A&A Works to Conserved Shophouses in Singapore: URA's 3R Rules, Permits and Fire Safety

Updated 9 November 202621 min read15 sources, 15 officialBy RRD Engr & Constr, editorial standards
The short answer

Any work to a conserved shophouse needs URA Conservation Permission before it starts, even repainting. URA's rule is maximum Retention, sensitive Restoration and careful Repair: the roof, party walls, front façade, five-foot way and (in historic districts) timber floors must be kept. Rear extensions and roof mezzanines are allowed only within set limits, and Fire Code clause 9.9 governs timber floors and stairs.

A conserved shophouse is one of the few buildings in Singapore where the law cares about the original material as much as the finished result. In an ordinary A&A project, the authorities ask whether the new work is safe and permitted. In a conserved building, the Urban Redevelopment Authority (URA) also asks what you are taking away. A timber floor replaced with concrete, a rear wall rebuilt in new brick, a granite five-foot-way kerb lifted and discarded: each can be a breach even if the replacement is structurally better.

The stakes were made concrete in April 2026, when a court fined an individual S$250,000 and a property-owning company S$150,000 over unauthorised demolition at a conserved shophouse at 32 Desker Road, and ordered the building to be reinstated.7 The maximum penalty where unauthorised works in a conservation area include demolition is S$500,000, imprisonment of up to 12 months, or both.5

This guide sets out URA’s conservation principles, which elements must be kept, the additions URA permits (rear extensions, roof mezzanines, lifts, roof structures), the conservation permission process, the structural and fire-safety issues peculiar to old timber-and-brick buildings, and change of use. It reflects URA’s guidelines and the law as at 9 November 2026. It is written for owners, tenants and fit-out managers of conserved shophouses; for approvals in ordinary buildings, start with the master guide to A&A approvals.

S$400,000 combined fines imposed in April 2026 over unauthorised works at 32 Desker Road, with reinstatement ordered7

The principle: maximum Retention, sensitive Restoration, careful Repair

URA describes the “3R” principle as fundamental to all conserved buildings, whatever their size or complexity: maximum Retention, sensitive Restoration and careful Repair.1 Its explanation draws out several working rules:1

  • all original structural and architectural elements should be retained and restored;
  • replacement is a last resort, and where it is necessary, for example because an element contains asbestos, the owner needs URA’s clearance for a one-to-one replacement;
  • wholesale rebuilding is regarded as contrary to accepted international conservation practice;
  • in adaptive reuse, the existing structure should be kept and strengthened or repaired, as unobtrusively as possible and with original methods and materials where feasible;
  • the building should be researched and recorded before work starts, and each stage documented.

In practice, the 3R principle reverses the usual contractor instinct. The default is to repair the existing timber joist, not to replace it; to re-lay the original clay tiles, not to substitute new ones; to restore the original window, not to reproduce it. Any departure needs a reason the QP can put in writing to URA.

URA reissued its Do-It-Right Guide for conserved shophouses and terraces on 2 June 2026, with improved visual examples of allowable works, submission requirements and long-term maintenance; the circular noted unauthorised alterations causing irreversible loss of original fabric, and incompatible materials accelerating deterioration, as recurring problems.11

Historic districts, secondary settlements and why the category matters

URA publishes separate planning parameters and restoration guidelines for different kinds of conservation area. For shophouses, the two that matter most are:

  • Historic Districts, where URA applies the strictest form of conservation. URA’s press release on 32 Desker Road described Little India as one of four historic districts.7 The Historic Districts guidelines refer to the core areas of Chinatown, Kampong Glam and Little India.2
  • Secondary Settlements, such as Balestier, Joo Chiat, Geylang, Jalan Besar, Tanjong Katong and Tiong Bahru, where owners may conserve the main building and add a rear extension.3

The differences are material. Comparing the two sets of guidelines:

Element Historic Districts2 Secondary Settlements3
Roof Retain original profile, pitch, height, party wall and eaves; small V-profile, unglazed natural clay tiles Retain original profile, pitch, height, party wall and eaves
Timber floors Retention required (“important that the timber floor should be retained”) Retention encouraged
Party wall First 3 m behind the 1st-storey shopfront retained; openings less than 50% of wall length First 3 m behind the shopfront retained
Front façade Retain and restore fanlights, windows, doors, vents, balconies; balconies stay open Residential fronts retained and restored
Five-foot way Granite slab borders retained; ramp for level differences up to 175 mm, no steeper than 1:10 Granite slab borders retained
New rear extension Not provided for as such; new rear-court roof up to 2nd-storey floor level; roof garden on RC flat roof over rear court Allowed, with heights set by area
New basement Not allowed Not allowed in the conserved building
Original building height Retained Retained (main building)

Your QP should confirm the specific guidelines for the property on URA’s Conservation Portal; some streets also have site-specific restoration guidelines.

What must be kept

Roof

The main roof’s original profile, pitch, height, party wall and eaves projection are to be retained and restored.23 In historic districts, the tiles are to be small, V-profile, unglazed and natural-coloured clay.2 Dormer windows are not allowed; jackroofs and skylights are allowed only within URA’s positioning, setback and size limits (skylights on pitched roofs up to 30% of the slope, protruding no more than 150 mm).2 Where the roof needs strengthening with steel or reinforced concrete (RC) beams, the design must minimise visual impact on the traditional timber roof structure.2

Party walls

Party walls in shophouses are the principal load-bearing walls. The first 3 m of the load-bearing party wall perpendicular to the first-storey shopfront must be retained, preserving the fine-grained rhythm of the street.23 In historic districts, new openings in a party wall are allowed if their total width is less than 50% of the wall’s length within the building envelope; in RC-framed buildings these controls do not apply.2 Timber floor supports must abut the party walls.2 Because conserved shophouses share party walls, URA and BCA’s joint circular of March 2023 warns that they are prone to damage from vibration and ground movement caused by works on or next to them.10

Timber floors and staircases

In historic districts, URA states it is important that the timber floor be retained; original RC floors can stay as they are.2 Where floors are timber, any new staircase must be lightweight (timber or metal), not RC, and must not abut window, door or vent openings; the existing staircase may be retained or relocated with its original railings reinstated.2 In secondary settlements, existing timber floors are encouraged to be retained and restored.3 Voids of up to 25% of each floor are allowed, and the first-storey floor may be lowered by up to 600 mm for landscaping, ponds or lift pits.2

Front façade and five-foot way

Fanlights, windows, doors, vents and decorative features on the front façade are to be retained and restored, and balconies kept open.2 The five-foot way’s original granite slab borders must be retained and restored, and the covered walkway’s character protected.23 Changing five-foot-way flooring is a Category 3 work that still needs permission.4

Airwell, rear façade and rear service block

The airwell’s original size and location must be kept. It may be covered by a new roof that sits lower than the main roof eave and is lightweight and transparent or translucent; no lift, floor or other structure may be added in it.2 Original rear windows may be retained and restored or changed to French windows matching the front, and existing openings in the rear service block may be retained and restored.2 The rear is where owners most often assume they have a free hand. The 32 Desker Road case shows otherwise: URA described the rear façade, with its timber casement windows and green glazed ceramic vents, and the entire rear service block as fundamental elements that should have been fully retained.7

What can be added

URA’s guidelines allow a defined set of additions. All need conservation permission, and most are Category 1 or 2 works.4

Rear extensions (secondary settlements)

In secondary settlements, an owner may conserve the main building and add a new rear extension. URA sets heights area by area, for example up to 6 storeys in Balestier and Jalan Besar, 5 in Beach Road and Joo Chiat, 4 in Tanjong Katong (5 for specified units) and Tiong Bahru shophouses, and 10 in River Valley.3 Any part of the extension that rises above the main pitched roof eaves must be set back at least 600 mm clear of the conserved building, the design and materials of the extension’s roof and façade may vary, and any required car parking goes within the extension.3 A new rear extension is a Category 1 work.4

Roof mezzanines (attics)

New roof mezzanine floors are allowed within the building envelope, subject to setbacks from the inner face of the front façade: at least 1,500 mm if the floor is not lower than the top of the uppermost window or fanlight, or at least 2,500 mm if it is lower. The floor may not abut any window, door, transom or fanlight; it is built with timber joists and boards, with RC allowed only if the original uppermost floor was RC; and dormers are not allowed.23 Fire Code limits on attic size apply on top (see below).

Roof structures, lifts and other items

In historic districts, single-storey structures on flat roofs may be up to 3,600 mm high, cover no more than 35% of the flat roof area and be set back at least 3 m from front and side street elevations; roof-top plant must be screened on all sides.2 Lifts are allowed within the building envelope, but not in the airwell or rear court; a shaft protruding above the roof must sit on the rear slope or a secondary roof and below the main ridge.2 Canopies over openings may project up to 450 mm.2 New basements are not allowed.23

The conservation permission process

Section 12(2) of the Planning Act makes it an offence to carry out, or permit the carrying out of, any works within a conservation area without conservation permission.5 The ordinary fine is up to S$200,000, plus up to S$10,000 a day for a continuing offence after conviction; where the works include demolition of a building or part of one, the maximum rises to S$500,000, imprisonment of up to 12 months, or both.5

URA sorts works into three categories:4

Category 1 Category 2 Category 3
Effect Affects key elements significantly Affects key elements to a lesser extent Minimal, localised, or repair and maintenance
Examples Roof profile, pitch or height; jackroofs or skylights; altering original windows, doors or decorative features; changing an entire upper floor; voids or roof mezzanines; new rear extension; structural strengthening Replacing roof tiles; pergola with non-load-bearing cover; adding or removing a window; airwell cover; rear-court roof; sealing or adding a party wall opening; internal staircase or lift One-for-one repair or replacement of roof tiles, rafters, doors, windows, transoms or vents; security grilles; five-foot-way flooring; one-for-one replacement of timber floor boards and joists; painting; business signs; air-conditioning units; solar panels
Who submits QP who is a Registered Architect Registered Architect or Professional Engineer Owner or contractor; no QP
Route and time CORENET; decision within 20 working days CORENET; decision within 20 working days URA e-service; about two weeks; free

For Category 1 and 2 works, the sequence is: the architect consults the technical agencies; submits to URA with a measured survey endorsed by a registered surveyor, a PE’s structural report, calculation plans, photographs, and a detailed structural investigation report, method statement and protection plan endorsed by the engineer; URA issues conservation permission; the architect then obtains building plan approval from BCA and BCA’s permit; URA may inspect during the works; and on completion URA carries out a TOP/CSC inspection, granting clearance only if the works follow the approved plans.4 For Category 3, the owner or contractor submits photographs or drawings with the owner’s authorisation, waits for permission, and submits completion photographs for URA’s endorsement; no work may start before permission is issued.4 If unsure whether permission is needed, URA asks owners to consult it before starting.4

URA also notes the financial side. Development charge applies to new extensions and new floor areas such as roof mezzanines, but can be waived where restoration follows the approved plans and is completed within two years of the conservation permission; a car park deficiency charge can be waived if the guidelines are fully complied with.4 The Land Betterment Charge, administered by the Singapore Land Authority, replaced development charge and related levies from 1 August 2022.4

A realistic sequence for a Category 1 shophouse project

  1. Due diligence before purchase or lease. Confirm the conservation area, the applicable guidelines and allowable uses on URA’s Conservation Portal and URA SPACE; ask for previous approvals and as-built records.
  2. Appoint the team. Appoint a Registered Architect as QP and a PE for the structural investigation; commission a measured survey by a registered surveyor.
  3. Investigate and record. Document the existing fabric; assess timber floors, roof timbers, party walls and termite damage; test for asbestos before any stripping.
  4. Design to the guidelines. Retain first, restore second, replace only with justification; check the Fire Code clause 9.9 consequences of any attic, amalgamation or change of use at the same time.
  5. Conservation permission. Submit the Category 1 application with the structural report, method statement and protection plan; allow for URA’s 20-working-day decision and any queries.
  6. BCA and SCDF. Obtain building plan and, where needed, structural plan approval and the permit; obtain SCDF plan approval for the fire safety upgrading.
  7. Protect the neighbours. Monitor shared party walls during the works and keep vibration-generating methods away from them.
  8. Build under supervision. The QP supervises; any change on site goes back through the QP and, if it affects key elements, through URA.
  9. Completion. URA’s TOP/CSC inspection, SCDF’s fire safety certificate process, and completion within the timeframe needed for any charge waiver.

32 Desker Road: unauthorised works to a conserved shophouse (sourced public event)

URA reported that 32 Desker Road, a shophouse of about 1913 to 1914 in the Little India Conservation Area, retained a rare original first-storey façade with a double-leafed timber door and timber-framed casement windows with vertical iron bars. After the property was bought in October 2022 through a company, works were carried out to convert it into a co-living development without URA approval. URA inspected on 6 January 2023 after receiving feedback and issued a stop notice.7 In July 2025, URA charged the individual with carrying out unauthorised works, and the owner company with permitting them and with failing to appoint an architect to supervise the works; the works included demolition of the first-storey residential front, the rear façade and the service block, and removal of the original internal timber staircase.6 On 22 April 2026, URA announced fines of S$250,000 for the individual and S$150,000 for the company, which must also reinstate and restore the building at its own cost.7 URA said the original heritage fabric is irrevocably lost and the building can only be rebuilt with new materials, and that this was the first prosecution for unauthorised works to a conserved building since the Planning Act was amended in 2017.7 The cost chain is visible in the release itself: S$400,000 in combined fines, plus reinstatement and restoration of the demolished elements at the owner company’s own cost, on top of whatever was spent on the unauthorised works.

URA media release, 22 April 2026

After the 32 Desker Road sentencing, URA stated that owners of conserved buildings bear responsibility for ensuring all works comply with the regulations, and that enforcement action will be taken against all parties involved, including independent builders engaged for unauthorised works.7 It reminded owners to obtain conservation permission, appoint a Qualified Person and obtain approvals before work starts on site.7

Structural issues in old shophouses

Why old shophouses need a different structural approach

Pre-war shophouses typically combine load-bearing brick party walls, timber floors on timber joists, timber roof structures and shallow foundations. URA and BCA’s joint circular of 1 March 2023 asks QPs working on or next to conserved buildings to account for that vulnerability and to propose structural and foundation systems that meet code requirements for the building’s full design life.10 It notes that works to façades, roofs, party walls, floors and rear extensions can cause differential settlement, and that BCA structural plan approval is required where structural modifications are involved, alongside conservation permission.10 It also reminds owners that conserved buildings should be regularly maintained, with a PE engaged to address the root cause of defects such as spalling, cracks, termite damage and water leakage.10 Our guide to cracks in walls and ceilings helps distinguish cosmetic from structural cracking.

The approvals

Structural plans must be submitted by a PE in the civil or structural discipline.13 Under the Fourth Schedule of the Building Control Regulations, building works for shophouses not exceeding 3 storeys do not need an Accredited Checker’s certificate, but an attic or basement floor of more than 100 m² counts as a storey for that purpose.9 Building works without approved plans or a permit carry a fine of up to S$200,000, two years’ imprisonment, or both, for anyone who carries out, permits or authorises them.14

Practical points

  • Repair before replace. Timber joists with localised rot or termite damage can often be spliced, sistered or strengthened; URA treats one-for-one replacement of floor boards and joists as Category 3, but anything beyond that is a design decision with URA.4
  • New loads go to new structure. Lifts, roof-top plant and mezzanines should be supported independently where the existing walls cannot take them, with the visual impact minimised.2
  • Protect the neighbour’s wall. Party walls are shared. Avoid percussive hacking near them, and agree monitoring before demolition at the rear. The circular’s warning on vibration and ground movement applies to both sides of the wall.10 Our guide to hacking walls and structural elements covers safe methods.

Independent engineer's note

On a conserved shophouse, the PE’s structural investigation report and method statement are part of the URA submission itself.4 That report decides how much original fabric can be kept, so it should be written for the owner, not for the convenience of the builder’s programme. An owner-appointed PE can recommend repair of a timber floor where a contractor’s pricing might favour replacement. RRD’s usual independent engineering partner is CVC Engineers, a Singapore PE consultancy covering civil and structural design, PE endorsement and submissions, and regularisation of unauthorised works; owners are free to appoint any PE. More on this model on our independent engineer page.

Fire safety: Fire Code clause 9.9

The Fire Code 2023 has a dedicated clause, 9.9.1, for buildings with timber floors or staircases that are designated for conservation or were built before 1969.8 Its key requirements are:

Situation Requirement (Fire Code 2023, cl. 9.9.1)8
Scope of upgrading Applies to the whole building; partial upgrading is not allowed
Change of use Change of use to public accommodation (examples given: boarding houses, hotels, workers’ quarters) is not permitted
2- and 3-storey, no new attic Timber boards pressure-impregnated with flame retardant, or lined underneath with non-combustible boards to at least ½-hour fire resistance (lining condition does not apply to residential use); floor area not increased
4-storey, no new attic Underside lined to at least 1-hour fire resistance
New attic, 2-storey Lining to at least ½ hour; attic floor not lower than the top of the front façade window at the last storey; attic up to 50% of the floor below or 50 m², whichever is less, per compartment
New attic, 3- and 4-storey 1-hour lining to all floors; attic set back at least 1.5 m from the inner face of front façade and rear walls; same area limit
Timber escape staircases At least 1-hour compartmentation and flame-retardant impregnation, with exemptions for single-family residential shophouses without a new attic, and conditional relief for some 2-storey non-residential cases
Single escape route Maximum travel distance 13 m in a non-sprinklered building; single-family residential shophouses up to 3 storeys exempt
Amalgamating more than two units Fire shutters or doors at the separating walls between every two units; sprinklers where the amalgamated area exceeds 2,000 m²; at least two independent exits per storey unless otherwise permitted
Alarms Manual alarm acceptable up to 3 storeys and/or up to 2 units; automatic alarm above that

The clause also allows the rear courtyard to be covered up to the second-storey floor level if a protected exit staircase discharges to the back lane, and treats a retained timber-floored building next to a new RC extension as a separate building with independent staircases and 4 m between window openings.8

One procedural point surprises tenants. SCDF’s minor A&A lodgement route, used for small fit-out changes in other buildings, cannot be used for conservation projects: the Schedule to the Fire Safety (Building and Pipeline Fire Safety) Regulations excludes them expressly.15 Fire safety works in a conserved shophouse therefore go through full plan approval by a QP. See our guide to SCDF fire safety approvals for the process and the Fire Safety Certificate.

Change of use

Uses in conserved shophouses follow the Master Plan and URA’s guidelines for each area; residential and institutional uses may be considered on commercial-zoned sites in historic districts, certain trades are not permitted, and new restaurants are not allowed in problematic traffic areas.2 In the core areas of Chinatown, Kampong Glam and Little India, the first storey must have activity-generating uses such as shops.2

Where a change of use needs planning permission, the application is made through GoBusiness with the owner’s consent, costs S$500 (non-refundable) and generally takes 10 working days; URA advises not committing to a tenancy or renovation before its decision.12 Other approvals follow, including SCDF’s fire safety clearance.12 For a timber-floored conserved shophouse, the Fire Code’s bar on public accommodation uses is a threshold question to answer before any lease is signed.8

Before you buy, lease or renovate a conserved shophouse

  • Check the conservation area and whether it is a historic district or secondary settlement; read the applicable guidelines and any site-specific restoration guidelines.
  • Check allowable uses and, in core areas, the first-storey activity-generating use requirement.
  • Ask for previous conservation permissions and as-built drawings; compare with what is on site.
  • Appoint a Registered Architect for any Category 1 work and a PE for the structural investigation.
  • Count storeys and attic area, and identify any amalgamation, for the Fire Code clause 9.9 consequences.
  • Record the original fabric (photographs, measured survey) before any stripping.
  • Agree with the contractor, in writing, that no work on site starts before conservation permission and, where needed, BCA’s permit.
  • Plan party wall protection and monitoring with the neighbours.

How RRD approaches this

RRD carries out A&A and repair works in occupied and older buildings, starting with a site survey and an itemised quotation that separates conservation-sensitive items, such as timber floors, roof tiles and façade elements, from routine works. On conserved properties RRD does not start work on site until the relevant URA permission and any BCA permit are in hand, and recommends that the owner appoint the architect and engineer directly, with no RRD mark-up on their fees.

If works have already gone wrong

If you have bought or leased a shophouse with unapproved alterations, or works started before permission, stop and get a QP’s assessment before doing anything further on site. Under section 12(8) of the Planning Act, where a person is convicted without having been served an enforcement notice first, the competent authority may also order the removal, within 14 days, of property or materials used in connection with the offence.5 Our guide to unauthorised works and regularisation explains the general approach; in a conservation area, the answer often involves reinstatement rather than regularisation, as the Desker Road order shows.7

For a first pass at the approvals your works need, use the Approval Navigator. Our addition and alteration services page explains how we scope works in older buildings, and the glossary defines the terms used here.

Questions people ask

Do I need URA approval to repaint a conserved shophouse?

Yes. URA lists painting façades and murals as Category 3 works, which still need Conservation Permission before any work starts. Category 3 applications can be made by the owner or contractor without a Qualified Person through URA's e-service, cost nothing and are decided in about two weeks. After the works, the applicant submits photographs and URA issues a letter endorsing the completed works. URA may ask for a resubmission under Category 1 or 2 if the works are more extensive than described.

Which parts of a conserved shophouse must be kept?

In URA's historic districts, the guidelines require the roof's original profile, pitch, height, party wall and eaves to be retained, the front façade's windows, doors, fanlights, vents and balconies to be restored, the five-foot way's granite slab borders to be kept, the first 3 m of the load-bearing party wall behind the shopfront to be retained, the airwell to keep its size and location, and timber floors to be retained. In secondary settlements, timber floor retention is encouraged rather than required.

Can I build a rear extension to a conserved shophouse?

It depends on the area. In URA's secondary settlements, owners may conserve the main building and add a new rear extension, with heights set area by area, for example up to 4 storeys in Tanjong Katong and Tiong Bahru, 5 in Joo Chiat and 6 in Jalan Besar and Balestier. Any part rising above the main roof eaves must be set back at least 600 mm clear of the conserved building. A new rear extension is a Category 1 work needing a Registered Architect.

Can I add an attic to a shophouse?

URA allows new roof mezzanines within the building envelope, set back at least 1.5 m from the inner face of the front façade, or 2.5 m if the floor is lower than the top of the uppermost window or fanlight, without dormer windows, generally in timber. SCDF's Fire Code adds conditions for timber-floored shophouses: the attic is limited to 50% of the floor below or 50 m², whichever is less, per compartment, and the floors below need fire-rated lining.

What happened at 32 Desker Road?

URA reported that in a conserved shophouse in the Little India Conservation Area, the first-storey residential front, the rear façade and the entire rear service block were demolished without permission, and the original internal timber staircase was removed. In April 2026 the individual who carried out the works was fined S$250,000 and the owner company S$150,000, and the company must reinstate and restore the building at its own cost. URA said it was the first such prosecution since the 2017 penalty increases.

Does SCDF allow timber floors and staircases to stay?

Yes, with upgrading. Clause 9.9 of the Fire Code 2023 covers shophouses and conservation buildings with timber floors or staircases. Depending on the number of storeys and whether an attic is added, timber floors must be treated with flame retardant or lined underneath with non-combustible boards to a half-hour or one-hour rating, and timber escape staircases generally need at least one-hour compartmentation. Upgrading must cover the whole building; partial upgrading is not allowed.

Can a conserved shophouse be converted to a hostel or co-living use?

Check early, because two regimes apply. URA decides whether the use is allowed under the Master Plan and its conservation area guidelines, through a change-of-use application if needed. Separately, Fire Code clause 9.9 states that buildings within its scope, which are timber-floored or timber-staircased conservation buildings and pre-1969 buildings, may not be changed to public accommodation uses, giving boarding houses, hotels and workers' quarters as examples. A Qualified Person should assess both before you sign a lease.

Can a contractor do conservation works without an architect?

Only Category 3 works, which are minor, localised or repair works such as one-for-one replacement of windows, roof tiles or timber floor boards. Category 1 works must be submitted by a Qualified Person who is a Registered Architect, and Category 2 works by a Registered Architect or Professional Engineer. In the 32 Desker Road case, the owner company also faced a charge of failing to appoint an architect to supervise the works.

Sources

15 sources. Official sources are marked dark. Links were checked when this guide was last updated.

  1. ura.gov.sgUrban Redevelopment Authority — “URA Conservation Principles”. https://www.ura.gov.sg/conservation/about-conservation/ura-conservation-principles/ (accessed Nov 2026) ↩↩
  2. ura.gov.sgUrban Redevelopment Authority — “Planning Parameters and Restoration Guidelines for Historic Districts” (last updated 26 June 2026). https://www.ura.gov.sg/guidelines/conservation/historic-districts/ (accessed Nov 2026) ↩↩↩↩↩↩↩↩↩↩↩↩↩↩↩↩↩↩↩↩↩↩↩↩
  3. ura.gov.sgUrban Redevelopment Authority — “Planning Parameters and Restoration Guidelines for Secondary Settlements” (last updated 1 July 2026). https://www.ura.gov.sg/guidelines/conservation/secondary-settlement/ (accessed Nov 2026) ↩↩↩↩↩↩↩↩↩↩
  4. ura.gov.sgUrban Redevelopment Authority — “Submission Process for Additions and Alterations (A&A) and Category 3 Works”. https://www.ura.gov.sg/Corporate/Guidelines/Conservation/Additions-Alterations (accessed Nov 2026) ↩↩↩↩↩↩↩↩↩↩↩
  5. sso.agc.gov.sgPlanning Act 1998, section 12, current version as at 9 November 2026. Singapore Statutes Online. https://sso.agc.gov.sg/Act/PA1998?ProvIds=pr12- (accessed Nov 2026) ↩↩↩↩
  6. ura.gov.sgUrban Redevelopment Authority — Media release, “Individual and company charged for unauthorised works to conserved building at 32 Desker Road”, 15 July 2025. https://www.ura.gov.sg/news/media/pr25-38/ (accessed Nov 2026) ↩
  7. ura.gov.sgUrban Redevelopment Authority — Media release pr26-30, “Individual and company fined $250,000 and $150,000 respectively for unauthorised works to a conserved shophouse at 32 Desker Road”, 22 April 2026. https://www.ura.gov.sg/news/media/pr26-30/ (accessed Nov 2026) ↩↩↩↩↩↩↩↩↩↩
  8. scdf.gov.sgSingapore Civil Defence Force — Fire Code 2023, Clause 9.9 “Others” (cl. 9.9.1, shophouses and conservation buildings). https://www.scdf.gov.sg/fire-safety-services-listing/fire-code-2023/table-of-content/chapter-9-additional-requirements-for-each-purpose-group/clause-9.9-others (accessed Nov 2026) ↩↩↩↩
  9. sso.agc.gov.sgBuilding Control Regulations 2003, Fourth Schedule (“Minor building works not requiring certificate of accredited checker”), current version as at 9 November 2026. Singapore Statutes Online. https://sso.agc.gov.sg/SL/BCA1989-S666-2003?ProvIds=Sc4- (accessed Nov 2026) ↩
  10. ura.gov.sgUrban Redevelopment Authority and Building and Construction Authority — Circular URA/PB/2023/04-CUDG, “A&A works to or near conserved buildings and maintenance of conserved buildings”, 1 March 2023. https://ura.gov.sg/Corporate/Guidelines/Circulars/dc23-04 (accessed Nov 2026) ↩↩↩↩↩
  11. ura.gov.sgUrban Redevelopment Authority — Circular URA/PB/2026/06-CUDG, “Updated and new Do-It-Right Guides for conserved buildings”, 2 June 2026. https://www.ura.gov.sg/guidelines/circulars/dc26-06/ (accessed Nov 2026) ↩
  12. ura.gov.sgUrban Redevelopment Authority — “Changing the use of your property for business”. https://www.ura.gov.sg/guidelines/property-and-business-owners/business-owners/change-use-of-property-for-business/ (accessed Nov 2026) ↩↩
  13. bca.gov.sgBuilding and Construction Authority — “Structural plan submission”. https://www1.bca.gov.sg/safety-and-standards/applications-and-licenses/structural-plan-submission/ (accessed Nov 2026) ↩
  14. sso.agc.gov.sgBuilding Control Act 1989, section 20 (building offences), current version as at 9 November 2026. Singapore Statutes Online. https://sso.agc.gov.sg/Act/BCA1989?ProvIds=pr20- (accessed Nov 2026) ↩
  15. sso.agc.gov.sgFire Safety (Building and Pipeline Fire Safety) Regulations, the Schedule, paragraph 4(g), current version as at 9 November 2026. Singapore Statutes Online. https://sso.agc.gov.sg/SL/FSA1993-RG1 (accessed Nov 2026) ↩
Cite or link to this guide

Use this guide in a report, a tender or a by-law briefing. Please link to the page so readers get the current version.

RRD Engr & Constr. (2026). A&A Works to Conserved Shophouses in Singapore: URA's 3R Rules, Permits and Fire Safety. RRD Field Guide. Updated 9 November 2026. https://rrd.sg/guides/shophouse-conservation-aa-works/
Report a correction