Asbestos in Renovation and Strip-Out in Singapore: Surveys, Approved Removal and Owner Duties

Updated 9 November 202619 min read18 sources, 13 officialBy RRD Engr & Constr, editorial standards
The short answer

In Singapore, building works on a building whose completion certificate or TOP was issued before 1 January 1991 must not start until a competent person has surveyed for asbestos. Any asbestos found may only be removed by an MOM-approved asbestos-removal contractor, which must notify MOM at least 7 days ahead. The occupier must ensure no one else removes it, and the waste goes by licensed collector to Semakau Landfill.

Asbestos is no longer used in Singapore’s buildings, but a great deal of it is still in them. Buildings completed before the 1990s may contain it in roof sheets, ceiling boards, partitions, floor tiles, pipe lagging and fire protection boards. Left intact, most of these materials do little harm. The moment of danger is the renovation, the A&A works or the strip-out, when the material is drilled, broken or torn down and its fibres go into the air that workers and occupants breathe.

Singapore regulates that moment closely. The Workplace Safety and Health (Asbestos) Regulations 2014 require an asbestos survey before building works start on older buildings, allow only MOM-approved contractors to remove asbestos, require notice to MOM at least 7 days before removal, and set out how asbestos work and waste must be controlled.1 The National Environment Agency (NEA) then controls how the waste is collected, transported and landfilled.13

This guide explains where asbestos is found, what the Singapore ban covered and when, what the regulations require and of whom, NEA’s disposal rules, how to run the survey before strip-out, the health evidence, and a checklist for owners, MCSTs, tenants and fit-out managers. It is general information; check current requirements with MOM and NEA for your project.

Why renovation is the risk moment

The regulations define asbestos as crocidolite, actinolite, anthophyllite, amosite, tremolite, chrysotile, amphiboles, or a mixture containing any of them.1 “Work involving asbestos” covers using, handling, treating, cutting, removing, storing, disposing of or disturbing asbestos or asbestos-containing material at a workplace.1

Whether a material releases fibres depends on its condition and on what is done to it. NEA’s guidance distinguishes non-friable materials, where the fibres are bound in cement or another matrix, and states that these should not pose a health hazard if they are in good condition and not damaged.13 Renovation changes that. Breaking a cement roof sheet, cutting an old ceiling board, grinding a floor tile or stripping pipe lagging can release fibres in a way that intact materials do not. A 2011 review by NUS researchers found that occupational asbestos exposure in Singapore by then occurred mainly during demolition or renovation of older buildings.17

Where asbestos is found in Singapore buildings

NEA lists corrugated roofs, ceiling boards and partition walls as asbestos-containing materials that older buildings may still have.13 A 2011 peer-reviewed review of asbestos in Singapore records that the construction industry used asbestos widely in floor and ceiling tiles, asbestos-cement pipes and sheets, refuse chutes and fire-resistant structures, and also in pipe lagging, heat insulation, and cladding or sprayed-on materials on beams and between walls.17 The regulations’ First Schedule lists further “specified materials” that must be surveyed before work on them regardless of the building’s age.1

Material Typical location Condition and friability Notes
Ceiling boards and tiles Suspended ceilings, soffits, corridors, older offices and flats Usually non-friable when intact; broken edges and cutting release fibres Common strip-out item; NEA lists ceiling boards13
Corrugated roofing sheets Roofs of older factories, sheds, car porches, covered walkways Non-friable when intact; weathering and breakage degrade them NEA lists corrugated roofs;13 fragile to walk on, see our work-at-height guide
Partition walls and boards Internal partitions, fire-rated walls and doors Non-friable boards; fire protection boards can be more fragile Fire protection board, panel, wall and door is a specified material1
Pipe lagging and thermal insulation Plant rooms, boilers, hot-water and process pipes, vessels Often friable: the highest-risk category to disturb Thermal insulation of pipes, boilers and vessels is a specified material1
Floor tiles Older floor finishes and their adhesives Usually non-friable; grinding or breaking releases fibres Recorded by the 2011 review17
Sprayed insulation and cladding Beams, columns, between walls Friable Sprayed insulation is a specified material1
Cement pipes, refuse chutes Drainage, refuse chutes in older blocks Non-friable when intact Recorded by the 2011 review17
Gaskets, refractory linings, cable penetration insulation Plant, flanges, kilns, service penetrations Varies All are specified materials1

You cannot identify asbestos by sight. MOM states that visual inspection can rule out only non-composite materials such as glass, metal or wood; anything else must be sampled and tested where work will be carried out.7

Singapore’s ban: what was banned and when

Sources describe the ban as a series of steps rather than a single date.

Date Step Source
Late 1980s Use of asbestos materials in buildings, and import of raw asbestos, prohibited NEA13; MOM3
1989 Asbestos use in buildings banned by the authorities WSH Council14
From 1989 Phased bans; Factories (Asbestos) Regulations amended to require checks for asbestos in materials 2011 review17
1 January 1991 Cut-off used by the 2014 regulations: buildings with a CSC or TOP issued on or after this date fall outside the automatic survey duty WSH (Asbestos) Regulations, reg 31
1999 Import of products containing crocidolite, amosite and other amphiboles, and of building materials containing chrysotile, prohibited under the then Environmental Pollution Control Act 2011 review17
2001 onwards No known users of raw asbestos in Singapore 2011 review17
2002 Act renamed the Environmental Protection and Management Act; actinolite, anthophyllite and tremolite added to the prohibited list 2011 review17
30 May 2014 WSH (Asbestos) Regulations 2014 in force, revoking the Factories (Asbestos) Regulations Regulations, regs 1 and 241
1 June 2024 Amendments to the 2014 Regulations (S 434/2024), including the penalty provisions Regulations, as amended1

Two points follow for owners. First, the commonly quoted “1989” refers to use in buildings; import controls on other asbestos products came later and in stages, and the 2011 review notes that certain chrysotile-containing products could still be imported under licence at that time.17 Check the current import position with NEA if it matters to you. Second, the 1 January 1991 date in regulation 3 is the practical test: if the building, or the part you are working on, has no completion certificate or TOP issued on or after that date, a survey is required before building works start.1 MOM’s guidance puts it simply: a building built after 1 January 1991 is unlikely to contain asbestos-containing materials.3

The WSH (Asbestos) Regulations 2014

The regulations are made under the Workplace Safety and Health Act and came into operation on 30 May 2014, replacing the Factories (Asbestos) Regulations.1 They use the term approved asbestos-removal contractor: a holder of a valid certificate of approval from the Commissioner for Workplace Safety and Health.1 MOM’s website links to a search for approved contractors; a general builder’s licence or a renovation contractor’s other registrations do not substitute for approval.210

Key regulations at a glance

Regulation What it requires Duty-holder
3 Survey report from a competent person before work on a specified material, or building works on a building without a CSC or TOP issued on or after 1 Jan 1991; the Commissioner may order surveys in other cases Employer or principal
4 Surveyor takes samples (with the owner’s or occupier’s consent), has them tested by a recognised testing body, and reports without delay Competent person
5 Report and test results submitted within 3 months of appointment; kept for at least 2 years Competent person; employer or principal
6 Training before asbestos work (within the previous 12 months) and at least every 12 months Responsible person
7–11 Protective equipment, restricted access, minimising release and spread, decontamination, cleanliness18 Responsible person
12 Waste sealed in decontaminated containers or bags, labelled, and disposed of as soon as practicable Responsible person
13 Only an approved asbestos-removal contractor may remove asbestos; the occupier must ensure no one else does Contractor; occupier
14 Notify the Commissioner at least 7 days before each removal job; keep a copy on site Approved contractor
15–16 Appoint a competent person; prepare and fully implement an asbestos-removal plan of work Approved contractor; competent person
17 Where asbestos is present, ensure removal by an approved contractor is completed before demolition starts, so far as reasonably practicable Employer or principal
23 Offences and penalties All of the above

Sources: regulations as currently in force on Singapore Statutes Online.1

Survey before the works (regulations 3 to 5)

Regulation 3 places the duty on the employer of the person carrying out the work, or the principal under whose direction it is carried out. Work on a specified material, or building works on a pre-1991 building, may start only after the employer or principal receives a survey report from a competent person it has appointed.1 The survey requirement for a specified material does not apply if there is documentary proof that the material does not contain asbestos (reg 3(3)).1 MOM’s guidance summarises the rule: asbestos surveys are required for any building work, meaning demolition, alteration, extension or repair, in buildings built before 1 January 1991, and for work on the listed specified materials.4

A “competent person” is someone with sufficient experience and training who has completed the course the Commissioner requires.1 MOM states that an asbestos surveyor must have completed the WSQ Survey Asbestos and Other Fibres Risk Course.7 The surveyor must take samples with the consent of the owner or occupier, have them tested by a recognised testing body, prepare the report without delay and submit it with the test results within 3 months of appointment; the employer or principal must keep it for at least 2 years.1

Removal only by approved contractors (regulation 13)

Regulation 13(1) states that no person may undertake asbestos-removal work at a workplace unless it is an approved asbestos-removal contractor. Regulation 13(2) makes it the occupier’s duty to ensure that every asbestos-removal job at the workplace is done by an approved contractor “and no other”.1 For a building owner, MCST or tenant in control of premises, this is a personal duty, not something the main contractor can absorb by contract. Our guide on work-at-height law and occupier liability explains who counts as an occupier or principal under the WSH Act.

Workplace Safety and Health (Asbestos) Regulations 2014, regulation 13(2)

The occupier must ensure that every asbestos-removal work at the workplace is undertaken by an approved asbestos-removal contractor, “and no other”. Contravention is an offence carrying a fine of up to S$50,000, imprisonment of up to 2 years, or both, under regulation 23(1).1

Notification to MOM (regulation 14)

The approved contractor must notify the Commissioner of every asbestos-removal job at least 7 days before the work, or such shorter period as the Commissioner specifies in a particular case, in the form and manner the Commissioner requires, and keep a copy at the workplace for inspectors.1 MOM’s notification process asks for the asbestos-removal plan of work and the asbestos survey result. After the job, the contractor retrieves the notification and submits an asbestos waste disposal certificate, and submits an air monitoring report through MOM’s e-service.2

Build at least this week into the programme from the moment the survey confirms asbestos. In practice the critical path is longer: survey, laboratory results, appointment of the approved contractor, preparation of the plan of work, notification, removal, cleaning and any air monitoring, before the main works can proceed in that area.

Plan of work and control measures (regulations 6 to 12, 15 and 16)

The approved contractor must appoint a competent person, who prepares an asbestos-removal plan of work covering the nature, duration and exact location of the work, the type of asbestos, removal methods and measures to minimise release and spread, decontamination, storage and disposal of waste, monitoring, and emergency arrangements.1 The work must be carried out by or under the supervision of the competent person, and the plan fully implemented.1

The general controls apply to any work involving asbestos: training before starting and at least every 12 months; suitable protective equipment including respiratory protection; access restricted to people doing the work and wearing protective equipment; reasonably practicable measures to minimise airborne release, such as wet methods, local exhaust ventilation or containment; preventing spread beyond the work area, including enclosing it; decontamination facilities; and cleaning of the area.118 The WSH Council notes that employers must also arrange pre-placement and periodic medical examinations for workers exposed to asbestos, under the Workplace Safety and Health (Medical Examinations) Regulations 2011.14

Demolition (regulation 17)

Where a building is to be demolished and a survey report states that asbestos is fixed or installed, or the owner tells the employer or principal that it is, the employer or principal must ensure, so far as reasonably practicable, that removal by an approved contractor is completed before demolition starts.1 MOM summarises this duty as ensuring asbestos-containing materials are removed before buildings are demolished.8 For the wider demolition process, see our guide on demolition and strip-out safety.

Penalties (regulation 23)

Breach Maximum penalty
Core duties: survey (regs 3, 4), PPE (7(1)), access, release and spread, decontamination, cleanliness, waste (12(1), (5)), removal by approved contractor (13), competent person (15), plan of work (16(1)), demolition (17) Fine of S$50,000, imprisonment of 2 years, or both
Failure to notify the Commissioner (reg 14(1)) Fine of S$20,000, imprisonment of 2 years, or both; repeat offender S$50,000, 2 years, or both
Training (reg 6(1)) S$10,000; repeat offender S$20,000
Plan not made available to inspector (reg 16(3)) S$10,000
Survey report submission (reg 5(1)) S$2,000; repeat offender S$5,000

Source: regulation 23 as amended with effect from 1 June 2024.1 A repeat offender is someone convicted of a listed corresponding offence within the previous 5 years.1

NEA rules on asbestos waste disposal

Asbestos waste is a toxic industrial waste in Singapore; the 2011 review notes that asbestos is controlled under the Environmental Public Health (Toxic Industrial Waste) Regulations.17 NEA’s guidance on asbestos waste sets out the practical requirements.13

From removal to Semakau

  1. Seal it at source. Asbestos is placed into a sealed container or bag, together with disposable items from the work area such as plastic sheets, tapes, disposable clothing and vacuum filter bags. The outside of the container must be kept free of contamination.131
  2. Label it. Containers carry prominent labels showing the contents and warning of the hazard of asbestos exposure; NEA gives “Asbestos - Do not inhale dust” as an example.13
  3. Engage a licensed collector. The removal contractor engages a licensed toxic industrial waste collector (TIWC) capable of handling asbestos. Approved collectors need written permission from NEA to dispose of asbestos at Semakau Landfill.13
  4. Transport with care. Containers are loaded carefully to avoid damage, in vehicles with enclosed compartments or canvas covers. Compactors must not be used because they can rupture the containers.13
  5. Barge directly to Semakau. Asbestos waste containers must be barged directly to Semakau Landfill.13
  6. Close the loop with MOM. The approved removal contractor submits the asbestos waste disposal certificate to MOM after the job.2

Never let asbestos debris go into general construction waste, a renovation skip or a refuse chute. MOM directs members of the public who see illegal disposal of asbestos waste to report it to NEA, and unsafe asbestos-removal work can be reported to MOM with the site address, contractor’s name and photographs.1112

The asbestos survey before strip-out

The survey is the step owners can control most directly, and the one that most affects cost and programme. A survey done before tender lets contractors price the removal and plan around it; a survey triggered by a discovery mid-strip-out stops the job.

Which survey you need

MOM distinguishes the level of survey by purpose.7

Purpose What the surveyor does Is visual inspection enough?
Management survey, no works planned Identify suspected asbestos-containing materials and assess their condition Yes
Management survey, works planned Sample suspected materials where work will be carried out and send for laboratory testing No
Refurbishment or demolition Sample suspected materials throughout the building and send for laboratory testing No

For renovation, MOM states that the survey scope must include all areas undergoing renovation, and that areas not affected may be excluded; a survey of the whole building is not needed if only part is being worked on.56 For a strip-out or demolition, the survey must be thorough enough to find materials hidden above ceilings, inside risers, behind panels and under later finishes. MOM refers surveyors to Annex A of the WSH Guidelines on Management and Removal of Asbestos for a list of suspected materials.7

Running an asbestos survey before strip-out

  1. Establish the date. Find the CSC or TOP date for the building or the relevant part. If none was issued on or after 1 January 1991, regulation 3 applies to building works.1
  2. Define the scope. Mark up the areas and elements to be disturbed, including ceiling voids, risers, plant rooms and roofs.
  3. Appoint a competent surveyor. Confirm the surveyor has completed the WSQ Survey Asbestos and Other Fibres Risk Course.7 The appointment is made by the employer or principal; owners usually commission it so that the result is available at tender.
  4. Give consent and access. The surveyor needs the owner’s or occupier’s consent to take samples.1 Arrange access to concealed spaces and make good after sampling.
  5. Laboratory testing. Samples go to a recognised testing body.1
  6. Receive and keep the report. The report and results must be submitted within 3 months of appointment and kept for at least 2 years.1 Issue it to tenderers.
  7. Plan the removal. If asbestos is confirmed in areas to be disturbed, engage an approved removal contractor, allow for the 7-day notification, and sequence the main works around removal and clearance.1

Asbestos you are not removing

Not every asbestos material has to come out. Where asbestos-containing materials will remain, MOM advises building owners to put in place an asbestos management programme, including awareness training for people working near them, and to take corrective action immediately if any material is damaged; any removal or repair must be by an approved contractor.9 Record their locations on drawings and in the building’s maintenance records so that future contractors, electricians and cleaners do not disturb them unknowingly. This is part of running works in occupied premises safely.

Health effects

The World Health Organization’s fact sheet, updated in August 2026, states that all forms of asbestos are carcinogenic to humans.15 It lists mesothelioma and cancers of the lung, larynx and ovary, and chronic respiratory disease including asbestosis, as consequences of exposure, and recommends stopping all use of asbestos and protecting workers during maintenance and removal.15

200,000+ deaths a year worldwide estimated from occupational asbestos exposure, over 70% of work-related cancer deaths (WHO, 2016 estimates)15

Disease What it is Exposure pattern Typical latency
Malignant mesothelioma Cancer of the lining of the lungs or abdomen Low intermittent or indirect exposure can be sufficient; most cases are associated with asbestos 15 to 50 years16
Lung cancer Cancer of the lung; risk increased with smoking High cumulative exposure 10 years or more16
Asbestosis Scarring (fibrosis) of the lung High and prolonged exposure16 Long latency; no single figure given in the guidelines16
Cancer of the larynx and ovary Listed by WHO as caused by asbestos15 Not specified by WHO Not specified

The WSH Council’s guidelines on occupational diseases list demolition and renovation of buildings containing asbestos among the exposures for both asbestos-related lung cancer and mesothelioma.16 The same guidelines list asbestosis and malignant mesothelioma among the common occupational lung diseases reported in Singapore.16 Because latency runs into decades, Singapore is still seeing disease from past exposure: the 2011 review records 49 mesothelioma deaths between 1990 and 2006 and notes that the mesothelioma mortality rate had doubled since 2000.17

The practical point for owners is that the people at risk from a badly managed strip-out include not only the workers but anyone breathing the same air, which in a live building can be occupants, cleaners and neighbouring tenants.

Composite scenario: the ceiling that stopped the strip-out

A tenant took a floor in a 1980s office building and appointed a fit-out contractor to strip the existing ceilings and partitions over a weekend. No asbestos survey had been done; the landlord’s handover pack was silent on it. On the first night, workers broke out ceiling boards and swept the debris into the general waste bins. A building manager recognised the board type and stopped the work. A competent surveyor’s sampling and laboratory results confirmed asbestos in the ceiling boards and in debris on the carpet and in the ceiling void. The floor was sealed, an approved removal contractor was engaged and notified MOM, and the area was decontaminated and cleaned before work could restart. The tenant lost three weeks of programme, paid for removal and cleaning of debris that had been spread, and faced questions about whether, as occupier and principal, it had met its duties under regulations 3 and 13. A survey before tender would have cost a fraction of the delay. This is a composite scenario, not a specific case; the sequence of duties described follows the regulations.1

The owner’s role in practice

Most asbestos problems on renovation jobs are failures of sequence, not failures of technique. The owner’s influence lies in four decisions.

  1. Know the building’s date. The 1 January 1991 cut-off in regulation 3 tells you whether a survey is a legal precondition for building works.1
  2. Commission the survey before tender. Put the report in the tender documents so that removal is priced and programmed, not discovered.
  3. Separate the contracts or the scope clearly. Asbestos removal is either a separate contract with an approved contractor or a clearly defined subcontract to one. Make the main contractor’s scope start after clearance in affected areas.
  4. Control what happens on discovery. Write a stop-work-and-report procedure into the contract for suspected asbestos found during works, with a clear route to survey and approved removal.

For strata buildings, an MCST or managing agent is often the occupier of common property, and a tenant is often the occupier of its own premises; each should ask who has control before works start. Asbestos removal in a strip-out is one of several consents and safety steps listed in our guide to A&A works approvals, and opening up walls and slabs is covered in hacking walls and structural elements. Use the approval navigator to see what else your works may need.

Owner's asbestos checklist for renovation and strip-out

  • Find the CSC or TOP date for the building or the part being worked on; if none was issued on or after 1 January 1991, a survey is required before building works.
  • Appoint, or require the person directing the works to appoint, a surveyor who has completed the WSQ Survey Asbestos and Other Fibres Risk Course.
  • Make sure the survey samples every material to be disturbed, including ceiling voids, risers, roofs, plant rooms and floor finishes, with laboratory testing.
  • Issue the survey report to all tenderers and keep it for at least 2 years.
  • If asbestos is present, engage an MOM-approved asbestos-removal contractor, and check its approval on MOM’s register.
  • Allow at least 7 days for MOM notification, plus time for the plan of work, removal, cleaning and any monitoring.
  • Ask to see the notification, the plan of work, and, after the job, the waste disposal certificate.
  • Confirm the waste goes to a licensed toxic industrial waste collector for disposal at Semakau Landfill, not into general skips.
  • Keep occupants and other trades out of the asbestos work area; plan ventilation and access in occupied buildings.
  • Write a stop-work-and-report procedure for suspected asbestos found during the works into every contract.
  • Record any asbestos left in place, put it on drawings, and tell future contractors.

How RRD approaches this

On strip-out, A&A and reinstatement jobs in older buildings, RRD’s site survey records the building’s age and any suspect ceiling, partition, roof or insulation materials, and the itemised quotation lists asbestos survey and removal as cost-risk items before signing. RRD does not itself remove asbestos; where a survey confirms it, removal is carried out by an MOM-approved asbestos-removal contractor before RRD’s works proceed in the affected areas. Works start with a safety briefing and are supervised on site through to joint inspection and handover.

Summary

Asbestos in Singapore is a renovation problem, not a building-in-use problem: intact materials are generally low risk, but disturbing them is regulated tightly. For buildings without a completion certificate or TOP issued on or after 1 January 1991, a competent person’s survey must come before building works. Only an MOM-approved contractor may remove asbestos, with at least 7 days’ notice to MOM, a plan of work and full controls, and the occupier must make sure no one else does it. NEA requires the waste to be sealed, labelled, collected by a licensed toxic industrial waste collector and barged to Semakau. Owners who survey before tender, programme the removal and keep records avoid both the health risk and the stop-work. Definitions of the terms used here are in the glossary.

Questions people ask

Does my building contain asbestos?

It may if it is old enough. MOM says Singapore banned asbestos in building materials in the late 1980s, and that a building built after 1 January 1991 is unlikely to contain asbestos-containing materials. Older buildings may still have it in corrugated roof sheets, ceiling boards, partition walls, floor tiles, pipe lagging and fire protection boards. You cannot tell by looking: only a survey by a competent asbestos surveyor, with samples tested in a laboratory, confirms whether a material contains asbestos.

Do I need an asbestos survey before renovating?

Yes, if the building is old enough. Regulation 3 of the Workplace Safety and Health (Asbestos) Regulations 2014 requires a survey report from a competent person before building works start on a building, or part of one, that has no certificate of statutory completion or temporary occupation permit issued on or after 1 January 1991. MOM's FAQ confirms this applies to renovating a house. The survey must cover all areas being renovated; unaffected areas may be excluded.

Can my renovation contractor remove asbestos ceiling boards?

Only if it is an approved asbestos-removal contractor. Regulation 13 says no person may undertake asbestos-removal work unless approved by MOM, and makes the occupier of the workplace responsible for ensuring that only an approved contractor does it. A general renovation contractor that is not approved must not break, cut or remove asbestos materials. It can carry out the rest of the works after the approved contractor has finished removal in the affected areas.

How much notice does MOM need before asbestos removal?

The approved asbestos-removal contractor must notify MOM of every asbestos-removal job at least 7 days before the work starts, unless the Commissioner allows a shorter period in a particular case. MOM's online notification asks for the plan of work for removal and the asbestos survey result. After the job, the contractor updates the notification with an asbestos waste disposal certificate and submits an air monitoring report.

Is asbestos dangerous if I leave it alone?

NEA's guidance is that non-friable asbestos materials, such as cement sheets and boards, should not pose a health hazard if they are in good condition and not damaged. The danger comes when they are broken, drilled, cut, sanded or demolished, releasing fibres into the air. MOM advises building owners to survey, manage asbestos-containing materials that remain, take corrective action immediately if they are damaged, and use an approved removal contractor for any removal or repair.

What happens to the asbestos waste?

Under the regulations, asbestos waste must be sealed in containers or bags with decontaminated exteriors, prominently labelled with the contents and an asbestos hazard warning, and disposed of as soon as practicable. NEA requires the removal contractor to engage a licensed toxic industrial waste collector able to handle asbestos, which needs written NEA permission to dispose at Semakau Landfill. Containers must be barged directly to Semakau, and compactors must not be used.

Who is responsible: the owner or the contractor?

Both, in different roles. The employer or principal directing the works must obtain the survey before work starts and ensure asbestos is removed before demolition. The occupier must ensure only an approved contractor removes asbestos. The approved contractor must notify MOM, appoint a competent person, prepare and follow a plan of work, and control, decontaminate and dispose of the waste. An owner who commissions works can be the principal or the occupier, so the duties cannot simply be passed to the contractor.

What are the health risks of asbestos exposure?

The World Health Organization classifies all forms of asbestos as carcinogenic to humans. Inhaled fibres can cause mesothelioma, cancers of the lung, larynx and ovary, and asbestosis, a scarring of the lungs. WHO estimates more than 200,000 deaths a year worldwide from occupational exposure. Singapore's WSH Council guidelines give a latency of 15 to 50 years for mesothelioma and note that low, intermittent exposure can be enough, which is why prevention during renovation matters.

What should I do if suspected asbestos is found halfway through the works?

Stop work in the affected area, keep people out, and do not sweep or vacuum debris with ordinary equipment. Ask the person directing the works to arrange a survey by a competent asbestos surveyor, with samples sent for laboratory testing. If asbestos is confirmed, engage an MOM-approved asbestos-removal contractor, which must notify MOM at least 7 days before removal. Unsafe asbestos removal can be reported to MOM, and illegal dumping of asbestos waste to NEA.

Sources

18 sources. Official sources are marked dark. Links were checked when this guide was last updated.

  1. sso.agc.gov.sgWorkplace Safety and Health (Asbestos) Regulations 2014 (S 337/2014), regs 1–6, 9, 12–17, 23, 24 and First and Second Schedules, as amended by S 434/2024 with effect from 1 June 2024 (current version as at 9 November 2026). Singapore Statutes Online. https://sso.agc.gov.sg/SL/WSHA2006-S337-2014 (accessed Nov 2026) ↩↩↩↩↩↩↩↩↩↩↩↩↩↩↩↩↩↩↩↩↩↩↩↩↩↩↩↩↩↩↩↩↩↩↩↩
  2. mom.gov.sgMinistry of Manpower — FAQ: “If I suspect that I have asbestos materials in my house or workplace, what should I do?” https://www.mom.gov.sg/faq/notify-for-asbestos-work/if-i-suspect-that-i-have-asbestos-materials-in-my-house-or-workplace-what-should-i-do (accessed Nov 2026) ↩↩
  3. mom.gov.sgMinistry of Manpower — FAQ: “When do I need to conduct an asbestos survey?” https://www.mom.gov.sg/faq/notify-for-asbestos-work/when-do-i-need-to-conduct-an-asbestos-survey (accessed Nov 2026) ↩
  4. mom.gov.sgMinistry of Manpower — FAQ: “Do I need to carry out asbestos survey if I am renovating my house?” https://www.mom.gov.sg/faq/notify-for-asbestos-work/do-i-need-to-carry-out-asbestos-survey-if-i-am-renovating-my-house (accessed Nov 2026) ↩
  5. mom.gov.sgMinistry of Manpower — FAQ: “Is an asbestos survey needed for the entire building if only part of it is being worked on?” https://www.mom.gov.sg/faq/notify-for-asbestos-work/is-an-asbestos-survey-needed-for-the-entire-building-if-only-part-of-it-is-being-worked-on (accessed Nov 2026) ↩
  6. mom.gov.sgMinistry of Manpower — FAQ: “Is a visual inspection enough for an asbestos survey?” https://www.mom.gov.sg/faq/notify-for-asbestos-work/is-a-visual-inspection-enough-for-an-asbestos-survey (accessed Nov 2026) ↩↩↩↩↩
  7. mom.gov.sgMinistry of Manpower — FAQ: “What are the duties of an employer, principal and occupier in asbestos-related work?” https://www.mom.gov.sg/faq/notify-for-asbestos-work/what-are-the-duties-of-employer-principal-or-occupier-in-asbestos-related-work (accessed Nov 2026) ↩
  8. mom.gov.sgMinistry of Manpower — FAQ: “What should I do if there are asbestos-containing materials in my building?” https://www.mom.gov.sg/faq/notify-for-asbestos-work/what-should-i-do-if-there-are-asbestos-containing-materials-in-my-building (accessed Nov 2026) ↩
  9. mom.gov.sgMinistry of Manpower — “Asbestos removal contractor” (last updated 14 January 2026). https://www.mom.gov.sg/workplace-safety-and-health/wsh-service-providers/asbestos-removal-contractor (accessed Nov 2026) ↩
  10. mom.gov.sgMinistry of Manpower — FAQ: “How can I report unsafe asbestos-removal work?” https://www.mom.gov.sg/faq/notify-for-asbestos-work/how-can-i-report-unsafe-asbestos-removal-work (accessed Nov 2026) ↩
  11. mom.gov.sgMinistry of Manpower — FAQ: “How do I report the illegal disposal of asbestos waste?” https://www.mom.gov.sg/faq/notify-for-asbestos-work/how-do-i-report-the-illegal-disposal-of-asbestos-waste (accessed Nov 2026) ↩
  12. nea.gov.sgNational Environment Agency — “Asbestos Waste” (Toxic Waste Control; last updated 25 August 2026). https://www.nea.gov.sg/our-services/pollution-control/toxic-industrial-waste/toxic-waste-control/asbestos-waste (accessed Nov 2026) ↩↩↩↩↩↩↩↩↩↩↩↩
  13. tal.sgWorkplace Safety and Health Council — “About Asbestos”. https://www.tal.sg/wshc/topics/asbestos/about-asbestos (accessed Nov 2026) ↩↩
  14. who.intWorld Health Organization — “Asbestos: elimination of asbestos-related diseases” (fact sheet, updated 11 August 2026). https://www.who.int/en/news-room/fact-sheets/detail/asbestos-elimination-of-asbestos-related-diseases (accessed Nov 2026) ↩↩↩↩
  15. tal.sgWorkplace Safety and Health Council — “WSH Guidelines on Diagnosis and Management of Occupational Diseases” (PDF, 2025). https://www.tal.sg/wshc/-/media/tal/wshc/resources/publications/wsh-guidelines/files/wsh-guidelines-on-diagnosis-and-management-of-occupational-diseases.pdf (accessed Nov 2026) ↩↩↩↩↩↩
  16. doi.orgLim JW, Koh D, Khim JSG, Le GV, Takahashi K — “Preventive Measures to Eliminate Asbestos-Related Diseases in Singapore”, Safety and Health at Work 2011;2:201–209. https://doi.org/10.5491/SHAW.2011.2.3.201 (accessed Nov 2026) ↩↩↩↩↩↩↩↩↩↩↩
  17. littdb.sfo2.cdn.digitaloceanspaces.comWorkplace Safety and Health (Asbestos) Regulations 2014, regs 7, 8, 10 and 11 (text as archived by Legal Wires from Singapore Statutes Online, showing amendments by S 434/2024). https://littdb.sfo2.cdn.digitaloceanspaces.com/litt/SG/SSOStatutes/subsidiary_legislation/WSHA2006-S337-2014.html (accessed Nov 2026) ↩↩
Cite or link to this guide

Use this guide in a report, a tender or a by-law briefing. Please link to the page so readers get the current version.

RRD Engr & Constr. (2026). Asbestos in Renovation and Strip-Out in Singapore: Surveys, Approved Removal and Owner Duties. RRD Field Guide. Updated 9 November 2026. https://rrd.sg/guides/asbestos-in-renovation-singapore/
Report a correction