route 2: BCA’s lodgment scheme (platforms up to 100 m²)
Since December 2023, BCA has run a lodgment scheme for listed low-risk works.3 The Ninth Schedule of the Building Control Regulations lists, as lodgment works, any single-level platform where the span of frame between two supports does not exceed 6 m, any cantilever does not exceed 3 m, the height above the adjoining ground or floor level does not exceed 4 m, and the area does not exceed 100 m², together with a staircase or ladder used solely to reach it.2
Under lodgment, a QP prepares and lodges the plans, and on acknowledgement they are deemed approved by the Commissioner of Building Control.3 It is faster, not lighter:
- A QP still designs, signs and is responsible for the plans.
- BCA states that the permit to commence structural works continues to apply where applicable, and construction supervision requirements are unchanged.3
- BCA may audit lodged plans; non-compliance or false declarations are offences, and BCA may refuse further lodgments.3
Note that the Ninth Schedule item for platforms does not repeat the “storage only” and “industrial building” conditions of the First Schedule exemption.2 That makes lodgment the natural route for a platform between 50 m² and 100 m², or a small platform outside an industrial building, provided the QP confirms it qualifies.
Route 3: structural plan approval and a permit
Everything else, including larger mezzanines, multi-level platforms, platforms over 4 m high, longer spans, and anything that changes the existing structure, goes through normal structural plan approval. When the structural plan is approved, a permit is required before the structural works start; it is applied for jointly by the developer, the QP and the builder, and BCA’s stated processing time for the permit is 7 days.4
Two features push a “simple” mezzanine into this route more often than owners expect:
- Fixing into the existing slab or columns. A free-standing platform still transfers its load through base plates into the floor slab. If that slab was not designed for the new point loads, the existing structure may need checking or strengthening, which is structural work in its own right. See our guide on hacking walls, slabs and structural elements.
- Staircase openings and edge protection. A stair that needs a new slab opening, or guardrails fixed to the existing structure, adds structural scope.
What “exempt” does not mean
An exempt platform still has to be safe. The occupier’s duties under workplace safety law do not depend on BCA approval, and MOM has said plainly that storage racks must be designed for the intended load and properly installed.19 An exempt platform still needs edge protection, a safe means of access and a known safe working load.
SCDF: a mezzanine is a storey
The Fire Code defines “storey” as any floor or part of it, including platforms, mezzanines, attic levels and M&E floors.7 SCDF’s 2025 enforcement briefing to Fire Safety Managers puts it directly: under clause 1.4.100, racking systems, platforms and mezzanines accessible by occupants are considered a floor or storey. Before such works start, a QP must assess feasibility against the Fire Code and submit plans to SCDF for approval, and a Registered Inspector (RI) must inspect the completed works before a Fire Safety Certificate (FSC) is applied for.13
Means of escape
A mezzanine adds people and a new place for them to be trapped. SCDF’s briefing notes that adding a mezzanine changes the building’s layout and occupant load, and that the QP must make sure escape from the mezzanine is appropriate and sufficient.13
For factory and warehouse units, the Fire Code sets a specific relaxation. One open staircase may serve mezzanine floors within an above-ground factory floor (clause 9.6.1a(2)) or warehouse floor (clause 9.8.1a(2)) only if all of the following are met:89
| Condition | Requirement |
|---|---|
| Area | Aggregate mezzanine area per unit not more than 60 m² |
| Stair | Open stair at least 1 m wide, of non-combustible construction |
| Travel distance | From the remote point on the mezzanine to exits, within Table 2.2A of the Fire Code |
| Structure | Elements of structure of the mezzanine at least 1-hour fire resistance |
| Height | Habitable height of the mezzanine floor not more than 24 m |
| Use | Store and/or ancillary office only |
Source: SCDF Fire Code 2023, clauses 9.6.1a(2) and 9.8.1a(2).89
Two practical consequences follow. First, a mezzanine larger than 60 m² per unit cannot rely on that single open stair; the QP has to design a compliant second means of escape or other arrangement. The Fire Code’s own illustration notes that where the allowable common path of travel is exceeded, the mezzanine needs a second remote exit access.8 Second, “ancillary office” means ancillary. A mezzanine that becomes the company’s main office, a showroom or a dormitory is a different use with different rules.
Spiral stairs are restricted. The Fire Code allows a spiral staircase to serve as a required exit only if it is external and unenclosed, serves only mezzanine floors, balconies or a storey with an occupant load of not more than 25 persons, is non-combustible, has a tread length of at least 750 mm, and is not more than 10 m high.12 An internal spiral stair to a warehouse mezzanine therefore usually cannot be counted as an exit.
Fire resistance of the structure
Unprotected steel loses strength quickly in a fire. The Fire Code requires any column or beam that supports a gallery to have the same fire resistance as the gallery, and gives the column and beam supporting a mezzanine floor as an example.10 Combined with the 1-hour requirement for mezzanine structure in factory and warehouse units,89 this usually means intumescent paint, board encasement or a tested system on the steel. Budget for it at the quotation stage; it is a common omission in “supply and install” mezzanine quotes.
Sprinklers, detection and alarms
A solid mezzanine deck creates a shadow under which ceiling sprinklers and detectors cannot reach. SCDF’s briefing lists assessing the need to extend sprinklers or detectors to the area underneath the mezzanine, and verifying that fire alarms are audible and visual alarms adequate on the mezzanine, as part of the QP’s work.13 In high-rack storage warehouses, the Fire Code requires sprinkler coverage to be extended to areas shielded by access platforms, and the platform supports to have the same fire resistance as the warehouse’s elements of structure.9 On manual call points, the Code allows the mezzanine floor of a factory or warehouse unit (where it complies with the single-stair clauses) to rely on call points on the main floor, provided no one on the mezzanine has to travel more than 30 m to reach the nearest one.11
Extending sprinklers is fire safety work in its own right, needs a QP (in JTC buildings, JTC lists fire protection works as needing a PE (Mechanical) endorsement17) and is often the longest lead item in a mezzanine project.
Plan approval, RI inspection and the FSC
Under section 56 of the Fire Safety Act, no person may carry out, or permit or authorise, fire safety works unless SCDF has approved the plans, and works must follow the approved plans. The maximum penalty is S$200,000, two years’ imprisonment, or both, with daily fines for continuing offences.14 After completion, section 60 requires an application for a Fire Safety Certificate; failure to comply carries a fine of up to S$10,000 plus daily fines for continuing offences.14 For the wider SCDF process, including minor A&A lodgements and the RI’s role, see our guide to SCDF fire safety approvals for fit-outs.
URA: does the mezzanine add gross floor area?
URA’s GFA handbook states that intermediate load-bearing floors are included as GFA.16 A mezzanine is an intermediate floor, so in most cases it adds GFA. That matters because the development’s approved GFA is capped by its plot ratio. If the building is already at its permitted GFA, there may be no room for the extra floor area, and URA’s clearance should be checked before the steel is ordered.
URA treats racking more favourably, but on narrow terms. Racking systems are excluded from GFA if they are standalone modular systems that do not form an integral component of the building (for example, not reinforced concrete construction) and are used for storage purposes in industrial developments. The storage must relate to the main industrial use, and human access should be for storing and retrieving goods only. URA also tells applicants to obtain BCA clearance for structural safety and SCDF clearance for fire safety for the racking.15
The line between “racking” and “mezzanine” is therefore about people. Racking with a catwalk used only to pick and put away stock may sit within URA’s exclusion; a deck used as a packing area or office is a floor. If in doubt, assume it is GFA and let the QP confirm.
Two other URA points arise often:
- Use. An office mezzanine in an industrial unit must remain ancillary to the industrial use. A mezzanine converted to a showroom, retail area or dwelling is a change of use. See our master guide to A&A approvals for URA’s change-of-use process.
- Landed homes. Mezzanines and attics in landed houses are governed by URA’s landed housing envelope controls and storey rules, not the industrial rules above. See our guide on landed house A&A approvals.
JTC and landlord consent
Statutory approval is half the story; the lease is the other half.
JTC premises
JTC requires tenants carrying out additions or alterations to seek JTC’s plan consent and clearance from the relevant authorities. Its Space Submission Handbook sorts works into three lists.17
| JTC list | What it means | Mezzanine-related items |
|---|---|---|
| List A (exempt from JTC plan consent) | No JTC consent needed, but other authorities’ submissions still apply | Shelving or racks up to 3 m high and 1.2 m wide, with gross weight (racks plus goods) not exceeding 7.5 kN/m² or the allowable design imposed load, whichever is lower; at least 1.2 m clear passageway; stored material non-combustible |
| List B (QP endorsement required) | Submit to JTC with plans endorsed by the relevant QP | Construction of mezzanine floor and storage platform: PE (Civil). Shelves or racks exceeding 3 m high and 1.2 m wide: PE (Civil). Fire protection works such as sprinklers: PE (Mech) |
| List C | Submission needed, no QP endorsement | Minor items such as small signage |
Source: JTC Space Submission Handbook (PCP-WI-09).17
JTC’s fitting-out guidelines also state that tenants must not drill into or hack the floor structure without JTC’s written consent.18 Most mezzanine base plates are bolted down, so this applies to nearly every installation.
Private landlords and strata buildings
Private industrial landlords usually require their own approval of drawings, PE endorsement and evidence of statutory approvals before installation, plus reinstatement at the end of the lease. In strata developments, the management corporation’s by-laws and approval process apply as well; see our guide on MCST renovation approval. Remember that a mezzanine you install is normally a mezzanine you must remove at handback; factor that into the business case and see our office reinstatement guide for how reinstatement obligations are typically framed.
Load ratings, slab capacity and racking standards
Two loads, not one
A mezzanine has to carry its own design load, and the existing slab has to carry the mezzanine. The second check is the one that gets skipped.
7.5 kN/m² JTC’s cap on gross weight for racks to qualify for exemption from plan consent (or the slab’s design load, if lower)17
An illustrative example shows why. Suppose (Illustrative) an 80 m² storage platform is designed for stored goods of 3 kN/m², and the deck and steel weigh 0.5 kN/m². The total load is about 3.5 × 80 = 280 kN. If it stands on nine columns, each base plate delivers roughly 31 kN to the slab. Spread over a 150 mm × 150 mm base plate, that is about 1,380 kN/m² locally (Illustrative). The slab’s design load per square metre says little about whether it can take that concentrated force without punching or cracking. A PE has to check the existing slab, the location of beams below, and whether larger base plates or load-spreading steel are needed.
Display the safe working load
MOM’s WSH circular on storage racks, issued after fatal rack collapses in warehouses, sets out what it expects: racks must be structurally stable and designed for the intended use; the safe working load should be prominently displayed; stacked racks must account for the weight of the racks and goods above; there must be safe means of access, including work-at-height measures; the design should be re-assessed before any change of use or change in goods stored; and racks should be inspected regularly, with defective parts repaired or replaced before use.19 MOM said it would step up inspections, with Stop Work Orders, Remedial Orders, prosecution and composition fines among possible actions.19
The same logic applies to a mezzanine: a load notice at the stair, stating the uniformly distributed load the deck is designed for, is cheap and prevents the “we just kept adding stock” failure.
Racking standards
Singapore has no separate racking statute; occupiers rely on the general duties above and on engineering standards. Two European standards are widely used for steel storage systems:
- EN 15512, for the structural design of adjustable beam pallet racking. Its 2020 edition aligns more closely with the Eurocodes and was amended in 2022 (EN 15512:2020+A1:2022).21
- EN 15635, for the application and maintenance of steel static storage equipment, including safety and inspection of equipment in use and rules for measuring and classifying damage to uprights and bracing.20
Ask the racking supplier which standard the design follows, for its load tables and installation tolerances, and for an inspection regime. For rack-supported platforms and multi-tier picking modules, the racking is the building structure, so the BCA, SCDF and URA questions above apply to the whole system, not just the deck.
The Toa Payoh mezzanine collapse (sourced public event)
On 28 January 2025, a mezzanine floor and storage racks collapsed in a warehouse unit at 11 Toa Payoh Industrial Park. Three people, including two children, were trapped under rugs and racks, and four people were taken to hospital.22
The Straits Times reported that SCDF’s inspections on 28 and 31 January found no Fire Safety Certificate had been obtained for the mezzanine, and that BCA had received no applications for the steel platform and racking system; both agencies said investigations were ongoing. BCA said the partial collapse did not affect the structural integrity of the building. The tenant told the newspaper that a vendor had installed the mezzanine in May 2024.22
The cost chain in a case like this runs well beyond the steel: rescue and injuries, loss of stock, a closed unit, investigation by two agencies, exposure to offences that carry fines of up to S$200,000 for unapproved building works and fire safety works,514 and removal or regularisation of whatever remains. We have not found a published outcome of the investigations as at November 2026.
A worked example: an 80 m² platform in a flatted factory
This is a composite scenario to show how the rules interact. It is illustrative, not advice for a specific site.
A tenant in a JTC flatted factory wants an 80 m² steel platform, 3.2 m high, with a 1 m-wide steel stair, to store packaging and to house two desks for the warehouse supervisor.
- BCA. At 80 m², it exceeds the 50 m² First Schedule exemption, and the desks would breach “solely for storage” anyway.1 If the QP keeps spans within 6 m and cantilevers within 3 m, the platform fits the Ninth Schedule lodgment limits of 4 m height and 100 m².2 The QP lodges the plans; the permit and supervision requirements continue to apply where applicable.3
- SCDF. It is a storey.7 At 80 m² it exceeds the 60 m² limit for a single open stair, so the QP must design a compliant second exit or another compliant arrangement.8 The structure needs 1-hour fire resistance; sprinklers and detection may need extending underneath; an RI inspects; an FSC follows.813
- URA. As an intermediate load-bearing floor, it is likely GFA.16 The QP checks the development’s approved GFA.
- JTC. “Construction of mezzanine floor and storage platform” is a List B item needing PE (Civil) endorsement; any sprinkler extension needs PE (Mech).17 Bolting into the slab needs JTC’s written consent.18
Had the tenant kept it to 48 m², storage only, within the spans and height limits, BCA plan approval would not have been needed,1 but SCDF, URA and JTC would still have been relevant. Size reduces the paperwork; it does not remove it.
Independent engineer's note
The PE who designs and endorses a mezzanine is certifying that the existing slab can take the new loads, that the steel is adequate, and that escape and fire resistance have been thought through with the fire safety QP. That judgment should answer to the owner or tenant who will stand on the floor, not to the vendor selling the steel. RRD recommends that owners appoint the PE directly, so the engineer contracts with and invoices the owner; RRD adds no mark-up to engineering fees, and owners are free to appoint any PE. Where clients ask, RRD’s usual independent engineering partner is CVC Engineers, a Singapore PE consultancy covering civil and structural design, PE endorsement and submissions, SCDF submissions and regularisation of unauthorised works. See why PE independence matters and our independent engineer model.
The approval sequence
Getting a mezzanine approved and built
- Define the use and size. Write down what will go on the platform (goods only, or people working), the area, the height and the load. These decide the route.
- Check the lease and the GFA. Confirm the landlord, JTC or MCST will permit it, and ask a QP to check approved GFA and use with URA’s records.
- Appoint the QPs. A PE (civil/structural) for the structure and a QP for fire safety works; in JTC buildings, a PE (Mech) for any sprinkler changes.
- Survey the existing structure. The PE checks slab thickness, beam layout and capacity before the layout is frozen.
- Choose the BCA route. First Schedule exemption, Ninth Schedule lodgment, or full structural plan approval and permit.
- Submit to SCDF. Fire safety plans for the mezzanine, escape, fire protection of steel and any sprinkler or alarm extension.
- Obtain landlord or JTC consent. Submit endorsed drawings as the lease or JTC’s lists require.
- Fabricate and install under supervision. Keep delivery notes, mill certificates, fire-protection product data and inspection records.
- Complete and certify. RI inspection and Fire Safety Certificate; BCA completion steps where applicable; post a load notice.
- Maintain. Inspect regularly, keep the load within the notice, and re-assess before changing what is stored.
Buying or leasing premises that already have a mezzanine
Unapproved mezzanines turn up in due diligence for factory and warehouse units more than almost any other item. Our guide to unauthorised works and regularisation covers the regularisation process in detail. Before you sign:
Pre-purchase or pre-lease checklist for an existing mezzanine
- Ask for the BCA approved structural plans, or the lodgment acknowledgement, and the permit and completion records for the mezzanine.
- Ask for SCDF’s approved fire safety plans and the Fire Safety Certificate that specifically covers the mezzanine, sprinkler extension and stairs.
- Check whether the mezzanine falls within the First Schedule exemption (storage only, industrial building, not public, up to 4 m high and 50 m², spans up to 6 m, cantilevers up to 3 m). If it does not, and there are no approvals, treat it as unauthorised.
- Ask how URA treated the floor area, and whether the use (storage, ancillary office) matches what is approved.
- For JTC premises, ask for JTC’s plan consent; for strata premises, the MCST’s approval.
- Look for a load notice, the design load and the original supplier. No load information means no one knows what it can carry.
- Inspect the steel: base plate fixings, missing bolts, bent members, corrosion, fire protection coating, guardrails and stair condition.
- Check whether sprinklers and detectors reach the area under the mezzanine and whether alarms can be heard on top.
- Price the downside: a PE’s as-built survey, possible strengthening, submissions and fees, or removal and reinstatement. Reflect it in the price or the lease terms.
- Do not let anyone occupy or load an unverified mezzanine until a PE has assessed it.
How RRD approaches this
On mezzanine and platform works, RRD starts with a site survey and asks for the lease conditions and existing structural information before quoting. Our itemised quotation lists the approval route, fire protection of steel, sprinkler or alarm extension and slab checks as separate cost-risk items, so they are visible before signing. Where a PE or fire safety QP is needed, we recommend the owner appoints them directly, and we build to their approved drawings with supervised works and a joint inspection at handover.
Key takeaways
- If people walk on it, it is a floor for BCA, a storey for SCDF and usually GFA for URA.
- BCA’s exemption is narrow: storage-only platforms in industrial buildings up to 4 m and 50 m², with span limits, and timber lofts up to 5 m².
- Platforms up to 100 m² may use BCA’s lodgment route, but a QP still designs and lodges them.
- SCDF approval, RI inspection and an FSC are needed for occupant-accessible mezzanines and platforms, regardless of BCA’s exemption.
- In factory and warehouse units, a single open stair works only up to 60 m² of mezzanine per unit, for store or ancillary office use.
- Check the existing slab, not just the new steel, and post the safe working load.
- Use the approval navigator for a first view of which approvals your works need.
Questions people ask
Do I need BCA approval for a steel mezzanine in my warehouse?
Usually yes. The only exemption for a platform is in the First Schedule of the Building Control Regulations: a single-level platform used solely for storing goods, in an industrial building, not accessible to the public, no more than 4 m high and 50 m², with beam or slab spans up to 6 m and cantilevers up to 3 m. Anything larger, used as an office, or outside an industrial building needs a Qualified Person to submit plans, either through BCA's lodgment route (up to 100 m²) or normal plan approval, plus a permit where required.
If BCA exempts my storage platform, do I still need SCDF approval?
Very likely. BCA's exemption covers only the Building Control Act. SCDF's Fire Code defines a storey as any floor or part of a floor, including platforms and mezzanines. SCDF's own enforcement material says racking systems, platforms and mezzanines accessible by occupants must be assessed by a Qualified Person and submitted for plan approval before works start, then inspected by a Registered Inspector before a Fire Safety Certificate is issued.
Does a mezzanine count as gross floor area (GFA)?
Generally yes. URA's GFA handbook states that intermediate load-bearing floors are included as GFA. URA excludes racking from GFA only in a narrow case: standalone modular racking that is not an integral part of the building, used for storage related to the main industrial use, where people access it only to store and retrieve goods. A platform people work on is not racking. Ask a QP to check the development's approved GFA before ordering steel.
Can a mezzanine have just one staircase?
In a factory or warehouse unit, the Fire Code allows one open staircase to serve mezzanine floors only if the total mezzanine area per unit does not exceed 60 m², the stair is at least 1 m wide and non-combustible, travel distances comply with the Code, the mezzanine structure has at least 1-hour fire resistance, and the mezzanine is used only as a store or ancillary office. Larger mezzanines need a fuller means-of-escape design by the QP.
Is a loft in my home allowed without approval?
Only a small one. The First Schedule exempts a loft that has only timber flooring and does not exceed 5 m². Removing an existing timber or steel loft is also exempt. A larger loft, or a concrete or steel one, is building works needing a QP. In strata buildings you also need MCST approval, and HDB flats have their own renovation rules. Landed homes have separate URA envelope controls on mezzanines and attics.
What happened in the Toa Payoh mezzanine collapse?
On 28 January 2025 a mezzanine floor and storage racks collapsed in a warehouse unit at 11 Toa Payoh Industrial Park, trapping three people, including two children; four people were taken to hospital. The Straits Times reported that SCDF found no Fire Safety Certificate for the mezzanine and BCA had received no applications for the steel platform and racking system. The tenant said a vendor had installed it in May 2024.
Who is liable if a contractor installs a mezzanine without approval?
Potentially more than one party. Section 20 of the Building Control Act makes it an offence for any person who carries out, or permits or authorises, building works without approved plans or a required permit, with a maximum fine of S$200,000, two years' jail, or both. The Fire Safety Act similarly covers anyone who carries out, permits or authorises fire safety works without approved plans. An owner or tenant who commissions the work cannot assume the vendor carries the risk alone.
I am buying a factory unit that already has a mezzanine. What should I check?
Ask the seller for the approved structural plans or lodgment acknowledgement, the BCA permit and completion records, SCDF's approved fire safety plans and Fire Safety Certificate covering the mezzanine, and evidence that URA counted it within approved GFA. For JTC premises, ask for JTC's plan consent. If none exist, budget for a PE's as-built survey and either regularisation or removal before relying on the space.
Sources
22 sources. Official sources are marked dark. Links were checked when this guide was last updated.
- sso.agc.gov.sgBuilding Control Regulations 2003, regulation 2 (“floor”), regulation 3A and First Schedule items 1(v), 1(w), 1(za), 1(zb) and paragraph 16, as amended by S 218/2025 with effect from 1 April 2025. Singapore Statutes Online, https://sso.agc.gov.sg/SL/BCA1989-S666-2003 ; text read via archived copy https://littdb.sfo2.cdn.digitaloceanspaces.com/litt/SG/SSOStatutes/subsidiary_legislation/BCA1989-S666-2003.html (accessed Nov 2026) ↩↩↩↩↩↩
- littdb.sfo2.cdn.digitaloceanspaces.comBuilding Control Regulations 2003, regulation 3B and Ninth Schedule, Part 1 (lodgment works), items 3 and 4, inserted by S 854/2023 with effect from 18 December 2023. Archived text https://littdb.sfo2.cdn.digitaloceanspaces.com/litt/SG/SSOStatutes/subsidiary_legislation/BCA1989-S666-2003.html (accessed Nov 2026) ↩↩↩
- bca.gov.sgBuilding and Construction Authority — “Permit for structural works”. https://www1.bca.gov.sg/safety-and-standards/applications-and-licenses/permit-for-structural-works/ (accessed Nov 2026) ↩
- lawplayer.comBuilding Control Act 1989, section 20 (building offences), compiled text. https://lawplayer.com/sg/act/BCA1989/20 (accessed Nov 2026) ↩↩
- bca.gov.sgBuilding and Construction Authority — “Building works not requiring approval”. https://www1.bca.gov.sg/guidelines-and-requirements/building-works-not-requiring-approval/ (accessed Nov 2026) ↩
- scdf.gov.sgSingapore Civil Defence Force — Fire Code 2023, Clause 1.4 “Definitions”, 1.4.100 “Storey”. https://www.scdf.gov.sg/fire-safety-services-listing/fire-code-2023/table-of-content/chapter-1-general/clause-1.4-definitions (accessed Nov 2026) ↩↩↩↩
- scdf.gov.sgSingapore Civil Defence Force — Fire Code 2023, Clause 9.6 “Purpose Group VI occupancy”, 9.6.1a(2) “Mezzanine floor” and explanatory figures. https://www.scdf.gov.sg/fire-safety-services-listing/fire-code-2023/table-of-content/chapter-9-additional-requirements-for-each-purpose-group/clause-9.6-purpose-group-vi-occupancy (accessed Nov 2026) ↩↩↩↩↩↩
- scdf.gov.sgSingapore Civil Defence Force — Fire Code 2023, Clause 9.8 “Purpose Group VIII occupancy”, 9.8.1a(2) “Mezzanine floors” and 9.8.3c “Sprinkler protection”. https://www.scdf.gov.sg/fire-safety-services-listing/fire-code-2023/table-of-content/chapter-9-additional-requirements-for-each-purpose-group/clause-9.8-purpose-group-viii-occupancy (accessed Nov 2026) ↩↩↩↩
- scdf.gov.sgSingapore Civil Defence Force — Fire Code 2023, Clause 3.3 “Fire resistance of elements of structure”. https://www.scdf.gov.sg/fire-safety-services-listing/fire-code-2023/table-of-content/chapter-3-structural-fire-precautions/clause-3.3-fire-resistance-of-elements-of-structure (accessed Nov 2026) ↩
- scdf.gov.sgSingapore Civil Defence Force — Fire Code 2023, Clause 6.3 “Electrical fire alarm system” (manual call points). https://www.scdf.gov.sg/fire-safety-services-listing/fire-code-2023/table-of-content/chapter-6-firefighting-systems/clause-6.3-electrical-fire-alarm-system (accessed Nov 2026) ↩
- scdf.gov.sgSingapore Civil Defence Force — Fire Code 2023, Clause 2.3 “Means of escape requirements” (spiral staircases). https://www.scdf.gov.sg/fire-safety-services-listing/fire-code-2023/table-of-content/chapter-2-means-of-escape/clause-2.3-means-of-escape-requirements (accessed Nov 2026) ↩
- scdf.gov.sgSingapore Civil Defence Force — “Common Fire Safety Enforcement Findings”, FSM Seminar 2025 (slides on mezzanines and QP/RI engagement). https://www.scdf.gov.sg/docs/default-source/fire-safety-docs/fire-safety-manager-(fsm)/fsm-2025/common-fire-safety-enforcement-findings.pdf (accessed Nov 2026) ↩↩↩↩↩↩
- lawplayer.comFire Safety Act 1993, sections 55, 56 and 60, compiled text. https://lawplayer.com/sg/act/FSA1993 (accessed Nov 2026) ↩↩↩
- ura.gov.sgUrban Redevelopment Authority — GFA Handbook, “Racking Systems for Storage Purposes”. https://www.ura.gov.sg/guidelines/development-control/development-control-handbooks/gross-floor-area/racking-systems-for-storage-purposes/ (accessed Nov 2026) ↩↩
- ura.gov.sgUrban Redevelopment Authority — GFA Handbook, “Floors” (intermediate floors). https://www.ura.gov.sg/guidelines/development-control/development-control-handbooks/gross-floor-area/floors/ (accessed Nov 2026) ↩↩↩↩
- jtc.gov.sgJTC Corporation — “Fitting-out and Renovation Works Guidelines” (v2). https://www.jtc.gov.sg/-/media/project/jtc-cx/corpweb/assets/get-help/fitting-out-and-renovation-works-guidelines_v2.pdf (accessed Nov 2026) ↩↩
- iac.gov.sgMinistry of Manpower — WSH Circular “Safe Use of Storage Racks”, 7 May 2015, with Annex A. https://iac.gov.sg/-/media/mom/documents/safety-health/circulars/2015/circular-20150507-safe-use-of-storage-racks.pdf (accessed Nov 2026) ↩↩↩↩
- knowledge.bsigroup.comBSI — “BS EN 15635:2008 Steel static storage systems. Application and maintenance of storage equipment” (product page and scope). https://knowledge.bsigroup.com/products/steel-static-storage-systems-application-and-maintenance-of-storage-equipment (accessed Nov 2026) ↩
- knowledge.bsigroup.comBSI — “BS EN 15512:2020 Steel static storage systems. Adjustable pallet racking systems. Principles for structural design” (product page); amendment EN 15512:2020+A1:2022. https://knowledge.bsigroup.com/products/steel-static-storage-systems-adjustable-pallet-racking-systems-principles-for-structural-design-1 (accessed Nov 2026) ↩
- stomp.sgThe Straits Times (republished by Stomp) — “Toa Payoh warehouse floor that collapsed and trapped 3 people not approved by SCDF, BCA”, February 2025. https://www.stomp.sg/singapore-seen/toa-payoh-warehouse-floor-that-collapsed-and-trapped-3-people-not-approved-by-scdf (accessed Nov 2026) ↩↩
Use this guide in a report, a tender or a by-law briefing. Please link to the page so readers get the current version.