Demolition and Strip-Out Safety in Singapore: Permits, Structural Stability, Asbestos and Waste

Updated 9 November 202620 min read18 sources, 10 officialBy RRD Engr & Constr, editorial standards
The short answer

In Singapore, demolition is high-risk construction work needing a permit-to-work system. Hacking non-load-bearing walls and false ceilings is exempt from BCA plan approval, but removing columns, beams, slabs or load-bearing walls needs approved plans, a BCA permit and a PE's method statement. Older buildings need an asbestos survey first, and debris must go through NEA-licensed collectors.

Demolition is the part of a project that people think requires the least skill. It does not. Building something follows a design; taking it apart means working with a structure whose load paths, reinforcement and condition are only partly known, while it is being weakened on purpose. That is why Singapore’s workplace safety law treats demolition as high-risk construction work, alongside deep excavation, crane lifting, piling and tunnelling.1

Most demolition in occupied buildings is not a tower coming down. It is a strip-out: an office returned to bare shell, a shop gutted for a new tenant, a factory cleared of plant, a few walls hacked to open a layout. Those jobs fall into a grey zone where owners assume no approvals are needed. Sometimes that is right. Often it is half right: BCA may not need to approve the plans, but the workplace safety rules on demolition, the asbestos survey duty and the waste rules still apply.

This guide sets out when BCA approval or a demolition permit is needed, what the WSH (Construction) Regulations require, what a demolition method statement should contain, how to keep a structure stable during strip-out, and how dust, noise, asbestos and waste are controlled. It draws on the fatal collapse during demolition in Tanjong Pagar in June 2023, which MOM addressed in Parliament.

Demolition, strip-out and hacking: what the law covers

The WSH (Construction) Regulations define demolition work as work incidental to or connected with the total or partial dismantling or razing of a building or other structure, and it includes removing or dismantling machinery or other equipment.1 On that definition, a strip-out that removes partitions, ceilings, raised floors and plant is partial dismantling, and is demolition work for WSH purposes.

The Building Control Regulations take a different cut. They ask whether the works are structural, and list in the First Schedule the “insignificant building works” that need no plan approval.2 A non-load-bearing wall is one that supports no load other than its own weight.2 If a wall, slab or beam carries anything else, removing it is structural work.

So there are two separate questions on every strip-out:

  1. Does BCA need to approve plans and issue a permit? That depends on whether structure is affected.
  2. Do the WSH demolition rules apply? For most strip-outs, yes.

When BCA approval or a demolition permit is needed

The decision table

Work BCA requirement Basis
Demolishing a non-load-bearing wall or partition Exempt from plan approval First Schedule item 1(p)2
Demolishing a suspended false ceiling and its supports Exempt First Schedule item 4A2
Removing a timber or steel loft Exempt First Schedule item 1(w)2
Removing temporary decking over a trench Exempt First Schedule item 1(fe)2
Demolishing an awning, window hood or cantilevered roof with a projection up to 6 m, or up to 10 m above the adjoining ground or floor Exempt First Schedule item 132
Demolishing an entire standalone non-residential single-storey building up to 10 m high and 100 m², at least 15 m from any residential building and at least 1.5 times its height from other buildings and public routes (not a bridge or concrete chimney) Exempt First Schedule item 142
Hacking or removing structural elements (beams, columns, RC walls, slabs) as part of A&A works Structural plan approval and permit; QP supervision Building Control Act ss 5, 6 and 8 as summarised by BCA5; regulation 213
Demolishing a whole building Demolition works plans approved; permit with method statement and impact assessment; pre-construction survey of neighbours Regulations 10B, 21, 32 and 333

The items in the First Schedule were revised for works carried out from 1 April 2025.2 Read every condition: the single-storey building exemption, for example, fails if the building is within 15 m of any residential building.2

Two points about exempt work. First, “exempt” means exempt from BCA plan approval, not from safety law, MCST or landlord approval, or the asbestos and waste rules. Second, the exemption depends on the wall actually being non-load-bearing. That is a question of fact about the building, and it is the one most often answered wrongly. See our guide on hacking walls and structural elements for how to establish it.

Structural demolition inside an A&A job

Where part of a building undergoing alteration is to be demolished, no separate demolition permit is required; the structural works permit for the A&A covers it.3 The structural works still need approved plans and a permit before work starts, applied for jointly by the developer, the QP and the builder; BCA’s stated processing time for the permit is 7 days.18 Starting without them is an offence under section 20 of the Building Control Act for anyone who carries out, permits or authorises the works, with a maximum fine of S$200,000, two years’ jail, or both.4

Demolishing a whole building

For demolition of a building, the Building Control Regulations require demolition works plans prepared by a QP. They consist of demolition plans and, where applicable, instrumentation and monitoring plans, and must be accompanied by an impact assessment report on neighbouring structures (including calculations for every element whose structural continuity will be cut) and calculations showing that floors can resist the debris load, or the load of the demolition machine plus debris where a machine is placed on the floor.3

Each demolition plan must show, as applicable:3

  • the site plan and distances to adjacent buildings that are not being demolished;
  • for each floor, the design imposed load, the demolition sequence and demolition zones, the method statement for handling and disposing of debris, the type and weight of any demolition machine, and the location of temporary ramps;
  • the demolition sequence of all beams, columns, walls, slabs and edge parapets;
  • shoring and temporary supports, protective hoardings, covered walkways, catch platforms, catch fans, scaffolding, screens and safety nets, the safe route of any machine, and anchorage details where a continuous beam is cut at a boundary;
  • for monitoring, the instruments, frequency and duration, allowable vibration limits, and CCTV positions to monitor progress, especially for high-rise demolition.

The permit application for demolishing a building must be accompanied by a method statement detailing how the works will be carried out and an impact assessment report on surrounding buildings.3 Before demolition starts, the builder must carry out a pre-construction survey of the condition of adjacent buildings and structures and give each adjacent owner a copy of the report on their property; the investigation reports must recommend measures to prevent settlement or movement that could damage neighbouring buildings, and the builder must carry out every one of those measures.3

S$200 BCA plan fee per storey for demolishing an entire general building (Building Control Regulations, Second Schedule)3

BCA issued a circular in 2022 titled “Enhanced requirements for ensuring the safety of demolition works”, which is cited in the 2026 revision of SS 557, the code of practice for demolition.6 We were not able to read the circular itself, so we do not summarise its thresholds here; your QP will apply its current requirements.

Strata buildings: what the MCST should insist on

In a 2014 advisory to management corporations, BCA said there had been cases of unauthorised demolition of structural elements during renovations, some resulting in Dangerous Building Orders on the MCST. It advised MCSTs that demolition of structural elements requires BCA plan approval, a permit and QP supervision; that renovation plans involving demolition of non-structural elements other than floor tiles should be endorsed by a PE certifying that no structural works are involved; that such demolition should be carried out by contractors with workers certified by BCA Academy; and that MCSTs should spot-check works. Whenever reinforcement bars are exposed, works should stop and a PE should be called in, with BCA notified.5 Our guide to MCST renovation approval covers the by-law side.

The WSH (Construction) Regulations on demolition

Permit-to-work

Part III of the WSH (Construction) Regulations lists demolition work as high-risk construction work, together with excavation and trenching deeper than 1.5 m, lifting operations with tower, mobile or crawler cranes, piling and tunnelling.1 For these works the regulations set up a permit-to-work system:1

Role Duty under Part III
Occupier of the worksite Appoint a project manager and a safety assessor; ensure a permit-to-work system is implemented
Supervisor of the workers Apply for the permit, stating the safety measures; post it at the work area with a sketch where practicable; keep measures in place throughout
Safety assessor Assess the measures and inspect the site and surroundings with the supervisor; endorse only if satisfied
Project manager Issue the permit only after proper risk evaluation, with no incompatible work nearby; monitor progress; revoke and stop work if risk arises
Anyone on site Report incompatible work nearby immediately

No person may carry out high-risk construction work without a permit-to-work first issued by the project manager.1 The WSH Council’s technical advisory notes that permits for demolition are typically issued floor by floor, so each floor is inspected before demolition starts on it.10

Part X: specific demolition duties

Part X places the duty on the occupier of the worksite to comply with regulations 70 to 76:1

Regulation Requirement
70 Preparation Remove external glass and cladding before demolition; shut off and cap gas, electric, water, steam and other supply lines, or relocate and protect any that must stay live
71 Adjacent structures Determine the stability of adjacent walls, ceilings, slabs and beams before and during demolition; if an adjacent structure may become unsafe, no demolition without sheet piling, shoring, bracing or other means to keep it stable
72 Load-bearing structures Removal of any column, beam, floor or other load-bearing structure must have due regard to the integrity of the remaining structure and follow a method statement prepared by a Professional Engineer
73 Walls and partitions Demolish systematically, completing work above each tier of floor beams before its supports are impaired; do not loosen masonry in masses that endanger floors or supports; leave nothing that may fall or be weakened by wind or vibration; with hand tools, provide safe footing and do not leave walls standing more than one storey above the uppermost floor where people are working
74 Access Safe, protected access and egress throughout
75 Barricades and catch platforms Substantial barricades with warning signs along bordering sidewalks and thoroughfares; catch platforms during demolition of exterior masonry walls or roofs unless an external scaffold gives equivalent protection
76 Mechanical methods Swinging weights only on structures not more than 24 m high, with a demolition zone of at least 1.5 times the height; a zone within 8 m of a clamshell bucket’s line of travel; adequate zones for other machines; only essential persons inside barricaded zones

Source: WSH (Construction) Regulations 2007, Part X.1

For worksites where the contract sum is under S$10 million, the occupier must also appoint a trained workplace safety and health co-ordinator; since 1 June 2024, failing to do so carries a fine of up to S$20,000, two years’ jail, or both (higher for repeat offenders).1 Our guide on work-at-height law and occupier liability explains who counts as the occupier and principal, which matters because most of these duties sit with the occupier.

SS 557: the code of practice

SS 557 is the Singapore Standard code of practice for demolition. MOM told Parliament in July 2023 that SS 557 is an Approved Code of Practice setting standards for safe demolition.7 SS 557 was revised in 2026; the revision expands requirements before demolition across more structure types and methods and adds a clause on safe working zones. Its contents cover the demolition plan and stability report, temporary supports (including propping requirements when machines operate), health and safety, environmental factors, debris and waste handling, methods of demolition, stability-sensitive structures and special structures.6 The WSH Council’s demolition page still lists the 2010 edition,11 so confirm with your PE which edition applies to your project.

The demolition method statement

The method statement is where the plan becomes a sequence of physical steps. It is required by regulation 72 whenever load-bearing elements are removed, it accompanies BCA’s permit application for demolishing a building, and debris handling must be covered in the demolition plans.13 After the Tanjong Pagar collapse, the WSH Council’s alert stated that a demolition method statement must be prepared by a PE and must ensure that the stability of walls, ceilings, slabs, beams and adjacent structures is determined before and during demolition, taking into account the design and internal elements of each portion.8

What a demolition method statement should cover

  • Scope, drawings relied on (as-built or surveyed), and the PE’s assessment of the structural system and condition.
  • Pre-demolition surveys: structural stability, existing services and hazardous substances, including asbestos.10
  • Isolation of gas, power, water and other services, and protection of any that must stay live.1
  • Removal of external glass and cladding before demolition.1
  • Sequence and zones, floor by floor and element by element, normally top-down.38
  • Temporary supports: layout, capacity, sequence of installation and removal.3
  • Floor loading: safe working load for debris and any machine, ramps, and limits on debris build-up.310
  • Machine selection, weight, route and exclusion zones.13
  • Protection of the public and neighbours: hoardings, covered walkways, catch platforms, catch fans, netting.3
  • Monitoring of adjacent buildings, vibration limits and trigger actions.3
  • Debris handling: chutes, holding areas, transport and licensed disposal.310
  • Permit-to-work arrangements and supervision, with hold points where work must stop for inspection.1
  • Emergency and stop-work triggers, including exposed reinforcement or unexpected cracking.5

Keeping the structure stable during strip-out

Know what is load-bearing before anyone picks up a breaker

The WSH Council’s technical advisory describes a fatal case where a roof slab collapsed on a worker after the walls supporting it were largely demolished. The roof slab simply rested on brick walls; no props had been provided, and no competent person had assessed the slab and walls before demolition.10 A brick wall that looks like a partition can be carrying a slab, especially in older shophouses, extensions and buildings altered over decades. Verify against approved plans and site investigation, and where there is doubt, treat it as load-bearing until a PE says otherwise.

Prop first, then remove

Regulation 71 prohibits demolition where an adjacent structure may become unsafe unless shoring, bracing or other means keep it stable, and regulation 72 requires a PE’s method statement whenever load-bearing elements come out.1 SS 557 includes a dedicated clause on temporary supports and a table on propping requirements during machine operation.6 On a strip-out, typical triggers for a PE-designed propping scheme are:

  • forming a new opening in a load-bearing wall or slab;
  • removing a beam, column or transfer element;
  • demolishing walls that a slab or roof may be resting on;
  • placing a mini-excavator or breaker on a suspended floor;
  • stockpiling debris on a suspended floor.

Watch the floor loads

Debris is heavy and machines concentrate it. The Building Control Regulations require demolition plans to show that floors can resist debris loads, and machine loads where machines are used on floors.3 The WSH Council’s advisory says the safe working load, allowing for debris accumulation and machinery, should be determined by a PE, and floors must not be loaded beyond it; steel ramps and limits on debris build-up are among the precautions.10

An illustrative example shows the scale. Suppose (Illustrative) crushed concrete debris weighs about 15 kN/m³ when loose. A 0.5 m deep pile over a 4 m × 4 m patch weighs roughly 0.5 × 16 × 15 = 120 kN, or about 7.5 kN/m² over that patch. Compare that with the design imposed load for the floor, which the Building Control Regulations require demolition plans to state for each area.3 If the pile exceeds it, a single afternoon of hacking without debris removal can overload a suspended slab.

Work top-down and do not leave walls standing high

Regulation 73 requires work above each tier of floor beams to be completed before its supports are impaired, and, where hand tools are used, walls and partitions must not be left standing more than one storey above the uppermost floor where people are working.1 The WSH Council’s alert after Tanjong Pagar recommended a top-down wall-hacking approach to reduce the chance of a large wall segment collapsing.8

Protect the neighbours and the people next door

Adjacent structures must be assessed before and during demolition.1 In October 2025, answering a question on a different fatal wall collapse at a worksite in Toh Close, MOM told Parliament that existing safety requirements already require contractors to check the integrity of surrounding structures and to provide adequate shoring to prevent collapse during construction work.12 In strip-outs inside live buildings, “neighbours” includes the tenants on the other side of a shared wall and the public in the corridor outside the hoarding; see our guide to working in live premises.

Know when to stop

BCA’s advice to MCSTs is a sound site rule anywhere: when reinforcement bars are exposed unexpectedly, stop, call a PE, and notify BCA.5 Other stop triggers include new cracking in slabs or walls, movement in props, unexpected services and suspected asbestos. Post-tensioned slabs need particular care, because cutting a tendon releases stored force; see our guide on hacking structural elements.

The Tanjong Pagar demolition collapse, June 2023 (sourced public event)

On 15 June 2023, during demolition of a building in Tanjong Pagar, a wall segment at the second storey collapsed. According to the WSH Council’s alert, based on MOM’s preliminary investigations, a worker walking along the pedestrian walkway beside the worksite hoarding was pinned by the collapsed structure and died at the scene.8 The Straits Times reported that BCA and MOM described it as a reinforced concrete wall about 10 m long and 3.8 m high; BCA instructed the project parties to stop all construction activities and said it would revoke the permit for all works while investigations were ongoing, and MOM instructed the worker’s employer to stop all works at the site.9

On 4 July 2023, MOM told Parliament that it was investigating, had issued a full Stop Work Order to the occupier of the worksite, would review whether measures beyond SS 557 were needed once investigations concluded, and that the chief executives concerned would be required to personally account to MOM.7 We have not found a published outcome of the investigation as at November 2026.

The cost chain of a collapse like this runs from a death and a closed site to permit revocation, investigations by two agencies, potential prosecution, delay to a whole redevelopment and the reputational cost to every company involved.

Ministry of Manpower, oral answer to Parliament, 4 July 2023

Answering a question on additional safety measures for demolition after the Tanjong Pagar incident, MOM pointed to SS 557 as the Approved Code of Practice for safe demolition, said demolition and other higher-risk activities “require greater extent of risk assessment and preventive measures”, and noted that incidents involving such activities would generally attract more severe penalties where reasonable steps were not shown.7

Dust, noise and the neighbours

Dust

Section 18 of the Environmental Public Health Act makes it an offence to fail to take reasonable precautions to protect people using any public place from flying dust or falling fragments during the erection, alteration, construction or demolition of any building. NEA’s code for environmental control officers lists the maximum fine as S$2,000 for a first offence, S$4,000 for a second and S$10,000 for a third and subsequent offence.15 The same code recommends water sprinklers or sprays, shielding, netting, covers and hoardings, netting or barriers on scaffolding of suitable height, prompt removal of debris, and lined debris chutes from upper floors; it also notes that open burning of construction waste is an offence.15

Occupiers of construction sites with a contract sum above S$10 million must appoint an environmental control officer: part-time up to S$50 million, full-time above that.15 Smaller strip-outs do not need one, but the dust offence applies to everyone.

Noise

Demolition is among the noisiest construction activities. NEA’s code for environmental control officers recommends restricting noisier activities such as piling, concreting and demolition to daytime, and specifies real-time noise meters for demolition and piling at the specified construction sites it covers.15 Statutory noise limits, permitted hours and building-specific rules for noisy works are set out in our guide to construction noise and working hours. In commercial buildings, the landlord’s permitted hours for hacking often decide the programme; our office reinstatement guide shows how much difference those hours make.

Asbestos before demolition

Older buildings can contain asbestos-containing materials that are harmless until they are broken up. The WSH (Asbestos) Regulations 2014 deal with them before the first wall comes down.13

  • Survey duty. Before building works (defined to include demolition) start on a building for which no Certificate of Statutory Completion or Temporary Occupation Permit was issued on or after 1 January 1991, the employer or principal must receive a survey report from a competent person they appoint, stating whether asbestos or asbestos-containing material is fixed or installed in the building.13
  • Conduct of the survey. The competent person must exercise care and diligence, take samples with the owner’s or occupier’s consent, and submit the report and test results within three months of appointment; the employer or principal must keep them for at least two years.13
  • Removal before demolition. Where the survey (or the owner) indicates asbestos is present, the employer or principal must ensure, so far as reasonably practicable, that asbestos-removal work by an approved asbestos-removal contractor is completed before demolition starts.13
  • Notification. The approved asbestos-removal contractor must notify MOM at least one week before starting, uploading the removal work plan and survey result, and afterwards submit the asbestos waste disposal certificate and an air monitoring report.14

For buildings completed later, MOM may still direct a survey where it has reason to believe asbestos may be present.13 Our guide on asbestos in renovation and strip-out covers identification, removal and costs in detail.

Waste disposal and licensed collectors

Demolition waste is a regulated waste stream, not general refuse.

  • Licensed collection. NEA licenses general waste collectors by class, and lists construction and renovation debris under Class A, collected by licensed collectors. Check NEA’s list to confirm a collector’s licence covers the class you need.16
  • Licensed destination. NEA has stated that renovation waste such as hacked concrete and tiles is industrial waste that must be sent to a licensed recycling facility and not mixed with general waste or recyclables, and that building bins are only for general waste and recyclables from the occupiers they serve.17
  • Illegal dumping. In August 2021, a company director was fined S$18,000 for dumping renovation waste (hacked concrete and tiles in 231 jute bags) into bins serving premises in several areas. NEA stated that the maximum penalty for a first-time illegal dumping offence is a fine of up to S$10,000, up to 12 months’ jail, or both, rising for repeat offenders.17
  • On site. NEA’s code asks that debris be stored properly, removed quickly rather than allowed to accumulate, and kept in skips accessible to waste vehicles.15
  • Asbestos waste follows its own route, evidenced by the disposal certificate submitted to MOM.14

Ask your contractor for the collector’s licence details and for disposal tickets or records, and keep them with the project file. If a quotation for disposal looks too cheap, ask where the waste is going.

Independent engineer's note

On structural strip-outs and demolition, the PE decides what is load-bearing, designs the propping, sets floor load limits and writes or approves the method statement that everyone on site relies on. Those judgments should not be shaped by the contractor’s programme or price. RRD recommends that owners appoint the PE directly, so the engineer contracts with and invoices the owner; RRD adds no mark-up to engineering fees, and owners are free to appoint any PE. Where clients ask, RRD’s usual independent engineering partner is CVC Engineers, a Singapore PE consultancy covering civil and structural design, PE endorsement and submissions, temporary structures and regularisation of unauthorised works. See why PE independence matters and our independent engineer model.

How RRD approaches this

Before quoting a strip-out, RRD surveys the site and asks for the approved plans so that load-bearing elements, services and likely asbestos-containing materials are identified up front. Our itemised quotation separates propping, asbestos survey and removal, debris disposal through licensed collectors, and permitted-hours constraints as cost-risk items. On site we work under a permit-to-work system with a safety briefing and supervision, and hand over with a joint inspection and disposal records.

Owner’s checklist

Before any demolition or strip-out starts

  • Obtain the approved structural plans, or commission a PE’s survey, to identify every load-bearing element.
  • Confirm in writing which items are exempt under the First Schedule and which need BCA plans and a permit.
  • For structural work, appoint a PE (ideally directly), obtain plan approval and the permit, and arrange QP supervision.
  • For whole-building demolition, ensure demolition works plans, the permit with method statement and impact assessment, and the pre-construction survey of neighbours are in place.
  • Confirm the contractor will run a permit-to-work system with a named project manager and safety assessor.
  • Check the method statement covers sequence, propping, floor loads, debris handling and stop triggers.
  • Commission the asbestos survey early if the building’s CSC or TOP pre-dates 1 January 1991, and allow time for removal by an approved contractor.
  • Obtain MCST or landlord approval, including permitted hours for noisy works and any PE endorsement they require.
  • Agree dust controls (screens, sprays, chutes) and how debris will be moved through the building.
  • Confirm the licensed waste collector and keep disposal records.
  • Make sure utilities are isolated and capped before work starts.
  • Brief neighbours and building management on the programme.

Use our approval navigator for a first view of which approvals your works need. If the strip-out is the end of a lease, start with our office reinstatement guide and the late handback cost calculator.

Questions people ask

Do I need a BCA permit to strip out an office?

Usually not, if the strip-out is limited to non-structural items. The First Schedule of the Building Control Regulations exempts the demolition of non-load-bearing walls and of suspended false ceilings, among other items. If the works touch structural elements such as beams, columns, slabs or load-bearing walls, approved plans and a permit to carry out structural works are needed first, and a Qualified Person must supervise. Workplace safety rules apply either way.

Is a strip-out 'demolition work' under the WSH regulations?

It can be. The WSH (Construction) Regulations define demolition work as work connected with the total or partial dismantling or razing of a building or structure, including removing or dismantling machinery or equipment. Demolition is listed as high-risk construction work, which must be carried out under a permit-to-work issued by the project manager after evaluation by a safety assessor. Many strip-outs fall within that definition.

Who must prepare the demolition method statement?

Where demolition involves removing any column, beam, floor or other load-bearing structure, regulation 72 of the WSH (Construction) Regulations requires the work to follow a method statement prepared by a Professional Engineer, with due regard to the integrity of the remaining structure. For demolition of a building, BCA's permit application must also include a method statement and an impact assessment report on surrounding buildings.

What happened in the Tanjong Pagar demolition collapse?

On 15 June 2023, a wall segment at the second storey of a building under demolition in Tanjong Pagar collapsed and a worker was killed. MOM told Parliament on 4 July 2023 that it was investigating and had issued a full Stop Work Order to the occupier, and that it would review whether measures beyond SS 557, the code of practice for demolition, were needed. The WSH Council's alert called for a PE's method statement and a top-down approach.

Do I need an asbestos survey before demolition?

For many older buildings, yes. Under the WSH (Asbestos) Regulations 2014, before building works (including demolition) on a building for which no Certificate of Statutory Completion or Temporary Occupation Permit was issued on or after 1 January 1991, the employer or principal must receive a survey report from a competent person. If asbestos is present, it must be removed by an approved asbestos-removal contractor before demolition starts.

Can demolition debris go into the building's bins?

No. NEA classifies renovation waste such as hacked concrete and tiles as industrial waste that must be sent to a licensed recycling facility and not mixed with general waste or recyclables. Construction and renovation debris is collected by NEA-licensed general waste collectors. In 2021 a company director was fined S$18,000 for dumping renovation waste in bins serving other premises.

What is temporary propping and when is it needed?

Temporary propping means shores, braces or props installed to carry loads while a structural element is removed or weakened. The WSH (Construction) Regulations prohibit demolition where an adjacent structure may become unsafe unless shoring, bracing or other means are provided to keep it stable. In practice, any removal of a beam, column, slab or load-bearing wall, or work that leaves a slab resting on walls being demolished, needs a propping design from a PE.

What are the dust and noise rules for demolition?

Section 18 of the Environmental Public Health Act requires reasonable precautions to protect people in public places from flying dust and falling fragments during demolition; fines rise from S$2,000 to S$10,000 for repeat offences. NEA's code for environmental control officers lists water sprays, netting, screens and debris chutes, and recommends restricting noisy demolition to daytime. Construction noise limits and permitted hours are covered in our noise guide.

Sources

18 sources. Official sources are marked dark. Links were checked when this guide was last updated.

  1. sso.agc.gov.sgWorkplace Safety and Health (Construction) Regulations 2007 (S 663/2007), regulations 2, 6, 10 to 19 (Part III, permit-to-work) and 69 to 76 (Part X, demolition), as amended including S 434/2024 with effect from 1 June 2024. Singapore Statutes Online, https://sso.agc.gov.sg/SL/WSHA2006-S663-2007 ; text read via archived copy https://littdb.sfo2.cdn.digitaloceanspaces.com/litt/SG/SSOStatutes/subsidiary_legislation/WSHA2006-S663-2007.html (accessed Nov 2026) ↩↩↩↩↩↩↩↩↩↩↩↩↩↩↩↩
  2. littdb.sfo2.cdn.digitaloceanspaces.comBuilding Control Regulations 2003, First Schedule (Insignificant building works), items 1(fe), 1(p), 1(w), 4A, 13, 14 and paragraph 16, as amended by S 218/2025 with effect from 1 April 2025. Archived text https://littdb.sfo2.cdn.digitaloceanspaces.com/litt/SG/SSOStatutes/subsidiary_legislation/BCA1989-S666-2003.html (accessed Nov 2026) ↩↩↩↩↩↩↩↩↩↩
  3. littdb.sfo2.cdn.digitaloceanspaces.comBuilding Control Regulations 2003, regulations 10B (demolition works plans), 21 (permit to carry out structural works, including demolition), 32 (pre-construction survey) and 33 (impact assessment report), and Second Schedule paragraph 4A (fee for demolition of entire building). Archived text https://littdb.sfo2.cdn.digitaloceanspaces.com/litt/SG/SSOStatutes/subsidiary_legislation/BCA1989-S666-2003.html (accessed Nov 2026) ↩↩↩↩↩↩↩↩↩↩↩↩↩↩↩↩↩↩
  4. lawplayer.comBuilding Control Act 1989, section 20 (building offences), compiled text. https://lawplayer.com/sg/act/BCA1989/20 (accessed Nov 2026) ↩
  5. bca.gov.sgBuilding and Construction Authority — “Advisory on Control of Renovation Works Involving Demolition of Non-Structural Elements (Other Than Floor Tiles)”, BCA BC BMSC/CIR/2013/03, 14 January 2014. https://www.bca.gov.sg/bmsm_eservice/Others/Advisory_on_Control_of_Renovation_Works.pdf (accessed Nov 2026) ↩↩↩↩
  6. singaporestandardseshop.sgEnterprise Singapore — SS 557:2026 “Code of practice for demolition” (preview: foreword, contents and scope). https://www.singaporestandardseshop.sg/Product/GetPdf?fileName=260219165329SS+557-2026+Preview.pdf&pdtid=5aa50487-a0d5-4af0-af01-e5e4455b16e5 (accessed Nov 2026) ↩↩↩
  7. mom.gov.sgMinistry of Manpower — “Oral answer to PQ on high-risk construction activities”, Question No. 4736 by Mr Yip Hon Weng, 4 July 2023. https://www.mom.gov.sg/newsroom/parliament-questions-and-replies/2023/0704-oral-answer-to-pq-on-high-risk-construction-activities (accessed Nov 2026) ↩↩↩
  8. tal.sgWorkplace Safety and Health Council — WSH Alert, “Worker pinned by collapsed structure”, 23 June 2023. https://www.tal.sg/wshc/-/media/tal/wshc/resources/newsletters/wsh-bulletins/files/20230623a.pdf (accessed Nov 2026) ↩↩↩↩
  9. stomp.sgThe Straits Times (republished by Stomp) — “20-year-old found dead under 2m of debris at Tanjong Pagar building demolition site”, June 2023. https://www.stomp.sg/singapore-seen/20-year-old-found-dead-under-2m-of-debris-at-tanjong-pagar-building-demolition-site (accessed Nov 2026) ↩
  10. tal.sgWorkplace Safety and Health Council — “Technical Advisory for Demolition” (Programme-Based Engagement). https://www.tal.sg/wshc/-/media/tal/wshc/resources/publications/technical-advisories/files/technical_advisory_for_demolition.pdf (accessed Nov 2026) ↩↩↩↩↩↩
  11. tal.sgWorkplace Safety and Health Council — “Demolition” topic page. https://www.tal.sg/wshc/topics/demolition/demolition (accessed Nov 2026) ↩
  12. mom.gov.sgMinistry of Manpower — “Written answer to PQ on updates on investigation for fatal wall collapse incident”, 14 October 2025. https://www.mom.gov.sg/newsroom/parliament-questions-and-replies/2025/1014-written-answer-to-pq-on-updates-on-investigation-for-fatal-wall-collapse-incident (accessed Nov 2026) ↩
  13. sso.agc.gov.sgWorkplace Safety and Health (Asbestos) Regulations 2014 (S 337/2014), regulations 2, 3, 4, 5 and 17. Singapore Statutes Online, https://sso.agc.gov.sg/SL/WSHA2006-S337-2014 ; text read via archived copy https://littdb.sfo2.cdn.digitaloceanspaces.com/litt/SG/SSOStatutes/subsidiary_legislation/WSHA2006-S337-2014.html (accessed Nov 2026) ↩↩↩↩↩
  14. nea.gov.sgNational Environment Agency — “Code of Practice for Environmental Control Officers for Specified Construction Sites” (5th edition, 9 June 2022), sections 3, 8.4, 8.5 and the table of penalties under the Environmental Public Health Act. https://www.nea.gov.sg/docs/default-source/our-services/pest-control/environmental-control-officer/code-of-practice-for-eco-(scs)—5th-edition-finalad363da3b1064f94bdcf2f62f9429adf.pdf (accessed Nov 2026) ↩↩↩↩↩
  15. nea.gov.sgNational Environment Agency — “Waste collection systems” (licensed general waste collectors and waste classes). https://www.nea.gov.sg/our-services/waste-management/waste-collection-systems (accessed Nov 2026) ↩
  16. nea.gov.sgNational Environment Agency — advisory, “Company director fined a total of $18,000 for illegal disposal of waste from renovation works”, 20 August 2021. https://www.nea.gov.sg/media/news/advisories/index/company-director-fined-a-total-of-18-000-for-illegal-disposal-of-waste-from-renovation-works (accessed Nov 2026) ↩↩
  17. bca.gov.sgBuilding and Construction Authority — “Permit for structural works”. https://www1.bca.gov.sg/safety-and-standards/applications-and-licenses/permit-for-structural-works/ (accessed Nov 2026) ↩
Cite or link to this guide

Use this guide in a report, a tender or a by-law briefing. Please link to the page so readers get the current version.

RRD Engr & Constr. (2026). Demolition and Strip-Out Safety in Singapore: Permits, Structural Stability, Asbestos and Waste. RRD Field Guide. Updated 9 November 2026. https://rrd.sg/guides/demolition-strip-out-safety/