How long do approvals for a typical office fit-out take?

Answer

There is no single answer because each agency runs its own clock. Published BCA service standards are 7 working days for a complete structural plan without an Accredited Checker and 7 working days for the structural works permit; URA's change-of-use decisions generally take 10 working days; SCDF responds to TFP and FSC applications within 3 working days. Landlord reviews, resubmissions, design changes and the time taken to prepare a complete submission usually dominate, so build float into the programme.

From the RRD Field Guide, checked against the sources cited in A&A and Fit-Out Approvals in Singapore: Who Approves What, and When. General information, not advice for your project.

The fuller picture

Most Singapore fit-outs and A&A works need several separate clearances: BCA for structural and non-exempt building works, SCDF for anything touching fire safety (plan approval, or a $90 minor A&A lodgement for small works), URA for change of use or external changes, the landlord, JTC or MCST, plus licensed electrical workers, licensed plumbers and gas workers for services. A Qualified Person coordinates the statutory submissions.

Read the full guide

More questions on this topic