F&B and Commercial Kitchen Fit-Out Approvals in Singapore: SFA, NEA, PUB, SCDF, EMA and the Landlord

Updated 9 November 202620 min read19 sources, 17 officialBy RRD Engr & Constr, editorial standards
The short answer

A Singapore F&B fit-out needs the use cleared first (URA, HDB or JTC), then SFA's approval of the kitchen layout before renovation, an NEA-compliant exhaust with air cleaning, a PUB-compliant grease trap, SCDF approval for fire safety works such as exhaust ducts, hood suppression and LPG, gas work by EMA-licensed gas service workers, and the landlord's fit-out approval.

A commercial kitchen is the most regulated room in a fit-out. In an office, the approvals are mostly about fire safety and the building. In a kitchen, five more regulators join in: the Singapore Food Agency (SFA) on hygiene and layout, the National Environment Agency (NEA) on exhaust fumes, PUB on grease and sanitary drainage, the Energy Market Authority (EMA) on gas, and SCDF on the fire risk of grease, hoods, ducts and LPG. URA, HDB or JTC sit upstream, deciding whether the unit may be used as an eatery at all.

Each regulator has a different trigger, a different submitter and a different clock. Get the order wrong and the cost is rework: a kitchen built before SFA approves the layout, an exhaust that cannot reach the roof, a grease trap nobody can clean. Get it right and the approvals run in parallel with design.

This guide walks through each approval in the order it bites, explains what each one asks for in physical terms, and ends with a sequence, a timeline and the failures we see most. For the wider A&A picture, start with our master guide to A&A and fit-out approvals.

The approval map

Agency What it controls in an F&B fit-out Who submits When
URA (or HDB, JTC) Whether the unit may be used as a restaurant or eating house Owner, tenant, consultant or QP Before signing the lease
SFA Food shop licence; kitchen layout, sinks, wash hand basins, finishes, storage, exhaust Operator (company) via GoBusiness Layout approved before renovation
NEA Siting of kitchen exhaust; air cleaning; Code of Practice on Environmental Health QP at building plan stage; licensee before operation Design and pre-licensing
PUB Grease traps, sanitary drainage, trade effluent limits QP; licensed plumber for plumbing works Design and before installation
SCDF Fire safety works: exhaust ducts, hood suppression, LPG, sprinklers, escape QP; Registered Inspector at completion Plan approval before works; FSC after
EMA Gas service work and inspection Licensed gas service worker or PE (Mech) During works and annually
BCA Structural works (openings, heavy equipment, plinths) QP (PE) If structure is affected
Landlord, mall or JTC Fit-out drawings, kitchen specification, hoarding, house rules Tenant and its consultants Before works and before opening

Sources: SFA,12 NEA,3 PUB,45 SCDF,678 EMA,910 URA,13 landlords.1718

Step zero: is the unit allowed to be a restaurant?

SFA’s pre-licensing checklist asks for approval from the land agency, such as BCA’s TOP, URA’s change of use or HDB’s usage approval, and advises applicants to make sure the relevant planning permission is obtained before signing the tenancy agreement and investing in renovation.2 Treat that as the first gate.

Commercial buildings

URA states that no planning permission is required to convert between showroom, restaurant and shop in approved commercial premises. The authorisation applies to standalone commercial buildings such as shopping centres, commercial podium blocks, and commercial blocks physically separated from residential uses on sites zoned Commercial, Commercial and Residential, Hotel or White. Party-walled shophouses and shopflats are excluded. Conditions include that the premises was approved for commercial use and counted as commercial GFA, no special planning conditions restrict use, the change is for an individual unit, and licensing requirements are met before the use starts.15

Shophouses and other premises

Outside that authorisation, a change of use generally needs URA’s permission. URA’s processing fee is S$500, applications usually take about 10 working days, and URA advises against committing to a tenancy or renovation before a decision.13 For the first storey of shophouses and selected commercial buildings, URA’s Change of Use Lodgment scheme gives a deemed approval on successful submission for pre-identified uses, at a fee of S$150, subject to 12 conditions, including that the use has not already started and there are no unauthorised works.16 Eligibility for shophouses is checked on URA SPACE.16

URA also publishes road sections where new restaurants are unlikely to be approved, including stretches of Balestier Road, East Coast Road, Joo Chiat Road, MacPherson Road, Upper Serangoon Road, Geylang Road, Bukit Timah Road and Dunearn Road, Sembawang Road, Kampong Glam, the Little India Historic District and Bedok Road.14 And it defines a restaurant by its food: meals prepared for mealtimes. Finger food such as fries, wings or spring rolls does not count as meals, and URA looks at the kitchen, dining space, marketing and decor in deciding whether a “restaurant” is really a bar.14

Before you sign an F&B lease

  • Confirm the approved use of the unit (URA SPACE, the landlord’s records, or a QP’s check) covers a restaurant or eating house.
  • Check whether the unit is on a road section where URA is unlikely to approve new restaurants.
  • Confirm where the kitchen exhaust can discharge (roof, or an acceptable outdoor point) and that the landlord will allow the duct route.
  • Confirm a grease trap connection point exists, or can be built, at a location reachable for cleaning.
  • Confirm whether piped gas is available, or where LPG cylinders could legally go.
  • Get the landlord’s F&B fit-out guidelines and kitchen specification in writing.
  • Check that the kitchen can meet SFA’s minimum area (10 m², or 16 m² with catering).

SFA: the layout comes before the build

How the licence process runs

SFA’s Food Shop Licence costs S$195 and is valid for one year.1 The published process is:

Step What happens SFA’s published timing
Apply via GoBusiness with a layout plan Metric scale and ratio; kitchen equipment and infrastructure (exhausts, sinks, wash basins); boundaries of the refreshment area —
SFA reviews Requests for clarification if the layout is incomplete Within 7 working days
Layout approved SFA notifies the approved application and layout plan Within 7 working days
Renovate and set up Only after approval, according to the submitted layout —
Submit outstanding documents URA change of use or HDB approval, stamped tenancy agreement, cleaning programme, pest control contract Within 2 months of application, or the application closes
Pre-licensing inspection Virtual inspection or photo submission Book virtual slots at least 5 working days ahead
Pay and start operations Payment notification after inspection Pay within 28 days

Source: SFA.1

The practical lesson is in row four. SFA’s steps say that once it has approved your application, you may proceed with renovation according to the submitted layout.1 Kitchens built before approval are the ones that get re-plumbed.

Design requirements that shape the drawings

SFA’s food shop checklist translates into specific physical requirements:2

Requirement What it means on the drawings
Kitchen area At least 10 m², excluding servery; at least 16 m² where the shop does catering
Floor traps In the food preparation area, with the kitchen floor graded to them
Coving Wall-to-floor junctions coved for cleaning
No drainage fittings in food areas No manhole, inspection chamber, waste sump, screen chamber, grease trap or overhead sanitary pipes where food is prepared, cooked, stored or served
Wall linings Glazed tiles or other impervious material to at least 1.5 m in preparation and servery areas
Sinks At least one sink in the preparation area; more for large kitchens
Wash hand basins At least one in the kitchen with soap; if one bowl of a double sink is for hand-washing, two separate taps; sensor taps preferred. At least one in the refreshment area where food is eaten by hand and there are no toilets
Storage Separate storage for workers’ belongings, cleaning materials, ingredients, cutlery and packaging; food stores pest-proof
Fumes Extracted immediately, treated with an air cleaning system, discharged outdoors by hood and flue at or above the roof, facing away and screened from neighbours
Make-up air Sufficient make-up air, with negative pressure maintained when the hood runs
Ducts Non-combustible, smooth, easy to clean, with inspection openings

Source: SFA Food Shop Pre-Licensing Requirements checklist.2

Two people requirements also affect design and staffing: all food workers need Food Safety Course Level 1, and a Food Safety Course Level 3 holder is required for restaurants housed in two or more adjacent units or with a kitchen area over 16 m², among other categories.2

The “no grease trap in food areas” rule is the one that most often collides with the building. If the only drainage point is inside the future kitchen, the grease trap may need to go elsewhere, which affects pipe falls, floor build-up and sometimes slab coring.

NEA: kitchen exhaust and air cleaning

NEA’s Code of Practice on Environmental Health (COPEH), in its December 2025 edition, has a section on ventilation, ducting and kitchen exhaust systems for food shops, split between design requirements for the QP and operating requirements for the licensee.3

At design (building plan) stage, the QP must:3

  • exhaust kitchen fumes above the roof; where that is not practical, choose an outdoor discharge point that does not face adjacent buildings (COPEH illustrates how separation distance is measured);
  • consider the appearance of exhaust outlets, particularly near homes, and provide a suitable aesthetic screen for the duct and outlets;
  • site kitchen exhaust outlets more than 5 m from all edges or structures of cooling towers.

Before operating, the licensee must ensure that all fumes from the cooking range are extracted immediately and treated with an air cleaning system that captures particulate matter, grease, oil and water vapour, with no visible smoke or fumes from the exhaust, and that treated air is discharged above the roof or at an acceptable outdoor point not facing adjacent buildings.3

COPEH also points QPs and licensees to SCDF’s 12-month degreasing requirement and to Singapore Standard SS 553, the code of practice for air-conditioning and mechanical ventilation in buildings, for kitchen ventilation guidance.3

5 m minimum distance between a kitchen exhaust outlet and the edges of a cooling tower under NEA’s COPEH (2025 edition)3

In practice, the air cleaning system is specified by the landlord as much as by the regulator. CapitaLand’s fit-out guidelines for retail units, for example, require the tenant’s hood to comply with NEA’s specifications on acoustic levels, odour and grease controls; first-stage stainless steel grease filters with overlapping edges; a UV-C grease and odour removal system behind the filters; an electronic air cleaner in the exhaust duct within the premises; and the kitchen supply fan interlocked with the gas solenoid valve.17 In JTC premises, an air cleaner unit of up to 35 kg can be installed without JTC plan consent if it meets JTC’s conditions, including treating exhaust air with mufflers and activated carbon before discharge; heavier units and any external flue, chimney, ducting or exhaust hood need PE endorsement.18

PUB: grease traps and sanitary works

The requirement

PUB’s Code of Practice on Sewerage and Sanitary Works (third edition, March 2025) states that all food shops and food processing establishments must have grease traps to keep oil and grease within the limit in the Sewerage and Drainage (Trade Effluent) Regulations. For food shops with no cooking and no dine-in, a grease trap may not be required, subject to PUB’s permission.4 PUB’s grease trap page adds that owners must seek NEA’s and PUB’s approval before installing grease traps.5

Design rules that drive the layout

The Code sets out how the trap fits into the drainage:4

  • Separate system. Waste water from sinks and floor traps in food preparation areas must run through a separate system of waste sumps, discharge pipes and stacks to the grease trap. Toilet waste must not connect to the grease trap.
  • Approved types. PUB’s standard circular grease traps (to its standard drawings), or non-standard traps complying with BS EN 1825 or ASME A112.14.3. PUB treats its standard circular trap PUB/WRN/STD/040C as equivalent to nominal size 4 under EN 1825, and STD/041C as nominal size 2.
  • Access. Standard and non-standard traps must be sited where NEA’s licensed general waste collector can reach them for cleaning.
  • Portable interceptors. Portable grease interceptors inside food shops are allowed only where the premises has URA’s change-of-use approval and it is not feasible to discharge into a standard or non-standard trap.
  • Sizing. Capacity is based on EN 1825 nominal size, using the flow from the appliances and fittings discharging to it; the Code’s Annex E gives a worked example.

Maintenance obligations to design for

PUB recommends cleaning grease traps at least once every two weeks, more often for high grease loads, and says greasy waste should only be collected and disposed of by a licensed general waste collector.5 PUB’s page also recommends flushing the private sewer at least once every six months.5 A trap that can only be reached by lifting kitchen equipment, or by carrying waste through the dining room, will not be cleaned on that schedule.

In JTC premises, a portable grease trap is exempt from JTC plan consent only if it is a portable type (not below ground), its full operating weight is under 400 kg or within the floor’s design load, and it does not obstruct the 1.2 m escape route or firefighting equipment; heavier units need PE (Civil) endorsement.18 Plumbing and sanitary works there are listed for licensed plumbers.18

SCDF: hoods, ducts, suppression and LPG

Kitchen fire safety works need SCDF plan approval before they start. Under section 56 of the Fire Safety Act, carrying out, or permitting or authorising, fire safety works without approved plans carries a maximum fine of S$200,000, two years’ jail, or both; after completion, the Fire Safety Certificate process under section 60 applies.8 Our SCDF fit-out guide covers QPs, Registered Inspectors and the FSC.

Kitchen exhaust (Fire Code clause 7.1.13)

Fire Code requirement Detail
Independent system The cooking-area exhaust in a restaurant, coffee house or similar must be independent of systems serving other parts of the building
Clearance Hood and ducts at least 500 mm from unprotected combustible materials
Discharge Directly to external space, at least 5 m from any air intake opening
Duct outside the kitchen Enclosed in a structure, or constructed to at least the fire rating of the kitchen or the room it passes through, whichever is higher; risers in a protected shaft compartmented from other services
Fire dampers None to be fitted in kitchen exhaust ducts
Ducts outside the building Not within 3 m of unprotected openings (1.5 m if on the same plane), or separated by at least ½-hour fire-resistant construction
LPG Kitchen exhaust duct at least 3 m from unprotected LPG cylinders
Extinguishers Class F portable extinguishers to SS 578
Maintenance Entire duct and hood degreased and cleaned at least once every 12 months by a specialist; records kept

Source: SCDF Fire Code 2023, clause 7.1.13.6

Shared exhaust and hood suppression

Restaurants and small F&B outlets may share a kitchen exhaust system only if they are on the same storey, within an aggregate zone of not more than 2,000 m² and 50 m in length, with an aggregate floor area of not more than 1,000 m²; common ducts have a common fan; the building is sprinklered; the common duct outside the restaurants has at least 1-hour fire resistance; and the exhaust hood is fitted with a wet chemical fire extinguishing system.6 SCDF’s note to QPs says such systems must be of an approved type based on international standards such as NFPA 17A, and owners and operators must be aware of the maintenance regime in those standards.6

SCDF Fire Code 2023, clause 7.1.13

The Code explains why there are no fire dampers in kitchen exhaust ducts and adds that it is “expected that the majority of kitchen hoods will have their own suppression”.6 Wet chemical suppression for kitchen hoods is listed among fixed automatic fire extinguishing systems.19

For a standalone kitchen, check the landlord’s rules as well as the Fire Code: CapitaLand’s guidelines, for instance, require the fire suppression system and its interface with the building’s kitchen exhaust to comply with Singapore Standards.17

LPG cylinders (Fire Code clause 10.1)

Where piped gas is not available, LPG brings its own rules:7

  • All LPG cylinder installations for commercial and industrial buildings must be outdoors and at ground level; indoor cylinders are normally not permitted unless SCDF approves them in special circumstances (clause revised with effect from 3 September 2025).
  • No liquid LPG or LPG vapour above 20 psi (about 138 kPa) may be piped into a building.
  • At least one approved B:C dry chemical extinguisher of at least 9 kg at the installation, with warning signs.
  • Where the kitchen has a fixed fire suppression system, its activation must automatically shut off the LPG supply.
  • Separation distances include at least 3 m from any boundary and fire engine accessway, at least 10 m from any fire hydrant, at least 3 m from a fire exit route of a building with only one exit, at least 1.5 m from openings of a building with more than one exit (or a 2-hour masonry wall), and at least 3 m from the edge of a parking lot.
  • SCDF’s note to QPs states that a shop unit with an LPG installation must have a Fire Safety Certificate.

These distances rule out LPG at many shophouse back lanes and mall service corridors. Check them before choosing a cooking line that depends on gas.

EMA: gas service work

Gas pipes, regulators and appliances are gas service work under the Gas Act, and must be carried out by a gas service worker licensed by EMA. When the Gas Act and Gas (Supply) Regulations requirements took effect in February 2008, EMA stated that anyone who employs or instructs an unlicensed gas service worker to work on gas appliances commits an offence, with a fine of up to S$10,000, imprisonment, or both.9 Ask for the worker’s licence details before work starts and keep a copy with the project records.

EMA requires gas installations in commercial and industrial premises to be inspected annually, by a licensed gas service worker or a Professional Engineer in mechanical engineering.10 EMA has also notified licensed workers that the Gas (Supply) Regulations were amended with effect from 1 September 2025, with references to SS 608, the Singapore Standard code of practice for gas installation.11 Ask your gas contractor which edition and which certification steps apply to your installation, and who will issue the completion certificate.

The landlord and the mall

Statutory approvals are necessary but not sufficient. In a mall, the landlord’s fit-out manual usually controls the details: hoardings, kitchen specifications, working hours, testing and handover.

Examples from CapitaLand’s published guidelines for retail units:17

  • Hoardings must be erected before fitting-out work starts, using the hoarding design obtained from the Tenant Service Centre.
  • Shop-front drawings and material boards must be approved.
  • The tenant supplies, installs and maintains the kitchen hood, exhaust and supply fans to NEA’s Code of Practice, and if it fails to maintain them, the landlord may maintain them and recover the cost.
  • The tenant is responsible for installing and maintaining any grease interceptor.
  • The tenant must take all precautionary measures to contain food smells within its premises.

Expect similar requirements elsewhere, and expect the landlord’s approval to run in parallel with, and sometimes after, statutory approvals. Our guide to fit-out programme delays covers landlord review periods and permitted working hours, and working in live premises covers night works in operating malls.

The exhaust that had nowhere to go (composite scenario)

A café operator signs a lease for a ground-floor unit in a mixed development and orders a full hot kitchen. The design shows a hood and a duct “to roof”. During landlord review, it emerges that the roof route crosses three other tenancies and a residential podium, and the only outdoor discharge point faces the residential block. The operator redesigns to a lighter menu with no open-flame cooking and a recirculating hood, the landlord’s kitchen specification has to be re-approved, and the SFA layout is resubmitted. The equipment ordered for the original menu sits in storage. Rent is running throughout.

The cost chain: duplicated design fees, a second round of approvals, idle equipment, and weeks of rent with no revenue. The check that would have prevented it takes an afternoon: confirm the exhaust discharge route and the landlord’s consent before signing.

Sequencing an F&B fit-out

A practical sequence for F&B and commercial kitchen fit-outs

  1. Confirm the use. Check URA’s approved use, restricted roads and any HDB or JTC use approval before signing the lease.
  2. Collect the landlord’s rules. Fit-out manual, kitchen specification, exhaust and grease trap provisions, gas availability, working hours.
  3. Appoint the design team. Interior designer or architect, M&E engineer, fire safety QP, and a PE (civil/structural) if openings, coring or heavy equipment are involved; see our guide on hacking and coring structural elements.
  4. Fix the kitchen concept. Menu and cooking line decide hood size, exhaust volume, gas load, grease load and electrical load.
  5. Draw the SFA layout and submit. Kitchen area, sinks, wash hand basins, storage, exhaust and refreshment area boundaries.
  6. Submit the statutory packages. SCDF fire safety plans (exhaust duct, suppression, LPG, sprinklers); PUB and NEA approvals for the grease trap; BCA if structural.
  7. Get landlord approval. Submit the drawings the landlord requires; align the hood and air cleaner specification.
  8. Build. Hoarding first; then demolition, services, kitchen exhaust and duct, gas, plumbing and grease trap, finishes, equipment.
  9. Test and certify. Exhaust and air cleaner commissioning, hood suppression test, gas installation certification by the licensed worker, RI inspection and FSC.
  10. SFA pre-licensing inspection and payment. Book the inspection slot early; pay within 28 days of notification.
  11. Operate and maintain. Grease trap cleaning, duct degreasing, gas inspections, suppression servicing, all with records.

The clocks that matter

Item Published timing Source
URA change of use About 10 working days, longer if incomplete or other agencies are consulted URA13
URA change of use lodgment (qualifying shophouse units) Deemed approved on successful submission URA16
SFA application review and layout approval Within 7 working days each, for complete applications SFA1
SFA outstanding documents Within 2 months of application SFA1
SFA virtual pre-licensing inspection Book at least 5 working days ahead SFA1
SFA licence payment Within 28 days of notification SFA1
BCA permit for structural works 7 days BCA12

Timings are the agencies’ published targets for complete submissions. Clarifications, resubmissions and landlord reviews add to them. If you are weighing a cheaper contractor against programme risk, our delay risk simulator shows how a few weeks of slippage compares with the saving. Remember too that a kitchen you build is usually a kitchen you must remove at the end of the lease; see our reinstatement guide.

Common failures, and how to avoid them

  1. Lease before use check. The unit cannot lawfully be a restaurant, or only as a lighter use. Check URA’s records and restricted roads first.1314
  2. Exhaust route not secured. No roof access, or the only outdoor discharge point faces another building. Confirm the route and landlord consent before design.3
  3. Grease trap in the wrong place. Inside the food area, or unreachable for the waste collector. Plan the drainage route and access at layout stage.24
  4. Toilets connected to the grease trap. PUB prohibits it; separate the systems from the start.4
  5. Kitchen built before SFA approval. Sinks, wash hand basins and storage move after construction. Submit the layout first.1
  6. Duct fire rating forgotten. The duct leaves the kitchen through ceilings and corridors without fire-rated enclosure, or with a fire damper fitted by habit. Brief the M&E contractor on clause 7.1.13.6
  7. LPG with no legal location. Cylinders cannot meet the separation distances. Decide gas versus induction early.7
  8. Unlicensed gas work. Gas pipes run by a general plumber. Use an EMA-licensed gas service worker and keep the certificates.9
  9. Landlord’s hood specification missed. UV-C, electronic air cleaners and interlocks added late at extra cost. Read the landlord’s kitchen specification before pricing.17
  10. No maintenance plan. Grease traps and ducts are designed without access for the cleaning the regulations require.56

How RRD approaches this

On F&B fit-outs, RRD starts with a site survey that checks the exhaust route, drainage and grease trap location, gas availability and the landlord’s kitchen specification before we quote. Our itemised quotation separates kitchen exhaust and air cleaning, fire-rated ductwork, hood suppression, grease trap works and gas works as cost-risk items, and we coordinate the licensed gas service worker, licensed plumber and QPs within one programme. Works are supervised, with a joint inspection and handover of test records.

Owner's checklist for a commercial kitchen fit-out

  • Use confirmed with URA (or HDB or JTC) before the lease is signed.
  • Landlord’s fit-out manual and kitchen specification in hand.
  • SFA layout approved before renovation starts.
  • Exhaust discharge point agreed, air cleaning system specified, outlet more than 5 m from any cooling tower.
  • Grease trap type, size and location agreed with the QP; toilets separated; cleaning access confirmed; NEA and PUB approval obtained.
  • SCDF plans approved for exhaust duct, suppression, LPG and sprinkler changes; FSC obtained before opening.
  • Gas works by an EMA-licensed gas service worker, with certification; annual inspection diarised.
  • Maintenance contracts set up for grease trap cleaning, duct degreasing and suppression servicing.
  • Records filed: approvals, test certificates, cleaning logs.

Use our approval navigator for a first view of which approvals your works need, and see choosing a contractor for checking licences before you appoint one.

Questions people ask

Can I start renovating my restaurant before SFA approves the layout?

It is risky and SFA's process does not envisage it. SFA reviews the application and layout plan within 7 working days of a complete application and then notifies you of the approved layout. Its published steps say that once SFA has approved the application, you may proceed with renovation and set-up according to the submitted layout. Building first and submitting later invites rework if SFA requires changes to sinks, wash hand basins, exhaust or storage.

Do I need URA approval to open a restaurant?

It depends on the premises. URA says no planning permission is needed to convert between shop, showroom and restaurant in approved commercial premises such as shopping centres and commercial podiums, subject to conditions. Shophouses usually need a change-of-use application (S$500, about 10 working days) or, for qualifying first-storey shophouse units, a lodgment. URA is unlikely to approve new restaurants on certain listed road sections, such as Joo Chiat Road and East Coast Road.

Does every F&B outlet need a grease trap?

PUB's Code of Practice on Sewerage and Sanitary Works requires grease traps for all food shops and food processing establishments. Where there is no cooking and no dine-in, a grease trap may not be required, but only with PUB's permission. Portable grease interceptors inside food shops are allowed only where the premises has URA change-of-use approval and discharging into a standard or non-standard grease trap is not feasible.

Is a wet chemical fire suppression system mandatory for a kitchen hood?

The Fire Code expressly requires a wet chemical fire extinguishing system on the exhaust hood where restaurants share a kitchen exhaust system, and requires approved types based on standards such as NFPA 17A. The Code's rationale also expects most kitchen hoods to have their own suppression. Many landlords require hood suppression in their fit-out rules regardless. Confirm with your fire safety Qualified Person and the landlord's guidelines early.

Can I keep LPG cylinders inside my kitchen?

Generally no. The Fire Code requires all LPG cylinder installations for commercial and industrial buildings to be located outdoors and at ground level. Indoor cylinders are normally not permitted unless SCDF approves them in special circumstances. Outdoor installations must also meet separation distances, for example at least 3 m from any boundary and fire engine accessway and at least 10 m from any fire hydrant.

Who can install gas piping and appliances in a commercial kitchen?

Gas service work must be done by a gas service worker licensed by the Energy Market Authority (EMA). When the Gas Act requirements took effect in 2008, EMA stated that anyone who employs or instructs an unlicensed gas service worker commits an offence, with a fine of up to S$10,000, imprisonment, or both. EMA also requires commercial and industrial gas installations to be inspected annually by a licensed gas service worker or a Professional Engineer (Mechanical).

How often must kitchen exhaust ducts be cleaned?

The Fire Code requires the entire kitchen exhaust duct and hood, inside and out, to be degreased and cleaned at least once every 12 months by a specialist, with records kept by the owner or operator for the authorities. NEA's Code of Practice on Environmental Health refers to the same requirement. Many landlords set shorter intervals in their fit-out or house rules.

What are the most common reasons F&B fit-outs are delayed?

The usual causes are signing a lease before confirming the use is allowed, an exhaust route that cannot reach the roof or an acceptable discharge point, a grease trap location that cannot be reached for cleaning, SFA layout changes after construction has started, late landlord approval of kitchen drawings, and LPG or gas works that do not meet the Fire Code separation distances. Each is avoidable with early checks.

Sources

19 sources. Official sources are marked dark. Links were checked when this guide was last updated.

  1. sfa.gov.sgSingapore Food Agency — “Application Process & Fees for Licence / Permit for Food Retail” (Food Shop Licence steps, fees and timelines). https://www.sfa.gov.sg/food-retail/licensing-permits/food-shop-licence (accessed Nov 2026) ↩↩↩↩↩↩↩↩↩
  2. sfa.gov.sgSingapore Food Agency — “Food Shop Pre-Licensing Requirements” self-checklist. https://www.sfa.gov.sg/docs/default-source/food-retail/self-checklist_foodshop.pdf (accessed Nov 2026) ↩↩↩↩↩↩
  3. nea.gov.sgNational Environment Agency — “Code of Practice on Environmental Health” (2025 edition, December 2025), section 3 “Ventilation, ducting and kitchen exhaust systems for food shop”. https://www.nea.gov.sg/docs/default-source/resource/practices-/copeh-2025.pdf (accessed Nov 2026) ↩↩↩↩↩↩↩
  4. pub.gov.sgPUB, Singapore’s National Water Agency — “Code of Practice on Sewerage and Sanitary Works” (3rd edition, March 2025), sections 4.1(b) and 4.2.2 and Annex E. https://www.pub.gov.sg/-/media/PUB/PDF/Code-of-Practice-on-Sewerage-and-Sanitary-Works-3rd-Edition–Mar-2025.pdf (accessed Nov 2026) ↩↩↩↩↩
  5. pub.gov.sgPUB, Singapore’s National Water Agency — “Grease Trap”. https://www.pub.gov.sg/Professionals/Requirements/Used-Water/Grease-Trap (accessed Nov 2026) ↩↩↩↩↩
  6. scdf.gov.sgSingapore Civil Defence Force — Fire Code 2023, Clause 7.1 “Air-conditioning and mechanical ventilation systems”, 7.1.13 “Exhaust system for kitchen”, with rationale and note to QP. https://www.scdf.gov.sg/fire-safety-services-listing/fire-code-2023/table-of-content/chapter-7-mechanical-ventilation-smoke-control-systems/clause-7.1-air-conditioning-and-mechanical-ventilation-systems (accessed Nov 2026) ↩↩↩↩↩↩↩
  7. scdf.gov.sgSingapore Civil Defence Force — Fire Code 2023, Clause 10.1 “Liquefied petroleum gas (LPG) cylinder installations”, including amendment history. https://www.scdf.gov.sg/fire-safety-services-listing/fire-code-2023/table-of-content/chapter-10-requirements-for-special-installations/clause-10.1-liquefied-petroleum-gas-lpg-cylinder-installations (accessed Nov 2026) ↩↩↩
  8. lawplayer.comFire Safety Act 1993, sections 55, 56 and 60, compiled text. https://lawplayer.com/sg/act/FSA1993 (accessed Nov 2026) ↩↩
  9. ema.gov.sgEnergy Market Authority — media release, “New Requirements under the Gas Act and Gas (Supply) Regulations (with effect from 14 February 2008)”. https://ema.gov.sg/news-events/news/media-releases/2008/new-requirements-under-the-gas-act-and-gas-supply-regulations-with-effect-from-14-february-2008 (accessed Nov 2026, content read via search excerpt) ↩↩↩
  10. ema.gov.sgEnergy Market Authority — FAQ, “What are the types of gas installation that need to be inspected?”. https://www.ema.gov.sg/resources/faqs/gas/gas-installation-and-inspection/what-are-the-types-of-gas-installation-that-need-to-be-inspected (accessed Nov 2026, content read via search excerpt) ↩↩
  11. elise.ema.gov.sgEnergy Market Authority — Circular RD/G02/2025 to licensed gas service workers on amendments to the Gas (Supply) Regulations effective 1 September 2025. https://elise.ema.gov.sg/eguides/Circular_RD_G02_2025_ELISE.pdf (accessed Nov 2026, content read via search excerpt) ↩
  12. bca.gov.sgBuilding and Construction Authority — “Permit for structural works”. https://www1.bca.gov.sg/safety-and-standards/applications-and-licenses/permit-for-structural-works/ (accessed Nov 2026) ↩
  13. ura.gov.sgUrban Redevelopment Authority — “Changing the use of your property for business”. https://www.ura.gov.sg/guidelines/property-and-business-owners/business-owners/change-use-of-property-for-business/ (accessed Nov 2026) ↩↩↩↩
  14. ura.gov.sgUrban Redevelopment Authority — “Authorisation conditions for conversions between shop, showroom and restaurant in commercial premises”. https://www.ura.gov.sg/guidelines/property-and-business-owners/business-owners/change-use-of-property-for-business/related/authorised-conditions-shop/ (accessed Nov 2026) ↩
  15. ura.gov.sgUrban Redevelopment Authority — “Change of Use Lodgment”. https://www.ura.gov.sg/guidelines/property-and-business-owners/business-owners/change-use-lodgment/ (accessed Nov 2026) ↩↩↩
  16. capitaland.comCapitaLand — “Fitting Out Work Checklist and Guidelines (For CapitaSky)”, April 2025, including retail-unit sections on hoardings, shop fronts and kitchen supply and exhaust. https://www.capitaland.com/content/dam/capitaland-sites/singapore/lease/commercial-spaces/welcomekit/5%20Fitting%20Out%20Checklist%20and%20Guidelines%20%28For%20CSky%29_Apr2025.pdf (accessed Nov 2026) ↩↩↩↩↩
  17. jtc.gov.sgJTC Corporation — “Space Submission Handbook” (PCP-WI-09), Lists A and B. https://www.jtc.gov.sg/-/media/project/jtc-cx/corpweb/assets/get-help/space-submission-handbook.pdf (accessed Nov 2026) ↩↩↩↩
  18. scdf.gov.sgSingapore Civil Defence Force — Fire Code 2023, Clause 6.5 “Fixed automatic fire extinguishing systems”. https://www.scdf.gov.sg/fire-safety-services-listing/fire-code-2023/table-of-content/chapter-6-firefighting-systems/clause-6.5-fixed-automatic-fire-extinguishing-systems (accessed Nov 2026) ↩
Cite or link to this guide

Use this guide in a report, a tender or a by-law briefing. Please link to the page so readers get the current version.

RRD Engr & Constr. (2026). F&B and Commercial Kitchen Fit-Out Approvals in Singapore: SFA, NEA, PUB, SCDF, EMA and the Landlord. RRD Field Guide. Updated 9 November 2026. https://rrd.sg/guides/fnb-kitchen-fit-out-approvals/