Who can replace windows found defective during the PFI?

Answer

BCA requires replacement windows to be installed by an approved window contractor, registered under workhead RW01, or by a GB1 or GB2 licensed builder, using a trained window installer. Contractors submit a certificate of completion within 14 days of finishing the works. For casement windows, BCA asks that aluminium rivets be replaced with type 304 stainless steel rivets.

From the RRD Field Guide, checked against the sources cited in Façade Defect Rectification in Singapore: What Happens After the PFI Report. General information, not advice for your project.

The fuller picture

After BCA accepts a PFI report, the owner must carry out the Competent Person's recommended repairs within the period BCA specifies. Make unsafe areas safe first, then repair by defect type: sealant, cladding, glazing, spalling concrete, corroded fixings, hollow tiles or windows. Structural repairs need plan approval, a permit and PE supervision; completion is certified with photos.

Read the full guide

More questions on this topic