How much does adjudication cost?

Answer

Under the Singapore Mediation Centre's fee schedule from 1 August 2025, the application fee is S$654 including GST. The adjudicator charges S$327 per hour including GST, up to S$2,616 per day, and the total adjudicator fee cannot exceed 10% of the claimed amount. The claimant pays a deposit of S$2,616 for claims up to S$24,000, or 10% of the claimed amount up to S$33,600 for larger claims.

From the RRD Field Guide, checked against the sources cited in Security of Payment Act (SOPA) Singapore: Progress Payments and Adjudication for Owners and Contractors. General information, not advice for your project.

The fuller picture

Singapore's Security of Payment Act gives anyone who does construction work or supplies goods or services under a written contract a statutory right to progress payment. The claimant serves a payment claim; the respondent must reply with a payment response within the contract period (maximum 21 days) or 14 days; unresolved disputes go to fast adjudication at the Singapore Mediation Centre, enforceable as a court judgment.

Read the full guide

More questions on this topic