Are LDs capped?

Answer

Only if the contract says so. Many contracts cap total LDs at a percentage of the contract sum, but there is no statutory cap. A cap protects the contractor and makes the job easier to price; it also means that once the cap is reached, the owner bears further delay cost. Read the cap together with any clause that preserves or excludes general damages, such as PSSCOC clause 16.3.

From the RRD Field Guide, checked against the sources cited in Liquidated Damages and Extension of Time in Singapore: An Owner's and Contractor's Guide. General information, not advice for your project.

The fuller picture

In Singapore, a liquidated damages clause is enforceable if it is a genuine pre-estimate of loss and not a penalty; the Court of Appeal in Denka Advantech (2020) kept the traditional Dunlop test and declined the UK Cavendish approach. LDs only run for delay the contractor is responsible for, so the contract needs a clear extension-of-time clause, notice rules and a certification step.